Core Scientific, Inc. (CORZ) Earnings Call Transcript
March 2, 2026
Earnings Call Speaker Segments
Alright, thanks. Good afternoon, everyone, and thank you for joining us for Core Scientific's call covering the fourth quarter and full year 2025 results. Before we get started, I should point out that anything said during this call that isn't a historical fact counts as a forward-looking statement under the Private Securities Litigation Reform Act of 1995, and it reflects what we currently expect. Terms like anticipates, estimates, expects, intends, and believes, along with similar words and expressions, signal forward-looking statements; such statements carry risks and uncertainties that might cause actual results to differ substantially; to learn more about these risks and uncertainties, we urge you to look at the risk factors covered in the company's reports on Form 10-K, 10-Q, and 8-K filed today with the Securities and Exchange Commission, plus the press release and slide presentation included with those filings. Any forward-looking statements we make today are only valid as of today, and we take on no obligation to update any such statement for events or circumstances that happen after today. You can find today's presentation on our website, investors.corescientific.com. The information in this conference call is accurate as of today, March 2, 2026. Here with me today from Core Scientific are our CEO, Adam Sullivan; our Chief Operating Officer, Matt Brown; and our Chief Financial Officer, Jim Nygaard; after management's remarks, we'll hold a question-and-answer session. We'll now begin with remarks from Adam.
Good afternoon, everyone, and thanks for being here. During our update call on October 30, we set out 4 specific deliverables for today's earnings call. To begin, we anticipate signing at least one new customer — a significant move toward broadening our customer base. Next, we intend to sign a single new power expansion contract at a site where we already operate. Third, we expected to sign a new agreement covering a large amount of land and power; and fourth, we plan to make an announcement regarding financing. Those items are the foundation for our future growth: expanding contracted revenue, increasing our power optionality, widening our footprint, and funding growth responsibly and repeatably. Before discussing those 4 priorities, let's turn to execution. These build-outs are enormously complex, and our progress on the CoreWeave build-out has been incredible, even with market challenges and shifting criteria for running the newest generation of GPUs. Adapting to changes in real time demands the deep bench that Core Scientific possesses. Matt will walk through the details, but here are the facts. As of this week, we'll have energized roughly 350 megawatts of capacity, and close to 200 megawatts of that is currently billing. That places us well — the halfway point of the CORE contract. By energized, we mean power has been delivered and is generally within 90 days of billing. How long it takes to move from energization to the start of billing naturally varies depending on the site and what the customer requires. Now consider this context. During the prior year, the megawatts we energized matched those of our closest publicly traded peers put together. We were building and delivering while they were still signing their first AI contracts. And going forward, to keep things simple and consistent, we'll report megawatts once billing begins; in this business, the market will always talk about demand. Investors should keep their attention on what truly matters here: execution. Schedules will always shift; it's easy at mile 2 of a marathon to claim you're on pace, but projects this large and complex reveal who can genuinely execute; we've demonstrated that we can build, turn on capacity at scale, and deliver for our customers. This leads directly into our pipeline. As this industry matures and weighs opportunities against more stringent criteria, we're confident we satisfy those boxes through proven execution and genuine site readiness; and we're disciplined. We only sign contracts we know we can deliver on time and done right; that discipline is how we're building a durable, long-standing company, one defined by execution and known for being a great partner to our customers. That's what we set out to do, and it's exactly what we're doing today; and over time, that's what will separate us from the rest of the industry and position us to be a market leader for years to come. Let me begin with an update on the item at the top of our priority list that everyone can see, a new customer contract. As of this call, no such agreement has been signed, and that is not a result we are happy with. Even so, demand exists, and 2 sites are currently tied up in short exclusivity arrangements. Our expectation is that this process will lead to colocation leasing agreements before long. Compared with a few months back, our funnel has grown both larger and wider, and talks are actively underway with hyperscalers, neoclouds and large enterprises. What we are facing is a matter of timing, not of