Home / Transcripts / Core Scientific, Inc. (CORZ) · May 7, 2025

Core Scientific, Inc. (CORZ) Earnings Call Transcript

May 7, 2025

NASDAQ US Information Technology IT Services earnings

Earnings Call Speaker Segments

Jon Charbonneau executive
#1

Hello everyone, and thanks for joining Core Scientific's earnings call for the first quarter of 2025. Right now, everyone is in listen-only mode. Once management finishes speaking, we'll open things up for a Q&A session. I want to remind you that some of what we discuss today includes forward-looking statements as defined under the Safe Harbor provisions of the Private Securities Litigation Reform Act of 1995. Such forward-looking statements cover, without limitation, any statement that isn't a historical or current fact and that predicts or points to upcoming events or trends, forecasts, performance, or achievements, and might include terms like believe, anticipate, expect, estimate, intend, project, plan, or similar words or phrases. These forward-looking statements rest on present expectations, forecasts, and assumptions involving risks and uncertainties that could lead actual results to differ materially; to learn more about these risks and uncertainties, we suggest you look at the risk factors covered in the company's annual report on Form 10-K submitted to the Securities and Exchange Commission, along with a special note about forward-looking statements found in the company's current report on Form 8-K filed today, plus the earnings release and slide presentation included in it. You can find today's presentation on our website, corescientific.com, under the Event and Presentations section. What's shared on this conference call is accurate only as of today, May 7, 2025. The company isn't obligated to update any statements made today to reflect events or circumstances that happen afterward. Here with me today from Core Scientific are our CEO, Adam Sullivan; our Chief Operating Officer, Matt Brown; and our Chief Financial Officer, Jim Nygaard. We'll now turn things over to Adam for his remarks.

