Jon Charbonneau executive
#1

Thanks a lot, and good afternoon everyone. Welcome to Core Scientific's earnings call for the first quarter of 2026. Before we get started, I have to point out that anything said here that isn't a historical fact counts as a forward-looking statement under the Private Securities Litigation Reform Act of 1995, and it reflects what we currently expect. Terms like anticipates, estimates, expects, intends and believes, along with similar words and expressions, are meant to flag forward-looking statements. Such statements carry risks and uncertainties that might make actual results come out substantially different. To learn more about those risks and uncertainties, we urge you to look at the risk factors covered in the company's reports on Form 10-Q and 8-K filed with the SEC today, plus the press release and slide presentation included with them. Any forward-looking statements we make today reflect our views as of today only, and we take on no obligation to update any of them for events or circumstances that arise after today. You can find today's presentation on our website, investors.corescientific.com. Everything in this conference call is accurate as of today, May 6, 2026. Here with me today from Core Scientific are our CEO, Adam Sullivan, Chief Operating Officer Matt Brown, and Chief Financial Officer Jim Nygaard; once management's remarks wrap up, we'll move to a question-and-answer session; and now Adam will begin our remarks.

Adam Sullivan executive
#2

Good afternoon, everyone, and thank you for joining us. This platform was built to handle the market's most demanding compute workloads. Over the last twelve months, we've turned that strategy into execution, delivering high-density capacity at scale across several states. Those sites were a key starting point, but our first customer was never the whole story at Core Scientific. Delivering these initial sites boosts our operating credibility and gives us a significant capital foundation we need to scale meaningfully from here; we have clearly shown we can deliver at scale. Across five sites, we're now developing one of the largest multi-site AI infrastructure build-outs anywhere in the market. We are currently earning revenue on roughly 245 MW, with another 200 MW expected to be earning revenue in the months ahead. Our execution, together with the favorable structure of our CoreWeave contracts, has unlocked our next phase of growth. Today, we closed on a $3.3 billion capital raise backed by that contract, with proceeds going toward future growth and developing projects for other customers. The fact that our tenant has fully leased and financed five facilities is a meaningful differentiator. We can push the next phase of development in a disciplined way by securing land, labor, and equipment to protect timelines and speed up delivery. As these new projects get leased, we expect opportunities for further financing to continue the cycle of our forward development go-to-market strategy. Our next phase of development has already started. In late last year, we committed existing cash on hand to buy equipment for our other existing sites. With the new secured financing, we're now accelerating development activity across multiple sites, including Pecos, Muskogee, Hunt, Dalton phase III, and Auburn. This positions us differently in the market; we aren't waiting for deal negotiations to conclude before advancing sites. With capital in place, we can move early, bringing RFS timelines within the 12 to 14-month timeframe that customers are actively trying to solve for; we're also scaling our campuses in a repeatable way. Today, we announced a path to approximately 1.5 GWs at Muskogee, closely following a similar plan at Pecos. A key enabler of that scale is power strategy. Customers are increasingly focused on solutions beyond existing grid capacity, including behind-the-meter options; we're proactively positioning our sites to support those needs, including efforts to secure natural gas infrastructure where appropriate to enable future expansion. Pecos is a clear example. We're actively converting the site from Bitcoin mining to high density colocation, with construction already underway and a pathway to RFS within 12 months. Muskogee is another; we see a path to 1.5 GWs of gross power supported by grid expansion, the Polaris acquisition, and behind-the-meter solutions, and we expect to deliver additional data center capacity outside of our current contract in late 2027. Taking a broader view, what we're doing is running a repeatable playbook: lock down strategic sites, put capital in ahead of signed contracts when it makes sense, and build assets that get more and more attractive the closer they get to being ready. That leads me to where we stand commercially — we're going to customers from a place of strength. Since development is already moving forward, our schedules don't hinge on when contracts get signed, and that's a meaningful difference in a market like this one. As we've talked about before, we've been in an exclusivity process with a hyperscaler covering Pecos and Muskogee. That exclusivity has now lapsed. Three hyperscalers came to the table right away on those very same sites, and discussions are active at this point. This drove home just how strategically valuable these assets are and how deep the demand runs for large scale, high density capacity; it also shaped our thinking on how we handle exclusivity moving forward. It's probably still a required piece of certain deal negotiations, but it also has to come with defined milestones. In a market such as this, we won't leave high value assets sitting off the market any longer than we have to. Since the start of the year, our talks with prospective customers have gone up considerably. Hyperscalers are still our main focus, and on top of that we're seeing more and more interest from chip makers, AI labs, and neocloud providers. These newer customer categories hold real opportunity, even though they frequently need extra credit support. Together with customers and financing partners, we're hard at work on structures capable of backing long term financable commitments. Zooming out, our situation is straightforward; we're constructing a scaled, high density digital infrastructure platform with a diversified portfolio of sites. We're putting capital to work to lock in timelines and speed up delivery; on top of that, we're seeing robust customer demand. Given how we're executing, our capital position, and our commercial momentum, we have confidence in our capacity to keep growing and keep generating long term value for our customers and our shareholders; with that, I'll hand the call to Matt Brown, who will walk through more detail on our operations and development progress. Matt.