demand. During the period we were bound by the merger agreement, hyperscalers were simply unwilling to engage with us. After the termination, those discussions picked back up, and we have advanced considerably. A deal at this scale cannot be done in a single meeting. It involves a demanding, multi-step process. Hyperscalers do take longer to contract with, yet the route to project financing and delivery is often simpler. The key point is that we are engaged, working through the process and vying for the right long-term opportunities. Turning to neoclouds, demand across the industry is substantial; even so, for such deals to make sense for us, a strong balance sheet must sit behind the contract. Typically, that requires a hyperscaler, chip manufacturer or another investment-grade guarantee. Establishing that structure calls for due diligence on both the neocloud and the investment-grade guarantee, which brings in more coordination and more steps; and since these guarantees are new to many parties, negotiating and finalizing them takes time. That is part of why, we believe, fewer neocloud deals have been announced industry-wide lately; we will not compromise on counterparty strength, because that protection is what matters across the life of the contract. Second, we stated that we intended to add new power at an existing site, and we did so in Dalton, Georgia. Dalton will grow to 450 megawatts of total gross power capacity, which includes 120 megawatts of uncommitted leasable customer capacity. Our Dalton site sits strategically roughly 90 miles from Atlanta, right in the middle of an extremely attractive demand corridor. We have spent more than a year working toward this expansion with local stakeholders. And to back it, we have obtained an additional 175 acres of land. This is what execution looks like, long-term planning, deep coordination and strong partnerships with the utilities and the local community. Late last year, we also raised leasable customer capacity in Pecos, Texas to 200 megawatts, an area that has drawn considerable interest for high-density compute. With that demand in mind, we are proceeding with converting Pecos from Bitcoin mining to colocation. Pecos sits in the Goldilocks zone for customer signing, which means we have secured a general contractor, locked in long lead equipment and conversion work is underway with a time line to RFS within 12 months. That puts Pecos inside a time frame customers are actively trying to solve for right now. If we zoom out, the approach we're taking hasn't changed. Over the coming 3 years, we anticipate that all megawatts we hold will go toward colocation. Next, we followed through by executing a fresh agreement covering land and power as part of our contract to pick up a significant new location in Hunt County, Texas. That property spans roughly 265 acres, which we believe is capable of accommodating about 430 megawatts of gross power capacity, equivalent to 285 megawatts of leaseable capacity for customers. Situated roughly 45 miles from Dallas, this spot sits within a colocation market that ranks among the quickest expanding. We anticipate closing this deal before Q1 wraps up. And crucially, this location offers a straightforward interconnection route. The ERCOT energization timeline got the green light during 2024, with electricity slated to start flowing in 2027 and scale up across 2029. You've likewise come across the news coverage regarding ERCOT. From where we stand, having greater discipline and transparency in that framework is a positive thing. It cuts down on speculation and benefits firms possessing genuine sites, genuine plans and the capability to deliver. Our view is that this renders our 2 leaseable sites in Texas — Hunt along with Pecos — even more appealing in the marketplace, thanks to the certainty surrounding their capacity to perform. As things stand right now, our pipeline holds about 1.5 gigawatts of leaseable capacity for customers. That figure isn't some speculative bet. It isn't padded with load studies; it encompasses solely genuine opportunities with an obvious route to development, current power already under contract, fresh sites such as Hunt and additional power available incrementally at both new and current sites. Power is essential, and we maintain discipline regarding it. Yet across the wider market, power frequently gets viewed as the limiting factor, and our sense is that this can be exaggerated. In reality, the larger obstacles tend to be procuring long lead equipment and assembling seasoned general contractors along with subcontractors. The truth is plain. We currently possess more power within our pipeline than we could possibly construct throughout the upcoming several years. And fourth, regarding financing. Our balance sheet stays solid, and we hold a range of financing avenues that Jim will walk through shortly. Turning to 2026, our goals are clear-cut: broaden our customer mix and deliver on the CoreWeave contract. We remain concentrated on execution, measured growth and following through on our commitments. I'll hand things over now to Matt for a refreshed construction overview.