Adam Sullivan executive
#2

I appreciate everyone being here today. Before we get into the quarter itself, I'd like to pull back a bit and discuss our current position, both as a business and within our sector. Artificial intelligence is fueling one of the largest infrastructure transformations witnessed in many decades; this isn't merely a matter of rising demand — it involves an entirely new category of infrastructure built specifically for workloads that are high-performance and high-density; we think we're at the very start of this shift, particularly given that a large number of our enterprise customers are only now starting to formulate their AI roadmaps, and already we can see initial indicators of substantial demand. As those roadmaps move into execution, Core Scientific occupies a strong position to serve as a leading provider of the infrastructure that will support it. There's an obvious imbalance in the marketplace right now. Conventional data center operators are finding it difficult to satisfy the density specifications that AI workloads require. That gap between what's available and what's needed has created a distinctive opening in which we stand as the sole pure-play infrastructure firm listed on public markets dedicated specifically to high-density co-location. That singular focus provides us a genuine chance to lead and to secure a meaningful portion of a market that is still in its early stages. Central to our approach is the relationship we have with CoreWeave. The agreements we hold with CoreWeave are fundamental, not merely due to their scale, but owing to the way they've been structured. CoreWeave is financing nearly the entire capital outlay for these deployments; this keeps leverage on our balance sheet modest, particularly relative to competitors, and it affords us the ability to deploy debt strategically as an instrument for financing future expansion and generating long-term shareholder value. To put it plainly, what we're constructing goes beyond capacity; we're establishing the groundwork for what lies ahead for this organization and for the expansion of Accelerated Compute. And although Core represents a major initial move, that's exactly what it is — the opening move in a lengthy journey. With that said, I'll begin with a brief update on our 3 strategic priorities, after which I'll pass things to Matt for a construction update, and then Jim will walk through the financials. We'll wrap up today with Q&A; though before proceeding further, I'd like to formally welcome Jim Nygaard, our Chief Financial Officer. Jim carries extensive expertise in M&A, capital markets and corporate finance. He has already delivered a strong impact, and I'm thrilled to have him alongside us as we grow this business. Let me begin with our first strategic priority, diversifying our customer base; there have been plenty of headlines lately asking whether appetite for AI infrastructure is beginning to weaken; yet if you actually hear from the data center providers themselves, Core Scientific among them, the narrative looks quite different. Universally, we're witnessing robust, enduring demand for high-density infrastructure. What customers are telling us is unambiguous, and the pipeline keeps growing. To be clear, we have yet to sign a new customer, but our sales pipeline is getting bigger. This group spans both hyperscale players and sizable enterprise accounts, a balanced blend overall, and right now we're in active talks with several of them. The caliber and magnitude of what's coming our way gives us real encouragement. When it comes to hyperscale interest, it might swing around from one account to another, but it keeps pacing along the same lines as the prior quarter. Even more striking is the demand starting to surface among big enterprises; these companies are only now starting to deploy AI applications, and it's dawning on them that the infrastructure they already have can't deliver the performance they need; sitting in our pipeline at present are a number of non-hyperscale deals, spanning customers from 50 megawatts up to 100 megawatts. Those represent sizable rollouts, and the return profile attached to them is appealing. It sends a clear message that demand from large enterprises has the potential to matter significantly and play a strategic role for our company. As ever, we aim to match the right customers with the right sites. And as I look toward the remainder of this year plus 2026, my confidence has never been higher that we can assemble a customer mix that is more varied, better balanced, and more closely tied to our strategic goals over the long haul. The objective hasn't changed: Core should account for under 50% of billable capacity once we reach the close of 2028. Our number two strategic priority involves carrying out the CoreWeave agreements, and I'd like to pause and recognize the sheer amount of headway we've achieved there. During the last quarter, we moved the needle considerably on building out 570 megawatts of total billable capacity for CoreWeave, which further proves how swiftly we can move, execute, and supply high-density colocation infrastructure at scale. A particular highlight is our Denton site, which has rapidly turned into a key anchor of this work. We anticipate handing over the initial tranche of 8 megawatts of billable capacity within this month, with more deliveries at Denton lined up across the year, among them a further 40 megawatts coming by the close of this quarter. Worth noting, based on public statements we understand Open-AI is collaborating with CoreWeave and Denton. Once construction is complete, it will house one of North America's biggest GPU clusters — potentially the biggest anywhere on earth. At full build, the location will amount to roughly 260 megawatts of buildable capacity. For context, we turned the first shovel in January, and in only about four months we've made meaningful headway. It stands as a powerful proof point of our capacity to execute rapidly and at scale, with before-and-after images featured in our refreshed investor presentation. Looking forward, my confidence is even greater than it was merely two months back that we'll reach our milestones: 250 megawatts by the close of this year, counting Austin, and 590 megawatts by early 2027. Before I update you on our third priority for this year, allow me a moment to discuss our contract with CoreWeave, which remains a foundational pillar underpinning our growth strategy. Plenty of people have shown interest in the way this agreement is put together, and rightly so. This stands as one of the biggest GPU infrastructure deals currently seen in the marketplace, and beyond that, it's structured in a way that sets us up for growth that scales efficiently in terms of capital; the arrangement is a take-or-pay agreement at a fixed price. What that means is CoreWeave carries a contractual obligation to pay for whatever capacity we bring online, no matter how much of it gets used. On top of that, the deal is structured so execution risk is shared, which maintains financial and operational alignment between both sides when it comes to hitting the important milestones. Looking at it from the capital side, CoreWeave is putting up essentially the entire CapEx tied to these deployments. The sole direct capital expenditure we bear under this contract is the $104 million tied to the 70-megawatt expansion that we told you about on our previous earnings call; because of that structure, our capital load drops considerably, our balance sheet leverage stays similar to that of our peers, and we gain room to deploy debt more strategically going forward as we grow. In our view, this method distinguishes us from others and lays out an obvious route toward building value over the long term. The hardware placed at our locations backs CoreWeave's contractual obligations regarding both the CapEx and the recurring payments called for in the contracts. As we mutually agreed, we filed UCC-one financing statements that reflect our contractual security interest in the assets sitting at our sites.

Adam Sullivan executive
#3

That being said, CoreWeave represents a key strategic partner for us, and the relationship keeps demonstrating robust momentum, which recent customer announcements make clear. Additionally, we think we gain from the essential part CoreWeave plays in influencing what accelerated compute looks like going forward, along with our robust commercial ties that benefit both sides across the long haul. Growing our data center capacity stands as our third strategic priority, achieved both through organic means and via focused M&A. When it comes to organic growth, we maintain confidence in our capacity to introduce roughly 300 megawatts of billable capacity throughout our current sites by the close of 2027. Going forward, we likewise keep believing substantial chances exist to expand into fresh geographies, and we aim for another 400 megawatts of buildable capacity via new site development during the coming three years. Our approach to picking sites keeps emphasizing places where we can obtain suitable power at a suitable price and align it with the suitable kind of customer demand. Regarding M&A, Jim will elaborate shortly on how we consider expansions via acquisition from a strategic standpoint. We concentrate on possibilities that fit with our fundamental strengths, present attractive economics and lend themselves to efficient scaling. Taken together, these initiatives lay the groundwork for capital-efficient growth over the long term and strengthen our standing as a top supplier of high-density infrastructure for the GPU cloud. Prior to handing things to Matt, I'd like to pause and acknowledge Denise Sterling, who lately left her post as our Chief Financial Officer. Denise assumed the CFO position during one of the most pivotal junctures in Core Scientific's past. She was instrumental in steadying the company, steering us through our prosperous restructuring and setting it up for growth over the long term. Denise assembled a superb finance team, took us through an intricate transformation and assisted in obtaining the resources required to carry out our long-term vision. She additionally was central to facilitating a seamless and effective shift to Jim as our incoming CFO. Thus, representing the whole Core Scientific team and community, thank you, Denise, for everything you've contributed to Core Scientific. Having said that, I'll pass it to Matt Brown, our Chief Operating Officer, for a thorough update regarding our construction progress.