Matt Brown executive
#3

Thank you, Adam. Looking back at Q1, the things we need to get right operationally haven't changed. Keep pushing forward on the pipeline we already have, add capacity in an efficient way, and get the company ready for the coming period of major expansion. The appetite for high performance compute infrastructure is still robust, and we've concentrated on getting our delivery schedules, supply chain preparedness, and power plans lined up to serve it. Let me start with an update on our dedicated CoreWeave facilities, where we keep delivering quickly and at significant scale. I'm happy to report that 243 MW of billable capacity has now been handed over to CoreWeave. That figure covers a milestone involving complete turnover of both phase I data centers in Marble, N.C. and Dalton, Ga. In Marble, we finished building and moved the whole site into operations, which added 65 MW of billable capacity. At Dalton phase I, we similarly completed full handover of the site and put 30 MW into service. What these milestones show is the team's capacity to build efficiently at scale, shift assets smoothly from construction into revenue production, and stay consistently in step with customer schedules — all of which stay essential as we keep moving ahead. At the rest of our contracted sites, we'll keep bringing billable megawatts online in the months ahead while ramping up execution under the CoreWeave contract, which puts us in position to hand over more than 450 billables before summer ends, and we remain on schedule to reach the complete 590 MW by early 2027. Now to our non-CoreWeave developments, where our development strategy keeps moving forward. The campus we have in Pecos, Texas is among our biggest development opportunities, with a plan to grow from 300 MW up to 1.5 GW via a multi-pronged expansion approach. Our power roadmap sits at the center of this. We've locked in another 300 MW and are pushing ahead with a combination of grid connected and behind-the-meter solutions to underpin long term growth. The behind-the-meter approach draws on low emission generation and wraps up construction of a linear gas pipeline running to the campus. Put together, these moves are meant to shorten time to power, boost resilience, and lower supply chain risk while letting us serve hyperscale demand. Meanwhile, construction of our first 431,000 sq ft, 185 MW facility is moving out of civil work and into foundation stages, with precast walls showing up for vertical construction. We've secured long lead items equipment, which helps cut execution risk and keep timelines on track. We're also building out infrastructure for high density colocation, such as redundant fiber capacity and a new regional interconnect point in Midland, Texas, connected back to the Pecos campus. At our Muskogee, Oklahoma campus, we announced today plans to expand that site to 1.5 MW of gross power, or roughly 1 GW of leasable capacity. Much like Pecos, this expansion will draw on a blend of behind-the-meter infrastructure and utility supply power, among it the roughly 440 MW acquired through the Polaris transaction. Since the general contractor is already on site, work has started on our first building of 82.5 MW, and we expect initial delivery during the second half of 2027. Now, moving to the remaining development sites — Hunt County, Texas, Dalton, Georgia, phase III, and Auburn, Alabama — each one keeps moving through pre-construction milestones and stays on schedule for its initial delivery timelines. To wrap up, looking forward, our confidence remains strong that we can deliver on our commitments and seize the opportunities ahead of us. Strong demand, a portfolio of scale developments that keeps growing, and ongoing progress with our power infrastructure strategies together leave us well positioned for the coming quarters. I'll now hand things over to Jim.