Appreciate that, Adam. Across 2025, our teams carried out their work with real drive and accuracy. We kept our attention on the things that count most — our customers, and constructing the infrastructure that fuels the Fourth Industrial Revolution. Our purpose is straightforward: engineer and provide AI factories at scale, built specifically for accelerated computing. Each quarter brought fresh architecture cycles, additional GPUs, greater power densities and emerging cooling approaches, which generated tremendous opportunity along with genuine complexity; we kept operations running through record weather occurrences spanning several regions, adjusted designs on the fly to accommodate the latest GPU platforms, and used insights gained from earlier deployments to bring infrastructure delivery into closer alignment with shifting customer requirements. every obstacle to sharpen the system. Every build improved the thinking machine. Let me now pull back and put into context how much the team achieved during the past 14 months. Together with our design build partners, we commenced work on 5 AI factories backing our 590-megawatt commitment to CoreWeave, 2 brownfield expansions — Denton, Texas and Marble, North Carolina; 3 greenfield campuses — Muskogee, Oklahoma, Dalton Phase 1 and Phase 2 in Georgia. During 2025, these 5 sites accounted for 1 million square feet of data center shell, close to $2 billion of installed infrastructure assets, over 5 million labor hours backed by an average of 3,300 workers on site and greater than $5 billion in total project investment. This ranks among the most significant AI expansions taking place anywhere globally. Let's begin with Texas. Our 262-megawatt 400,000 square foot Denton campus achieved outstanding progress. By the close of Q4, Denton had delivered 67 billable megawatts across 3 buildings, with approximately half the campus energized. As of today, Denton North is completely operational, running production GPU workloads, and accounts for 90 billable megawatts. At Denton South, the initial 40-megawatt data hall has started building; and as of today, our subsequent 41-megawatt data hall will kick off the energization process. The rest of the buildings at the South campus stay on schedule for Q2 energization with the whole campus finished by midyear. Denton by itself presently accounts for roughly 130 billable megawatts, actively powering over 50,000 Grace Blackwell GPUs. In North Carolina, our 65-megawatt 250,000 square foot Marble data center reached full site energization during 2025. 2 of the 3 data halls were handed over by the close of the fourth quarter, amounting to 36 billable megawatts supporting around 15,000 Grace Blackwell GPUs. The third and last data hall is presently in commissioning and should be delivered during the second quarter. Our customer is actively speeding up GPU deployments at the site this week. Moving on, at our Muskogee, Oklahoma campus, Phase 1 — a 70-megawatt, 138,000 square foot data center — has finished vertical construction and is now completely energized and has moved into commissioning, staying on schedule for full delivery in the second quarter. Last, our Dalton, Georgia campus Phase 1, a 30-megawatt 52,000 square foot data center, has likewise finished vertical construction and is now completely energized. Commissioning is moving forward and getting the facility ready for high-density liquid-cooled AI systems, with full delivery anticipated in the second quarter. Now, moving to Dalton Phase 2 — that's a 145-megawatt, 250,000 square foot data center — vertical construction is happening right now, and we're aiming for full delivery in early 2027. This site is going to be the last AI factory that backs CoreWeave's 590-megawatt commitment. As we look forward, I'd like to lay out our development and go-to-market approach, which we call Operation Forward Observer. The idea here is simple: push development forward at several sites all the way through the first commissioned data hall, while at the same time locking in long lead equipment so we can scale quickly. When we bring sites to that advanced point before a contract is even signed, it puts us in front of our competitors and helps us win colocation agreements; customers get a strong sense of certainty about RFS time lines — both for that first delivery and for smooth expansion into later data halls. Carrying out this plan sharpens our competitive edge and gives us more room to negotiate favorable terms with a wide base of creditworthy customers. Let me take you through our initial forward observer sites. The first is the Hunt campus, a planned 285 leasable megawatt AI campus in a strategic spot near the Dallas-Fort Worth market. Our development teams are busy with predevelopment work so we can deliver the entire 285 megawatts across several buildings, with the first delivery presently slated for the second half of 2027. Next up, our Pecos campus — a planned 200 leasable megawatt campus out in West Texas. Development teams there are mobilized and moving forward on early civil work and engineering for Phase 1, which is built to deliver 185 megawatts of leasable capacity across multiple data halls, with initial delivery anticipated to start in early 2027. At Dalton, Phase 3 will be a greenfield data center of roughly 250,000 square feet, planned to deliver 120 megawatts of leasable capacity across multiple data halls, with first delivery targeted for the second half of 2027. Development teams are mobilized there too, working through early civil work and engineering. Lastly, construction has begun on the first phase of our 30-megawatt leasable data center in Auburn, Alabama. That site is still on track to hit its first 10 megawatts in the second half of 2026. Auburn is designed as a Tier 3 facility with dense connectivity, positioned to serve multi-tenant enterprise AI customers. Engineering, preconstruction and permitting are finished, and all long lead equipment has arrived on site. To wrap up, the takeaway is simple; we've built a repeatable execution engine for AI infrastructure at scale. We've delivered more than 185 meaningful billable capacity, moved multiple campuses through energization and commissioning, hit 350 megawatts energized and grown our development pipeline by 600 leasable megawatts to support the next wave of accelerated computing, all while continuing to improve how we design, build and onboard customers. As we enter 2026, our priorities are clear: stay aligned with customer GPU deliveries, remain ahead of the technology curve and keep turning megawatts into production-ready AI factories. We're proud of what the team accomplished in 2025 and even more focused on the path ahead in 2026. With that, I'll hand it over to Jim.