Matt Brown executive
#4

Thanks, Adam. I'd like to begin by backing up what you said. Our team has made tremendous strides over the last few months, and I couldn't be happier, as we keep moving forward on building out 570 megawatts of billable capacity for CoreWeave at four sites: Denton, Dalton, Marble and Muskogee. Once finished, these locations will add up to an infrastructure investment surpassing $5 billion. As of today, we've locked in every piece of equipment required to hit our 2025 delivery targets, and we're strongly shielded from the effects of the tariff shifts we've seen worldwide recently. This quarter, my remarks will center on our Denton, Texas facility — a 64-acre campus set to provide 260 megawatts of billable power capacity spread over eight buildings, which together amount to 350,000 square feet of high-density colocation space. Every building has been engineered and purpose-built to handle next-generation computing platforms that stretch the limits of performance and efficiency. The scale and execution here are remarkable. As of now, manpower at Denton has grown to more than 600 contractors; we've recorded over 187,000 man-hours, poured in excess of 2,800 cubic yards of concrete and put in place more than 30 miles of conduit. I want to express my thanks to our trade partners and the Core Scientific delivery team for not only hitting their targets, but surpassing them. I'd also like to recognize the City of Denton and Denton Municipal Electric, whose partnerships have been crucial in keeping this project advancing at pace. This month, we are handing over the first tranche of 8 megawatts of billable capacity to CoreWeave, and we'll keep delivering capacity steadily through the remainder of the year, including another 40 megawatts by the close of the second quarter. All told, Denton should account for a significant share of the 250 megawatts we intend to deliver for CoreWeave in 2025. To wrap up, I have full confidence in our capacity to deliver 250 megawatts to CoreWeave before this year ends and the complete 590 megawatts by early 2027. With that, I'll pass things over to our CFO, Jim Nygaard.