Jim Nygaard executive
#4

Thank you, Matt. In Q1, we crossed a key inflection point: our colocation business grew enough that it now covers its operating expenses and has started to lift margins. That's a notable achievement in our transformation, since colocation has turned into a major contributor to our broader financial picture. At present, we invoice for 243 MW, equal to over $350 million in annualized colocation GAAP revenue, and we anticipate a substantial amount of added capacity starting to bill within the coming months. Keep in mind that, per GAAP, revenue tied to the CoreWeave contract gets recognized evenly across the 12-year lease term, which in effect accelerates the escalators. On the Bitcoin mining side, we continue to prioritize optimization and operate that segment to help counterbalance contractual power expenses as we keep shifting toward high-density colocation. Looking ahead, we anticipate mining operations will keep tapering off across the year, with a sizable reduction in miners running during the back half. Earlier in the year, we converted a large share of our Bitcoin holdings into cash and now hold just a small quantity of Bitcoin on the balance sheet. Turning to expenses. Cash-basis SG&A for Q1 came in at slightly above $30 million. Although we aren't issuing formal SG&A guidance, we see this figure as a sensible baseline for corporate costs ahead, with room for selective investments that back growth across the coming few years. On a separate note, you might have observed that we raised our target cash gross profit range on the CoreWeave contract to 80%-85%, versus our initial target of 75%-80%; we first put that target out about two years back, and at this point we have far better visibility into the related cost structure, since we're now billing on a substantial slice of the contracted megawatts. Given that operating backdrop, let me shift to capital formation, where today brought yet another significant milestone for Core Scientific. We completed our earlier-announced $3.3 billion CoreWeave project bond financing carrying a 7.75% interest rate, which, for a financing of this size, we regard as a very appealing cost of capital. Once closing costs were paid and the mandatory debt service reserve account was funded, net proceeds came to roughly $2.9 billion; for further context, these bonds carry a lockbox structure — a cash control setup in which project revenues flow straight into a designated account and are then allocated via the indenture-defined cash waterfall, first to operating expenses, next to debt service, and last to other purposes the indenture allows. Rather than the conventional project finance arrangement, in which a lockbox exists to fund one specific project still being developed, our setup permits distributing the great majority of offering proceeds up to the corporate level so we can invest in assorted new projects sitting outside the box. Looking forward, the lockbox will cover the debt backed by CoreWeave contracted site assets and cash flows. Looking at it this way, this deal meaningfully bolsters our capital position on a consolidated basis, confirms that the cash flows we have under contract are high quality and predictable, and equips us to carry out the following stage of our growth strategy with more flexibility, more speed, and more certainty. In 2026, we anticipate spending about $2 billion in total capital expenditures. That figure covers roughly $700 million for two things — the Hunt County, Texas, site purchase, which was completed yesterday, and the Polaris acquisition at our Muskogee, Oklahoma, location that we announced earlier today — plus spending to kick off pre-seeding of about 1 GW of new billable capacity. That spending involves procuring equipment with long lead times along with assorted site development and utility support work at a number of project locations; we are deliberately putting the business in position to sign appealing new customer contracts, with capacity beyond CoreWeave ready for delivery beginning in early 2027. The platform we are constructing, combined with the economical capital we have arranged for new project equity investments, stands apart in the marketplace, and we think it sets up Core Scientific to generate significant long-term value for shareholders. Finally, we recently brought on Jorge Rey as our Chief Accounting Officer, which makes our finance and accounting team even stronger. Jorge carries valuable experience in accounting and public company reporting, and his leadership will matter as we keep scaling the business and back our next stage of growth. At this point I'll hand the call to the operator for questions.

Brett Knoblauch analyst
#5

Hey, everyone. Appreciate you fielding my question, and congratulations on what's happening with the build-out in Texas and Muskogee. So I suppose regarding the Hyperscale exclusivity — it lapsed. Obviously, with other tenants sort of stepping in to fill that space, there's demand there. Could you give us some insight into the reason it lapsed, why things didn't move forward? Was it possibly that those locations weren't appealing, or they had no interest, or just some additional context on how that played out?