Thank you, Matt. For our company, 2025 represented a year of transition. The bulk of what we earned still came from Bitcoin mining, but our main attention went toward growing the colocation segment, which included continuing to build out capacity for CoreWeave. Meanwhile, mining keeps helping fund the business as we move through this shift. Even though colocation revenue during 2025 stayed modest, we anticipate hitting a key inflection point over the next few months, when billing starts on added megawatts, lifting colocation revenue to a point where it covers operating costs and also fuels meaningful margin expansion ahead. On the Bitcoin mining side, our emphasis stays on optimizing operations, and we will keep mining in order to cover contractual power costs. We closed out the year with a very solid balance sheet, holding total liquidity of roughly $530 million. We also took advantage of market conditions to sell slightly more than 1,900 Bitcoin for about $175 million in January, at prices substantially above where the market sits now. Currently, we hold fewer than 1,000 Bitcoin and anticipate staying opportunistic moving forward. Regarding a wider approach to capital formation, a full set of financing choices is open to us, and we will keep assessing them over the months and quarters ahead as our requirements change, among them sizable options at the corporate level as well as the up to $4 billion we are able to raise against our contracted capacity with CoreWeave once stabilized. Going forward, these capital sources will pay for investments in our pipeline sites. At those sites, we will likewise employ project-based financing structures featuring a 60% to 85% advance rate on build costs, subject to customer credit quality and site characteristics. Lastly, I want to speak to the historical restatement described in the 10-K we filed today. At the start of 2025, we made a change in audit firms, bringing in KPMG to replace Markham. During the course of KPMG's usual audit procedures, along with our own ongoing review of how old mining locations are being repurposed for colocation, we identified a mistake in our prior accounting that goes back to 2024. This involved specific property, plant and equipment that had been torn down as part of those conversion projects. The way we had been accounting for it meant that demolition expenses got capitalized while the existing carrying values stayed on the books. It was ultimately determined that those values and costs ought to have been written off during certain earlier periods. To fix this error, we have submitted amended statements. For today's filings, please check the SEC or the Core Scientific Investor Relations website. Just to be clear, revenue, adjusted EBITDA, and net cash flow were all unaffected. You'll notice a material weakness disclosed in our filings covering the next 4 quarters, but I want to assure you we've already put the right measures in place to tighten how we handle nonroutine accounting items moving forward. Looking toward what's next, our enthusiasm about where this business is headed could not be greater. Demand for high-performance infrastructure continues to be robust, and Core Scientific is positioned to seize that opening through scale, disciplined operations, and a well-defined strategic vision. What we're aiming to build is a data center platform that truly stands out, supported by the expertise and financial strength required to compete directly against the very best. We have a seasoned, dedicated group, a pipeline that keeps expanding, and a dedication to allocating capital with discipline. Because of this, we feel we are more than ready for the year ahead — we're also built in a way that should generate substantial value over the long haul for those who hold our stock. Having said that, I'll hand things over to the operator so we can take your questions.
Adam, you mentioned 2 deals that are, I suppose, currently being discussed. Could you share additional specifics regarding how large those deals could potentially be, and perhaps which locations they'd involve? And I'm also just somewhat interested in your selectivity concerning the kinds of tenants that you're — possible tenants you'd be open to speaking with at this point, and how significant credit quality is in that?
Sure, glad to do so, and I appreciate the question, John. It helps to revisit October 30, when we initially came out of the merger agreement's termination. Among the things we discussed was that we had been in engagement with a variety of counterparties, neoclouds among them. Yet back then, hyperscaler customers along with specific large investment-grade counterparties weren't prepared to talk with us at that point, which made sense. What we've done with our sales pipeline over these last 4 months is we've kept going, or we've re-engaged with those large counterparties, which has been wonderful to witness. We are in conversations involving several of them and several of our sites. And one point I'd add is that as of today, we have 500 megawatts tied up in exclusivity arrangements with a large investment-grade counterparty, and we're eager to keep pushing that ahead, and we genuinely hope to get one of those signed in the near future.