Jim Nygaard executive
#5

Thank you, Matt. Before diving in, I want to express just how genuinely thrilled I am to be part of this and to come aboard with the team at what is such a defining juncture in this company's journey. The thing that drew me toward this role was the impressive transformation that's already in motion — moving away from Bitcoin mining toward the datacenter business, and doing so with genuine momentum. The CoreWeave agreements give us a distinctive and deeply strategic base for making that shift. Through these deals, we get recurring revenue over the long term while putting up very little capital ourselves — a combination you almost never come across in this sector. We find ourselves in a period unlike anything the wider data center industry has seen for years. Demand powered by AI is radically reworking what infrastructure needs to look like globally, and this organization sits in an exceptionally strong position to take the lead through that change. Naturally, the market carries plenty of noise, with stories that frequently diverge from what's actually happening on the ground. Even so, I share the view held by many of you that eventually the market will turn its attention back to fundamentals: execution that's disciplined, growth that's both sustainable and profitable, and value creation over the long haul. That's precisely where we're focused, and that's the thing that will distinguish us. What lies ahead represents a massive opportunity, and I'm eager to help our team seize it to the fullest. Let me start by offering my thinking on capital allocation in the areas that will be essential to how we generate shareholder value over the long term. As we grow, every dollar we put to work has to line up with our strategy, boost our operational flexibility, and underpin growth that is sustainable and profitable. Our priorities for allocating capital are straightforward. We'll put money into developing and expanding capacity at sites we already have, at new locations, and by way of strategic M&A — concentrating on deals capable of widening our customer base and reinforcing our strengths as a top-tier developer of next-generation, high-density colocation infrastructure. Such investments don't just advance our strategic aim of bringing CoreWeave below 50% of billable capacity by the close of 2028; in our judgment, they're also the finest route to maximizing shareholder value over the long term. That being said, we hold a demanding standard when it comes to deploying capital. Although we don't set rigid return thresholds, each project undergoes thorough assessment on the basis of its strategic merit — considerations such as location, power availability, site attributes, potential customer demand, and the financial contribution it makes to the wider portfolio. At the close of the first quarter, we held roughly $780 million in liquidity, encompassing cash, cash equivalents and bitcoin. On top of that, the way the CoreWeave contracts are structured — with them funding the overwhelming majority of the related CapEx — lets us make efficient use of those agreements. Going forward, we intend to employ conventional project financing structures of the kind that are commonly relied upon throughout the data center sector. And as time passes, we're of the view that our net debt to adjusted EBITDA leverage can and ought to move toward roughly 4 times, in line with peers in this industry. Now, a quick note on Bitcoin. As our financial profile keeps shifting alongside our move into colocation infrastructure, we stay committed to refining our mining operations so we can satisfy our long-term utility commitments throughout the transition. When Q1 came to a close, we had slightly below 1,000 Bitcoin. By April, that figure stood at a bit under 1,200 Bitcoin. Today we're in a position to hedge that exposure efficiently, which lets us control downside risk and still keep upside potential. So to sum up: we're seeing growing scale, better profitability, stronger stability, and a customer base that's more diversified. Over time, we think these things will help bring down our cost of capital and support a structurally higher valuation framework for the company. Let's move now to the first quarter results. Revenue totaled $79.5 million for the quarter, a 16% drop quarter over quarter, while adjusted EBITDA came in at negative $6.1 million. The quarter-over-quarter revenue decrease was mostly the result of mining disconnections and relocations, since we keep converting sites to support high-density colocation. To be more specific, we earned 719 Bitcoin in Q1 versus 974 in Q4. We closed the quarter with roughly 156,000 self-mining units in our fleet, and during the period our self-mining energized hash rate averaged 18.1x hash. That said, because we're continuing to prioritize our high-density colocation business, we've decided not to publish monthly bitcoin production reports anymore. Rather, we'll focus on giving more consistent updates about CoreWeave-related construction progress, which in our view is more useful for investors, as it better reflects where the business is strategically headed. Turning to CapEx, it came in at just under $90 million for the first quarter, with over half of that funded by CoreWeave, consistent with contract terms. Beyond the amounts CoreWeave was responsible for, we funded a modest amount of CapEx tied to acquiring land and prefunding costs for colocation sites not related to CoreWeave. Lastly, as we've told you before, we had previously signed a purchase agreement with Block for 3-nanometer chips, and during the first quarter we made the second scheduled installment payment. We still expect the remaining installments under the Block agreement to be paid during 2025 and early 2026. Looking ahead, we don't expect first quarter CapEx to be representative of future quarters. Our pro forma fully diluted share count as of May 1 was about 502 million shares. For 2025, we're currently modeling a statutory effective tax rate of 22%. We also hold more than $380 million in net operating loss carryforwards, which will lower future cash taxes. With that, I'll open the call up for questions.

Joe Flynn analyst
#6

Hello, and thank you for taking my question. Since we've observed lease comps from other quarters, we were curious whether your lease includes any credit enhancements — for instance, a guarantee provided by CoreWeave's end customer, or step-in rights should a default occur. It just appears, as you noted regarding the opening at Denton, that the scale of infrastructure will ultimately matter quite a bit for their build out, and would they really want to risk one party losing access to it? Thanks.

Adam Sullivan executive
#7

Yes, thank you for asking, Joe. As I believe we showed on page 12 of our investor report, we laid out certain of the key terms tied to the contract. Regarding your prior question about any pass-throughs, that is a matter that would need to be talked about directly with CoreWeave. The one point I'd make, though, is that we're genuinely thrilled about the CoreWeave contracts we've signed to date, and as a commercial counterparty to Core Scientific, we hold them in high regard.

Joe Flynn analyst
#8

Great, thank you. Then, I'm hoping you might be able to give us additional detail regarding the initial colocation CapEx for colocation and what the possible plans are for the remaining 100 megawatts in North Dakota that could be leased out.

Matt Brown executive
#9

Yes, Matt here. I can offer a bit more detail on that. Basically, what we were up to in Grand Forks was, in a sense, getting that site ready for an eventual full build-out and expansion. So, buying around 70 acres of land situated directly next to the site that's already operating, so that we can, in a sense, connect to the power infrastructure already present at that site for a future high-density co-location facility.

Joe Flynn analyst
#10

Great, thanks.

Brett Knoblauch analyst
#11

Hey, everyone. Appreciate you taking my question. This might be one for Adam. You sounded especially optimistic about the big enterprise opportunity, not just the Tier 1 hyperscalers. So I'm wondering, what's shifted in the last couple of months that's caused those conversations to pick up?

Adam Sullivan executive
#12

Yeah, absolutely. Before we get into large enterprise, one thing I'd note about hyperscaler demand: it comes with major ebbs and flows. Looking at things overall, the shape of their demand stays pretty steady; however, when you zoom in on any single company, you get ups and downs. We've all clearly read the updates regarding several of the hyperscalers. Compared with wrapping up final contract terms in large enterprise, those schedules are quite different; yet during the last half-year, we've watched the large enterprise channel keep growing. That's happening because really big enterprises keep working out their AI use cases and figuring out what they truly require when it comes to where things sit and how big they need to be. As I noted before, there's considerable demand accumulated in that pipeline across the channel—coming not just from smaller clients but from major ones too. We're observing requests anywhere between 50 and 100 megawatts, and that's got us quite enthusiastic. We also think big enterprise players might serve as anchor tenants at certain new sites we're currently assessing.