Adam Sullivan executive
#6

Of course. Thanks, Brett Knoblauch. Those locations, like you said, are extremely appealing — Pecos and Muskogee both — because of how much they can scale, and they offer a huge opportunity for a hyperscaler. Like we said in our prepared remarks, 3 hyperscalers engaged right away. These are very appealing sites. Honestly, with the party we hold exclusivity with, pinning down the precise reasons is difficult. From our standpoint, we reached the conclusion of the exclusivity period, and we believed now was the ideal moment to take these back out to the market, since hyperscalers kept coming to us and inquiring about the sites, and we understood we couldn't pass up the chance to get another hyperscaler involved. We're feeling very good about where we stand now, considering how competitive things are.

Brett Knoblauch analyst
#7

Great. Yeah, perhaps only a single additional question. You know, it appears as though the AI pendulum is sort of swinging into complete, you know, bullish territory at this point. From what I understand, you folks actually have quite a bit of capacity open for those kinds of RFS, you know, come early 2027. Do we think we might be nearer to a second tenant now than we were, you know, back when you guys reported 4 Q in early March?

Adam Sullivan executive
#8

Yeah, I mean, if you look throughout our site portfolio, you know, we've got five sites where first data halls are RFS in 2027. That's an unbelievably distinctive spot to be in considering the varying size and scale and geographic dispersion that exists within our portfolio. You know, we are talking with every one of the hyperscalers, chip makers, AI labs, neo clouds. You know, we occupy a distinctive spot here, simply because of the asset spread that we possess. I'd say without a doubt, throughout the whole site portfolio, we are nearer than we previously were.

Brett Knoblauch analyst
#9

Great, that's really helpful. Thanks a lot, everyone.

Adam Sullivan executive
#10

Appreciate it, Brett.

John Todaro analyst
#11

Hey everyone, I appreciate you answering my question, and congratulations on the power expansion. I've got two things. Actually, let me start with just one — circling back to those other three hyperscalers that you're currently in discussions with. If we try to put this into context, had there already been some conversations at some earlier point? Obviously the pool of possible partners is somewhat small, but should we view this as essentially beginning from scratch with them, or has there already been progress — maybe at some stage things had gotten fairly advanced — meaning we might see something land a bit sooner rather than having to start everything over?

Adam Sullivan executive
#12

Yeah. Thank you, John. The connection we have with those companies isn't a recent development. We're already working with them at other locations. What happened here was simply getting Pecos and Muskogee, both of them, back into the discussion. That's the real reason we can reconnect with those customers right away.

John Todaro analyst
#13

Okay, that makes sense, and it's quite useful. So, as you were saying, you've begun work on developing a few of these assets. From what it sounds like, that's happening prior to a lease being signed at certain locations. I suppose my question is whether there's any limit on the amount of capital expenditure you'd be willing to commit before a lease is in place.

Adam Sullivan executive
#14

Sure. The way we look at it at this moment is that our goal is to bring the initial data hall all the way to full RFS. That involves locking in the workforce and lining up the trades. We're also securing equipment with long lead times. This positions us so that should a customer commit at essentially any point prior to the first data hall reaching RFS, we're able to simply keep extending all the labor we've already locked in on site. That's essentially the boundary we're operating under at present; our confidence in this approach is high, and being able to demonstrate to customers the headway we're achieving at every one of these sites is what's truly driving the engagement here, since right now everybody is extremely eager for capacity that will be delivered in 2027.

John Todaro analyst
#15

Got it, that's clear. Thanks for the explanation, both of you.

Adam Sullivan executive
#16

Thanks as well.

Tim Horan analyst
#17

Thanks, everyone. Is there any ballpark sense of when a deal might get signed? Could you also walk us through what's happening with pricing, just broadly speaking?