Okay, sounds good. Then, to build on that, your presentation mentions 700 megawatts worth of unannounced leasable customer power opportunities. Would that be extra power potentially available at land sites you already have? Or does it involve new land sites? How should we understand precisely what falls into that bucket?
Sure. It's genuinely a mix of those two things. In some cases, we could be holding off on signing particular power extensions at a site we already operate because of specific collateral requirements, waiting until we get nearer to a customer signing. In other cases, these could be sites where we hold exclusivity and are finishing due diligence, yet we feel confident enough to include them in customer discussions as opportunities we can offer.
Adam, regarding the new Hunt County location — my sense is that most of the agreements we've watched get inked tend to involve sites that already have live power. Clearly, this one won't have power until the following year. Could you speak to how confident you feel about securing a lease for that location, given that electricity will only arrive at a later point?
Sure. From our standpoint, honestly, whether power exists right now isn't the deciding factor, since building and developing that location will take us a while anyway. So if the electricity and the ramp timeline the utility has given us line up with how we plan to build, prospective customers find that perfectly fine. That leaves us feeling very good about Hunt. The way we view it currently, neither Senate Bill 6 nor any of ERCOT's newer adjustments affect this location; additionally, we've been informed that ERCOT won't be re-studying this project. That gives us considerable confidence in the location and the project. And we're eager to develop another big campus at scale right outside Dallas.
Great. Then perhaps, as a single follow-up regarding demand and possibly how you're pricing things, it seems as though the deals have improved progressively with each passing month and each successive quarter. When you're talking with prospective tenants, are you observing the same thing on your side? I'm just interested in your general take on the pricing landscape and the direction it's taking.
Yes. Pricing has unquestionably kept moving. Equipment costs and labor costs rising steadily in the market account for part of that. Consequently, you're witnessing a comparable trend when it comes to leasing economics. One factor behind our decision to kick off our project by moving ahead with locking down long-lead equipment, bringing trades onto sites, and starting civil work at a variety of locations was our desire to fix economics at those sites — in essence, pinning down what our costs will be while we remain in a climate where lease rates keep climbing. So for our business, that's a more defensive thing, yet it's equally an offensive strategy that lets us keep going after the market and position ourselves to genuinely contend for deals with hyperscalers, since what they anticipate is capacity handed over in under 18 months and, in certain instances, under 12 months; therefore, to place ourselves in those situations, we must be taking the steps we're taking now, which involve truly ensuring site readiness at these new locations.
If I could ask 2 things. First, regarding the Hunt County location, might you share roughly what the payment amounted to? And I realize you mentioned it would be energized in 2027. In what manner does that sort of energization ramp up? Then, Jim, as a follow-up, you commented on financing tied to the CoreWeave deal once there's "stabilization" — could you clarify what that term actually refers to, and possibly that it's 6 months after every campus has been completed?
Yes. Thank you, Darren. We'll share additional specifics about the Hunt County site once that site reaches closing later this quarter. Regarding energization, when we examine the megawatts, tail megawatts exist in this case, yet the energization timeline really ramps in parallel with how our construction timeline appears. Thus we feel that how that site appears at present regarding our site readiness and our capacity to deliver against the ramp schedule given by the utility; we believe that places that site in a very strong position concerning satisfying a number of various criteria that both hyperscalers and other large offtake companies might hold; so we're enthusiastic about that site and how it keeps progressing. I'll let Jim address the last question you raised.
Appreciate that, Adam. If you consider the magnitude of the CoreWeave agreement we hold, sitting at 590 megawatts, the total infrastructure involved falls somewhere in the range of $5 billion to $5.5 billion. So my mention of stabilization, along with pointing to capital availability of as much as $4 billion, refers to fully stabilizing that contract against the asset base currently under construction on our side. What's true here is that this differs from the way things are typically set up under project finance conventions, where the borrowing happens first and the building comes afterward. Against that asset base, we have considerable availability, which means we could draw down a sizable chunk of that $4 billion right now. Even so, the ramp is happening very quickly, since our billing progress is already so far along that we'll clear the large majority of it prior to the close of this year.