Brett Knoblauch analyst
#13

Thanks. Turning to the new location topic, should we expect an announcement on that during this year? Would you make that announcement roughly alongside a possible new tenant, or would you first pick up extra capacity ahead of a prospective tenant, with that capacity then going live? Also, as a related question, do you believe that adding the 8 megawatts, followed by the 40 megawatts, in this month and this quarter, will provide many of the large prospective tenants with something worth reviewing and perhaps assist in getting some of those agreements finalized?

Adam Sullivan executive
#14

Yes, definitely. Let me address the first portion concerning new sites. At present we are actively in the market pursuing quite a few new sites, and those are sites we anticipate announcing together with new customer developments; therefore, we hope that across 2025 we can issue several announcements on this front, since we are right now assessing multiple jurisdictions to keep expanding into. As for the second portion of your question, I will pass it to Matt Brown.

Matt Brown executive
#15

And would you mind repeating the second part of your question?

Joe Flynn analyst
#16

Yeah, could you perhaps discuss how significant it actually is to get some capacity up and running so that prospective tenants can see it — for instance, your capability to deliver Blackwell's — and how that would make them feel more assured about signing an agreement? Do you believe they are holding off for that?

Adam Sullivan executive
#17

Yeah. No, I believe that is an excellent observation. So, to some extent, I would say yes. What I mean is, we are definitely focused on simply getting things done and demonstrating that we possess the know-how to carry out these sizable, highly intricate initiatives. Therefore, as we keep adding that capacity, we anticipate being able to secure even greater trust within the marketplace.

Darren Aftahi analyst
#18

Yeah. I appreciate you answering these, and nice work on the momentum. Adam, regarding what you said on enterprise compared with hyperscaler — I'm just a bit curious, I realize nothing's been signed yet, but when you consider a big enterprise next to a hyperscaler, do you have any feel for the sort of timeline for actually getting a lease inked, meaning do you figure an enterprise would take less time to wrap that up? And is there any sort of preference internally for one over the other?

Adam Sullivan executive
#19

Yeah, that's a really good question. Thanks Darren. When it comes to large enterprises, the path to reaching final contract terms is certainly quicker than what happens on the hyperscale side. There's a built-in pull toward hyperscale when you think about their creditworthiness more broadly; but the large enterprises we're reviewing right now are, I believe, $75 billion market cap and above and show a creditworthiness we consider quite acceptable, and the return profile on these is greater than hyperscale deals too. So, when we weigh possible multitenant build-outs down the road, large enterprises might serve as major anchor tenants for those new sites, which would let us kick off development in new geographies and start putting up new sites. And to return to something asked earlier, Denton is a flagship facility we're building now, and we believe it will be a genuinely large standout facility, and there are reasons our peers keep mentioning that site. It will truly be a flagship site in the Dallas-Fort Worth area.

Darren Aftahi analyst
#20

Great. And then perhaps just one additional item. Regarding how the 8 megawatts come in, followed by the 40 additional before the quarter closes, could you perhaps assist us in grasping how we ought to perhaps build that into our models? Does more of it land toward the back half of the second quarter? Thanks.

Adam Sullivan executive
#21

What I'd say is that these sites will keep being brought online across the coming few months, and both the 8 megawatts and the 40 megawatts are going to be brought online. As that happens, there's a day by day element regarding when those will turn on; and so, it's difficult for us to state right now the precise day or hour that those will turn on, Darren.

Darren Aftahi analyst
#22

That's reasonable. I appreciate it.

Nick Giles analyst
#23

Thanks, operator. Hello, everyone, and good afternoon. To start, I'd like to congratulate Denise for her tenure at Core, and also congratulate you, Jim, for taking on this role. For my first question: today you've restated the construction schedule, and you noted that monthly progress reports on construction will now be given. So which project milestones ought we to anticipate, to really get a clear sense that work is proceeding according to plan, and that the schedule you've given us is still holding?

Matt Brown executive
#24

Yes, that's a terrific question. What I'd say is that the reports you'll get from us are going to add further detail with every passing month, and as we make our way through the calendar year, showing precisely what we're aiming at for ready for service dates along with important project milestones. So when we finish items such as commissioning, or when commissioning dates draw near and handover dates draw near, we'll begin discussing those items, and also reaching important milestones at several of the other sites besides Denton.