Adam Sullivan executive
#18

Sure. What I'd say is that at this moment we're in active discussions with all the big players, and our confidence is strong when we compare our current position to the one we held three months back. The sole difference is that the value of our assets keeps growing. We've kept putting more capital to work, and we've kept moving nearer to the RFS date; we have a lot of confidence in the talks we're having with customers at present. Tim, could you repeat your other question for me?

Tim Horan analyst
#19

Yeah, so, what trends are you observing when it comes to pricing, or how are the rates looking on the new contracts that you're anticipating?

Adam Sullivan executive
#20

Yeah. I'd say you should probably anticipate that rates will keep getting stronger. That's really driven by the fact that both labor costs and equipment costs keep rising. What you're basically witnessing is the same kind of shift when it comes to price.

Tim Horan analyst
#21

And then finally, on the topic of behind-the-meter power, could you provide some indication of the lead time involved there? In the end, how would your expense for building your own, you know, stack up against the grid, you know, when compared?

Adam Sullivan executive
#22

Yeah. No, what I mean is, at present, what we're really considering is putting behind-the-meter solutions in place, you know, somewhere in the range of roughly 12 to 14 months. The wonderful aspect for us is, you know, these represent opportunities, given the locations that are open to us, and it's genuinely going to be a fantastic chance to keep growing at those sites. You know, that other site we haven't discussed, Hunt. You know, there's a possibility that Hunt could potentially add behind-the-meter, and that's something we remain in the evaluation stage on as of today. We haven't really completed as much of the due diligence as we've carried out at Pecos and Muskogee and the work that is presently underway there.

Tim Horan analyst
#23

When it comes to what a customer ultimately pays, is that roughly equal to grid pricing, or is it somewhat higher?

Adam Sullivan executive
#24

Roughly equal, yes. What I'd say is that from our standpoint as a developer, the economics appear quite comparable. For the end tenant, when you blend it together, the rate per unit of power isn't meaningfully different.

Tim Horan analyst
#25

Thanks.

Michael Donovan analyst
#26

Hey, everyone. Appreciate you fielding this. I've got another one about behind the meter. This morning's Muskogee news mentioned Oklahoma's behind-the-meter law. Could you walk us through what that law alters regarding Core Scientific's capacity to build, and does it hand Muskogee either a schedule or expense edge relative to chances in Texas?

Adam Sullivan executive
#27

Yeah, so Kevin Stitt has pushed hard to attract behind-the-meter possibilities into Oklahoma. As you know, his quote appeared in today's press release. The state, of course, is keen on discovering ways to add more generation. As for our execution in Oklahoma, I wouldn't claim it's automatically simpler or tougher than our Pecos location, though we clearly enjoy the government's backing there to keep adding generation within the state.

Michael Donovan analyst
#28

Excellent. Many thanks. If I could just ask one more thing. Have you given any thought to holding the generation assets outright, or would you only ever work alongside a power developer? What's your thinking on redundancy?

Adam Sullivan executive
#29

Sure, I'll handle the opening portion of that, and then Matt can address the redundancy side. As you know, when we look at behind the meter solutions, certain ones might be ones we'd hold on our own books, while others we'd go through a third party, which would give us a PPA, and we'd be making payments on those across a period of time, with that folded into the power price. There are a handful of different paths we could take. Ultimately it boils down to the economics question, plus who the behind the meter solution comes from. Matt, do you want to speak to redundancy?

Matt Brown executive
#30

That covers, too, the upkeep and running of the generation sitting behind the meter, which the PPA agreement brings along with it. Looking at it from a redundancy angle, clearly, as we put in behind-the-meter assets, redundancy matters a great deal more when what you're developing is high availability services. Our way of thinking about redundancy is that we must be capable of carrying the entire load for whichever part of the campus we're supplying from behind-the-meter, even while maintenance is happening — in other words, we have to be able to pull certain pieces of that equipment out of service for maintenance, keep carrying the full load, and still have spare capacity running and ready should something fail. You could roughly frame that as, at the low end, an N plus 1 setup, or perhaps a scheme with N +2%, or N + 20%, or N + 30% redundancy.

Michael Donovan analyst
#31

Excellent. Thanks for that, and congratulations on the progress.

Matt Brown executive
#32

I appreciate it.