Henry Hearle here, filling in for Nick Giles. I'd like to ask a follow-up about the new Hunt County site. To be specific, what condition is that site in at present? And before building can get underway, are any preliminary permits required?
Yeah. Thanks for asking; as things stand, what we essentially must do in order to bring power to that site is that a substation still has to be constructed; therefore, when we consider the utility energization timeline alongside the construction timeline, we believe we're able to begin energizing that site in late '27, yet doing so will mean we need to get things moving on both our preconstruction work and getting the substation started within a fairly tight timeframe.
Then, regarding the preliminary construction permits, is there anything you can share?
Essentially, we've completed nearly every EFA Phase I and Phase I study, along with geotechnical work for that location. Schematic designs are already done. As a result, we possess a solid understanding of how we'll develop that site. What remains is simply to finish the design documents, reach the IFP stage, and afterward issue them for permitting.
Matt, you brought up new architectures, cooling, and also fresh GPUs. That comes across as somewhat frustrating. I'm just wondering — when you're putting together new sites, what degree of change are you noticing compared with earlier sites?
Right. On the tech stack, the progression is such that, clearly, if you're constructing projects that need 12, 18 months just to emerge from the ground, and during that window you encounter several shifts in technology and must adjust to them on the fly; for us, we began our initial data center alongside CoreWeave, launching with H100; after that we moved rapidly to NVIDIA's initial version of Grace Blackwells, the NVL36s, followed by the NVL72s, and then from the GB200 platforms over to the GB300 platforms, and we had to bring the data halls along mid-flight to match those technology iterations; more recently, NVIDIA put out its reference architecture for Vera Rubin. Consequently, we have a fairly solid sense of what that kind of paradigm shift will begin to resemble. This applies to both cooling and power distribution. So I'd say our teams are beginning to incorporate those changes into our new projects. As a result, we're both — we're fairly future-proofed regarding what we anticipate happening next; additionally, the final point I'll make is that, clearly, Google and the TPUs, with TPUs growing more common in the market. Therefore, we're likewise assessing how we might take our standardized design base so that we achieve a highly predictable, repeatable method for delivering product to market that can adapt both to what we do now and to what we anticipate from NVIDIA later on, plus these new chipsets entering the market such as TPUs, as they grow more widespread even beyond the Google ecosystem, so that we can adjust our data halls to those shifts too. So many moving parts, many developments occurring within the technology ecosystem, yet our engineering team and our development teams are, in my view, well ahead of the curve when considering how we adjust to all of that.
That's quite useful. As a quick follow-up for Adam: you brought up the wider and bigger pipeline of organizations you're engaged with, yet you've also indicated that at some stage we'll need investment-grade guarantees. Given those guarantees, how wide can that pipeline actually get? Are you observing that availability?
Yeah. I'd say what we're seeing spans quite a broad spectrum, and that spectrum keeps growing. It helps to look back at 2025. Recall the demand during the first half of 2025 from neoclouds as well as from AI Labs — basically, you hardly saw any new deals getting announced. Then obviously, in Q3 that shifted drastically once guarantees entered the market. There were certain deals we saw with Google backing them. And my belief is that as time goes on, we'll keep witnessing these guarantees evolve. Furthermore, the ones observed up to now originate from sources that are broad and varied. We named hyperscalers, chip manufacturers, and other sizable investment-grade guarantors — and that's genuinely what the market is showing us. It's a broad spectrum. They vary in form, ranging from debt guarantees through to full lease guarantees, so they span the entire range. And my expectation for what we'll witness across 2026 is really a convergence around terms tied to those guarantees and wrappers present in the market. Thus, I believe part of the delay and pause you've noticed in some neocloud and lab signings during the last 3 months stems more from the question of what those guarantees will end up looking like, since my view is they won't resemble how they've appeared previously. So right now we're negotiating with certain guarantee counterparties, and we're hopeful that those counterparties start converging on the appropriate guarantee so that data center developers can go out and finance these developments.
During your prepared comments, you mentioned that your pipeline holds more power than you could possibly construct within the coming several years. Could you provide a megawatt range that you feel certain about delivering annually? Also, is there anything troubling you right now regarding either supply chain or labor availability?