Nick Giles analyst
#25

Appreciate that, Matt.

John Todaro analyst
#26

Hi everyone, thank you for letting me ask, and congratulations on the quarter — I really like the new presentation. In my view it set out a great deal of the material and addressed many questions. To start, Adam, you said you have greater confidence about reaching milestones today than you did just two months back. That appears true given the 8 megawatts that are coming online; yet did anything shift on the construction side or elsewhere that produced that added confidence and helped make some of those milestones achievable?

Adam Sullivan executive
#27

I appreciate that, John. When you move nearer to the commissioning dates for the first building, your confidence grows that you can keep delivering on subsequent buildings at that location. So this is what we are witnessing, clearly above all, at Denton, though we will also keep witnessing it at sites to come. As we move nearer to the commissioning of the first building, we will gain far more clarity regarding the schedule and the delivery of later buildings at that location; therefore, this initial 8-megawatt building represents a significant milestone for the Denton campus; and soon after it will come a 40-megawatt building, and we anticipate buildings continuing to come online throughout this year at that facility too.

John Todaro analyst
#28

Understood, that's clear. For my follow-up, I was hoping to get a bit more detail regarding that shift in the CapEx setup; from what I gather, the core we've asked one brought up, $300 million was released from escrow. I just want to confirm I've got that right. Could you shed any light on precisely which element of the CapEx arrangement ended up being modified?

Jim Nygaard executive
#29

Happy to address that. CoreWeave's obligation to provide funding for the CapEx remains unchanged. What did change was the method by which that funding was carried out. We managed to do away with the escrow structure altogether, and it became more streamlined on their books too. So to put it plainly, whenever we owe a payment on a PO to a contractor or need to fulfill our commitments, those payments won't go out until CoreWeave's money comes in. Our contract specifies exactly that. In effect, we're mirroring that same setup when it comes to what we're exposed to. Nothing meaningful about our CapEx arrangement shifted because of this modification.

John Todaro analyst
#30

Understood, got it. Thanks, everyone. Appreciate it.

Adam Sullivan executive
#31

Yeah, thank you.

Analyst analyst
#32

Hey, guys. Logan here, filling in for George. Appreciate you taking the questions. Adam, could you discuss what's behind your confidence regarding those 300 megawatts you plan to secure from the sites you already have today? Perhaps also an update on where things stand in that process as you talk with utilities, regulators, and so on?

Adam Sullivan executive
#33

Yeah, absolutely; and thanks for the question, Logan. Yeah, I mean, where we stand right now is we have an exceptionally tight relationship with the utilities at every one of our locations. It's something we built when we were, I'll say, the odd one out in this industry, when we're a Bitcoin miner among the utilities; and those relationships got forged via deep communication with every one of those utilities as a bitcoin mining business; and so, as we've progressed and demonstrated advancement at the sites in our development toward conversion into colocation facilities. They've been impressed by what we've developed. They're seeing us keep growing at these locations and they're enthusiastic about that too; and right now we're in talks with those utilities regarding how those future contracts will be structured, what the overall power potential is. And given where we stand with talks today, we feel confident in our ability to obtain and that's 300 megawatts of billable capacity. So, we think we can reach roughly four fifty megawatts of gross capacity across 2025 and 2026 from our current utilities, which we're excited about. We'll have the chance to keep expanding those locations and possibly bring in new customers too.

Analyst analyst
#34

Understood, and perhaps a brief additional question. I mean, you've discussed how distinctive the CoreWeave arrangement is, and you said a bit before that the return profile with those enterprise clients could be somewhat stronger. I'm simply curious whether you can discuss how we ought to consider possible terms on fresh deals, whether enterprise or hyperscalers, will differ from that CoreWeave arrangement, or does it shift monthly? Any update on that would be welcome.

Adam Sullivan executive
#35

Yes, definitely. The CoreWeave contract won't be duplicated in the market. The differentiation I'd draw as we assess fresh contracts moving forward is that there are truly 2 elements to working out a contract, whether it's with a hyperscaler or a sizable enterprise. Those 2 elements are NRC and MRC. The NRC is basically what that initial payment goes toward for the CapEx, and the MRC is that charge recurring each month. So, when we assess deals, there's a mutual concession, whether you're getting and what the magnitude is of a non-recurring charge compared to that monthly recurring charge. So, we're presently assessing several distinct deal structures that we're having talks about with clients; and I'd say we're enthusiastic about the return profiles the big enterprises offer since they do possess the ability, given their scale and their size, that they're requiring now to serve as an anchor tenant for us to launch a new site location. So, we will keep assessing deals moving forward, and we're enthusiastic about the ever-expanding pipeline in the big enterprise channel.

Analyst analyst
#36

Understood. Thanks.

Analyst analyst
#37

Hi, Will, sitting in for Joe here. Appreciate you taking my question. Adam, this might be a big-picture one from me. Would you be willing to discuss whether customer conversations have shifted quarter over quarter because of tariffs and fresh market dynamics? Then perhaps how the speed of those talks has evolved? Also, are hyperscalers reacting differently than enterprises? Thanks.

Adam Sullivan executive
#38

Sure. Thanks for asking. Regarding your first point, tariffs are an intriguing shift in what's happening across this industry at present. Our current view is that new construction will require somewhat higher CapEx, and we think that keeps pushing lease rates upward in the near term, at least until the tariff effect on new data center projects becomes clearer. We've begun to see a bit of that show up in lease negotiations, yet we're confident that, thanks to our top-tier supply chain group, our rates will be comparable though somewhat pricier — roughly 5% to 10% pricier on the CapEx side — and after that the whole industry will see a matching rise in lease rates; now, as for your question about how quickly discussions are moving, I'd say big enterprises have sped up regarding the demand they have. At first, I think they were assessing what size and which locations they wanted to target. Yet that has gotten far more precise as time passed, once they solidified their growth plans; and I think large enterprise will keep being a major growth driver for big, high-density colocation facilities down the road. That's the reason we brought it up in our prerecorded remarks. And we think it will be a meaningful channel for us moving forward.

Analyst analyst
#39

That's quite useful, thank you.

Kevin Dede analyst
#40

Hello, Adam, and Jim, good to have you. Perhaps to start, on Matt's behalf, I realize Core Scientific put in tremendous effort alongside CoreWeave to assist them through building out the infrastructure, specifically networking, and so on. And I'm curious, since there are now other companies trading publicly, whether some of that intellectual property you helped create is entirely proprietary, or whether it carries over automatically to CoreWeave's other vendors?

Adam Sullivan executive
#41

Yes. My view of it is that CoreWeave and Core Scientific share an extremely tightly coupled connection, spanning both design engineering and delivery. Although it's essentially Core Scientific's teams constructing the infrastructure and taking the lead on design — we're definitely doing so in very close collaboration with CoreWeave's engineering team and infrastructure delivery team — therefore, whatever IT comes out of that would definitely be shared between the two organizations, and we would regard that as a competitive edge in the market. Nobody to date has attempted a GPU build at the scale of Denton specifically. Consequently, we believe we'll pick up many of those lessons earliest, we'll be ahead of the competition, and we can apply those learning experiences toward upcoming projects, which we believe will only broaden our competitive advantage in the market.

Kevin Dede analyst
#42

Alright. When it comes to M&A, what can you tell us about the kinds of targets you'd pursue and the criteria for acquisitions, given this gap Core Scientific is positioned to fill by delivering high density while legacy data center operators remain stuck with builds that have low rack power? How do we make sense of that?

Matt Brown executive
#43

Appreciate that question, Kev. The way we're looking at it at this moment is that we're assessing opportunities within the new generation of data center capacity. What we're really after is potential targets that offer a chance for us to keep extending our lead when it comes to how much infrastructure is being built out across this next generation of compute. That said, we'll also still pursue acquiring certain asset types that might bring us some diversity in workload as well. Our belief is that as time goes on and we grow Core Scientific into a genuine data center platform, we'll end up with a mix of more traditional GPU or CPU capacity, though our real emphasis is on continuing to expand and build out our GPU deployment platform, which we think will rank among the largest in the United States, and we'll aim to keep extending our lead in that space.

Kevin Dede analyst
#44

So Adam, what I'm taking away from this is basically that you'll be hunting for locations and construction projects matching the criteria you have right now, rather than moving backward along the technology development chain?

Matt Brown executive
#45

What I'd say is that we're considering a solid combination of locations plus businesses holding agreements with top firms in this sector.

Kevin Dede analyst
#46

That sounds fair, sir. I truly appreciate your time on my questions. Great job on the progress.

Paul Golding analyst
#47

Thanks so much. I have one quick housekeeping question regarding digital asset mining. Previously, I think you mentioned that hosting capacity for digital asset mining would be shut down by year-end. Since some revenue from that came in this quarter, I just wanted to confirm the plan is still the same. Then, my main question is about long lead time items. Regarding what you said about 2025 objectives, and the equipment being purchased to achieve them. I'd like to ask about 2026 and what we're hearing regarding extended procurement timelines for step-down infrastructure and other parts, especially electrical equipment — I just wanted to check on how that's coming along. Thanks.