Yeah. Well, I do appreciate you asking that. So — regarding what we consider roughly an order of magnitude for what we believe we can develop, much of that will truly be determined by customers; we shared in our strategy that we are moving multiple sites forward through the design build process into 2027. However, once customers commit to those, that will genuinely shape the scalability and how quickly things accelerate in terms of how many megawatts we ultimately construct. During earlier quarters, I believe we offered guidance suggesting that, theoretically, we might construct up to 500 megawatts within one calendar year. I believe that is definitely achievable, though it will demand that customers commit to these projects quite early so we can arrange the financing and arrange the supply chain to expand those out to that kind of development magnitude; put differently, our internal capability to handle 0.5 gigawatt in a year and an 18-month time horizon is something we feel quite at ease with. It truly comes down to aligning economics and financing to back that strategy. I hope that addresses what you asked.
Can you expand on what you said earlier regarding the billing? When you energize and when you receive the bill, there's a 90-day lag. Is that what you meant to tell us?
I'll take the first portion of that. Speaking as Matt — essentially, what we mean is that when we power up a building, we hit what is basically our energization milestone, which involves filling all the equipment with electrons. After that, every data hall inside that building must proceed through the later commissioning stages — the fully commissioned test commission — and undergo all integrated testing so that each of those data halls in that structure becomes operational. Therefore, between when energization begins and when we finish fully commissioning those data halls, the span can fall approximately within a 90-day timeframe, at which point we'd anticipate revenue coming on.
All right. Then I believe this figure escaped me — but by the time the year wrapped up, what number of megawatts had been provided to CoreWeave?
As of the close of calendar year '25?
Yes.
Yeah, so by the time the calendar year wrapped up, we'd brought 213 megawatts online. That left us just a touch shy of what we were aiming for — one data hall short. But like we mentioned on this earnings call, we've more than caught up and gotten ahead of plan, with 350 megawatts energized and close to 200 megawatts billing. So I'd say the jump in progress across the past couple of months has been pretty impressive.
And you mentioned that around the midpoint of the year, everything would be up and running?
Once we reach the conclusion of — essentially as we move toward 2027 or during the first portion of '27, all the contracts ought to be completed and handed over in full to CoreWeave.
Kevin, could you go a bit deeper on Alabama? At 30 megawatts, it struck me as somewhat of an outlier. I'm curious how you fit that into the broader picture of securing hyperscalers. Adam: Sure thing, Kevin, and I appreciate you asking. That 30-megawatt location in Alabama is one we identified early as a place where things could progress fast. We likewise understand the power limitations in Georgia, and we see the low latency Auburn provided. As we sit here now, based on what our customers have told us, we think that site draws interest from quite a few possible counterparties. And we're leveraging it with customers on bigger contracts. One key point: hyperscalers don't just care about bigger sites and bigger campuses. They also want backfill in particular locations to cover particular markets. In our view, Alabama and Auburn in particular fit that need extremely well. So that project has us enthusiastic, and we're eager to secure a customer there too.
So in your view, does that kind of satisfy what's needed for an inference-style solution? And assuming that's true, is Matt in some way changing how sites get built and adjusting for possible shifts in use cases?
Yeah. That site will certainly serve inference use cases. However, Matt, I'll hand it over to you regarding infrastructure design.
Yeah. Auburn stands apart in a few ways. First, it kind of resembles a far more conventional multi-tenant data center — a Tier 3 style build, several 10,000 square foot data halls, strong security, plus a huge amount of connectivity. So it's closer to something you'd see at Digital Realty or Equinix, or a current Equinix-style site. From that angle, we view Auburn as genuinely a gateway, in terms of AI inferencing workloads and also the enterprise segment, because enterprise tends to involve smaller deal size, smaller deal constructs, along with the demand for dense connectivity and multicarrier-neutral environments — the infrastructure set up there makes it close to perfect for several different customer segments, covering AI and some non-AI segments too. So Auburn is a bit distinctive in that respect. When it comes to adapting to inferencing as opposed to large language model sites, say, from a technology angle, we don't observe much of a gap in what the density and power density requirements are across them. What we may see occurring is that cluster sizing could differ somewhat between an inference cluster and a large language model cluster, which might drive a bit more segmentation inside the campus at some future point. So that's broadly how — what we believe is taking place right now.
All right. Adam, before you wrap me up here — and honestly, no one has really brought up Bitcoin mining yet. I realize it isn't at the top of the priority list, but for a little while longer, it's still where most of the revenue comes from regardless. Could you share your thinking on how you see this year playing out when it comes to hash rate, and are you still going after those block miners you figured you might take a look at as last year wrapped up?