Adam Sullivan executive
#48

Yes, thanks, Paul. On the digital asset mining hosting side, we do still have a legacy contract, and it will keep rolling off throughout 2025. So for your modeling, that's the expectation — it will continue to decline across 2025. As for your second question, about items with long lead times needed to hit our 2026 objectives, I'll pass it to Matt Brown.

Matt Brown executive
#49

Okay, so here's how I'd frame it. When it comes to 2025, the equipment is fully accounted for — we've got it all locked down already, and the majority is physically on location, whether that's in storage facilities near the active projects or directly at the job sites. From an equipment perspective, then, 2025 is completely set. As for 2026, we've got solid visibility into both what will be available and what it'll cost. A significant share of that gear for the first half of ’26 has already been purchased, and certain pieces will begin arriving in the back half of this year, since those are tied to projects that will carry over and kick off during 2026. That said, this topic does bring in tariffs along with whether equipment can be obtained, and thanks to the strong ties we've built with our vendors, I'd say our visibility into supply is genuinely excellent, and at this point we aren't especially worried about being unable to receive equipment or hit our OJ dates — or any buy dates — needed to fulfill our delivery targets.

Paul Golding analyst
#50

Matt, I really appreciate that context.

Bill Papanastasiou analyst
#51

Hello, everyone, and thanks for taking my questions this evening. Adam, I think during the call it was said that multiple pipeline opportunities fall in the 50-megawatt to 100-megawatt range. Could you speak to who those prospective customers are? Also, how would you characterize their potential to grow past 100 megawatts, or perhaps 150 megawatts? Might we see scaling capability similar to what CoreWeave has shown?

Adam Sullivan executive
#52

Bill, thank you — that's an excellent question. To be clear, the reference to 50 megawatts up to 100 megawatts applied to the large enterprise segment. And my answer would be yes, without question. In some situations, big companies want megawatts distributed over several locations. So it's entirely possible we'd have a customer taking 50 megawatts at a single site while continuing to expand with Core Scientific across many years. That's genuinely what we aim to create as we keep developing this business into a genuine data center platform. We're focused on forming lasting partnerships with our customers and on growing together with them as they pursue their own further build-outs. We're quite sure we can secure those deals, and throughout 2025 we'll keep letting the market know which ones we manage to land.

Bill Papanastasiou analyst
#53

That's helpful detail. Now turning to the 3-nanometer block ASICs, could you provide an update regarding the delivery schedule and make clear if those units have been affected at all by the tariffs that came up recently, or are they likewise relatively shielded?

Adam Sullivan executive
#54

Right, I'd begin by restating our position from the last earnings call: our belief, which remains unchanged as of today, is that these machines will arrive at some point during the second half of 2025. As for tariffs, our expectation is that we'll be protected on the whole from their effects; one thing worth noting is that our agreement carries a fixed price for taking delivery of those machines. So our hope is that throughout 2025 we can keep the market informed about how far along we are in getting these new block units deployed, which is something we're extremely enthusiastic about right now.

Bill Papanastasiou analyst
#55

Thanks.

Analyst analyst
#56

Hello, Adam — Matt here — and Jim, welcome aboard. I appreciate you taking the question. Could the substantial share of core weave business be putting off other hyperscale clients who want to sign leases with Core Scientific? That's my first item. And separately, regarding Grand Forks in particular, could you say more about the scale of enterprise interest you're seeing from prospective HBC tenants at that location? Thanks.

Adam Sullivan executive
#57

Yes. On whether hyperscalers get swayed by CoreWeave's share, my view is that it works in precisely the reverse way compared with what I said during one of the earliest questions earlier today: our delivery and execution, I believe, will simply build confidence as the year progresses. Also, at this moment we are likely among the few data center operators set to bring 250 megawatts online within one calendar year — capacity that amounts to over 100,000 GB200 units. So our execution, I think, will demonstrate itself, and that will earn trust among hyperscalers.

Analyst analyst
#58

Thanks. Could you also address the second — apologies, please continue.

Matt Brown executive
#59

No problem, apologies. Regarding the second portion of what you asked, about the Grand Forks location: at present, at that Grand Forks location, from our perspective, we were in the process of obtaining 70 acres of property for high-density colocation growth there, and that is definitely included in what we intend to do. Curiosity about that location has come from enterprises, content providers, and a few of the hyperscalers. Therefore, I believe we have observed interest from essentially every segment when it comes to that site.

Analyst analyst
#60

Thanks, Matt.

Jon Charbonneau executive
#61

Thanks. We really appreciate you being on today's call, and don't forget to cast your vote for your shares. Should you run into any issues, simply contact our IR email, which you can find on the website. Thanks so much.

Operator operator
#62

Thanks. That brings today's call to a close. We appreciate everyone taking part. At this point, feel free to hang up, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Core Scientific, Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Core Scientific, Inc. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.