Yes, of course. Watching what's going on in the mining space has been quite a thing, hasn't it? Hash price is reaching levels nobody has ever witnessed, and falling under $0.03 was surely something people figured would arrive, say, around 2027 or 2028, considering the efficiency of machines as they stand now; on our side, that business remains basically in runoff as we speak, correct? What we're doing is managing our fleet of machines according to the minimum power draw requirements we have at a variety of sites. And we'll keep running in that same mode throughout this year. At this point we're simply optimizing so that we — so that we meet those minimum power draw requirements everywhere in our portfolio. As for the block units, installation of those is happening right now. That will therefore help us keep productivity up across our mining portfolio and genuinely help us reach — given that most of our machine fleet sits somewhere between 4 and 5 years old at this point — it really lets us keep meeting those minimum power draw requirements while staying profitable.
Kevin, that situation keeps changing as we go; at a lot of these sites, we're putting up new buildings right beside the existing ones, and that's the reason we keep buying more land throughout our portfolio. So essentially, the mining operation will shut down at the point when we move that power across to a data center.
On the progress front. People have been talking about NVIDIA providing backing for several neocloud-type companies. That could significantly widen the pool of clients you'd be able to bring on board. I'm just curious whether that's begun to show up in certain lease negotiations. Any thoughts on that?
Sure. My expectation is that every chipmaker will eventually get into the business of offering guarantees as a way to lock in their buyers going forward and truly cement architecture within the data center around their GPU chipset; so this is certainly a phenomenon we've observed. As I mentioned before, I believe it will keep developing. However, my expectation is that hyperscalers along with chip manufacturers will keep advancing along that same trajectory of seeking to offer guarantees for neoclouds and labs alike.
Got it. Then, setting aside some of those contract provisions for a moment, when it comes to lease rates — thinking about the newest generation of architecture, the somewhat greater CapEx that data center operators are putting up, and possibly the shifts in use cases you described when answering Kevin — will leasing rates begin climbing substantially relative to what's historically been signed, everything from you folks holding one of the earliest leases through the more recent deal with — ought we to anticipate a meaningful upward shift?
I wouldn't go so far as to call it a meaningful upward shift. What we've observed in the market is that our lease rates have generally trended somewhat higher relative to the CapEx involved in those builds. So I wouldn't claim that as we sit here right now, we're about to witness anything material that falls outside the range of what's been signed in the past. That said, I do think that across 2026, we could see a bit more normalization along with a slight upward drift when it comes to lease rates, though that's mostly a function of the fact that a lot of the hyperscalers set their data center pricing according to a yield, and they're aware of what their basis of design runs them.
So, sort of continuing from what was just asked, I'm a bit curious whether you're noticing any split between sites in more urban locations and what the potential pricing might be there — I suppose, the demand profile for those sites — and how that might possibly result in better pricing at a site such as Hunt County, which sits very close to one of the biggest data center hubs in the U.S.
Yes. I mean, when we look at Hunt, there's certainly improved pricing capacity available to us, and to data center developers at large, if you're inside a particular latency band relative to a major metropolitan market. Compared with, I'd say, more urban settings, that isn't really a game that we participate in. That's closer to the Equinix Digital Realty style of model. But my expectation is that our pricing for sites nearer to major metropolitan areas would be stronger than for sites that could be farther from major metro areas. So that pricing bifurcation does exist, and part of it ties to a dual use case — when you're nearer to the major metropolitan area, it can serve both LLMs and inference. Yet the other piece here is also time to RFS. It's something we discussed in our prepared remarks. Time to RFS is truly the trump card for data center developers. The closer you are to RFS, the greater your pricing power.
Great, that's really useful. And then, if I could, just one more question. Apologies if this was covered before. I'm just wondering whether there's any timeline for Kentucky and North Dakota at those sites, and any thoughts on what demand looks like there for possible HPC contracts?
Talks are ongoing with several different counterparties. Those are on our priority list, even though the projects Matt Brown described a moment ago are where we're focused right now.
We've reached the point where no more questions are coming in. With that, we're wrapping up the call for today. Feel free to hang up whenever you're ready, and I hope the rest of your day is great.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Core Scientific, Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Core Scientific, Inc. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.