Joseph Vafi analyst
#33

Hi, everyone. Afternoon. Nice work on the momentum. Appreciate you fielding this. I was just curious about how you might be handling the labor component of these builds. I'm not entirely certain whether you're using a couple of major GCs for the builds or, you know, do you see construction labor as a bottleneck in the current market? Thanks.

Matt Brown executive
#34

Yeah. No, that's a great question. Labor ranks among the market's biggest bottlenecks, if not depending on the specific market we're discussing. Looking at it nationally, labor is a significant problem; that's among the reasons we believe we hold an edge through our ability to proactively put money into developing these sites, to lock down and secure the labor via our projected RFS and expanding past that. As for how we're accomplishing this, we currently have 2 large GCs sort of carrying out our sites and development; those GCs possess considerable leverage in the marketplace, enabling them to lock down electrical contractors, mechanical contractors, civil, et cetera. Every one of those, all except for probably 1 site, is already fully mobilized and carrying out our developments, right now.

Joseph Vafi analyst
#35

Great. Thank you very much.

Paul Golding analyst
#36

Thanks so much. Congrats on the progress. I just wanted to ask about those behind-the-meter opportunities you've been discussing. I know you just mentioned, in response to another question, that you might partner with someone who would provide a PPA, or you might consider an opportunity to handle it yourself behind-the-meter in terms of generation. How is the air quality component of that structured, or how do you see that potentially being structured? Do you still have to go to market and apply for those emissions permits, or would a partner you're speaking with already have that in hand? I have a follow-up. Thank you.

Matt Brown executive
#37

Yeah, that's a great question. Like I said in our prepared remarks, the technologies we plan to back and support across all of our behind-the-meter sites will generally be low-emissions technologies. That should give you some sense of what we're steering away from on that front. Now, on the permitting side: yes, we will definitely need to apply for air quality permits for a lot of these deployments. Sometimes that will happen alongside the behind-the-meter operator or supplier. Other times, we'll handle it ourselves. Regarding both Pecos and Muskogee, I'd note that our air quality studies tied to rolling out those solutions are, in a sense, already quite far along.

Paul Golding analyst
#38

Got it. Thanks a lot. I was just hoping you could give us some additional detail on the different favorable and unfavorable factors that allowed you to raise the run rate margin profile on the energized and billable capacity you have now from 75% to 80% to 85%. Thank you.

Jim Nygaard executive
#39

Two years back, when we entered into the first CoreWeave contract, that agreement covered a planned scope of service. Looking back, I think we were being somewhat cautious, because at that point we hadn't started construction on the project yet, and the rollout was going to happen over a pretty extended timeline, so we wanted a really firm handle on what we believed we could achieve. Now that two years have passed, you're in the middle of it, and we've gained more experience — you know, knowing exactly which people will actually be assigned to these tasks, which contractors we're working with, and who's genuinely out in the field — so really, it's just bringing that experience up to date. We're pleased with the margin level we're able to achieve right now, and we've gained enough confidence to offer somewhat more specific guidance about where we expect to land.

Paul Golding analyst
#40

Great. Thanks so much.

George Sutton analyst
#41

Thank you. So when you start pitching the chipmakers along with the neo clouds, I'm just wondering — is your sales book split in two, so that certain sites, and perhaps even certain portions of a location, get pitched to those companies while the hyperscalers get others? How does that play out across the system?

Adam Sullivan executive
#42

Yeah, I mean, honestly, we're putting both chipmakers, neo clouds, labs in front of the very same sites we're also bringing to hyperscalers. I mean, as these processes move along, quite often, you know, they end up shifting to one site or another. In truth, you know, every customer who walks through our door gets to see all of our portfolios.

George Sutton analyst
#43

Another thing I wanted to ask about is the choice to move forward before those contracts were in place. When you've already locked down the supply chain and you're pushing ahead, how does that shift the way talks go with some of these prospective clients? Does it speed things up? Does it hold their attention better? Could you just take us through how that works?

Adam Sullivan executive
#44

Yeah, it absolutely holds their attention better. I mean, it's uncommon for them to come across a site in their inbox where the RFS timeline sits inside 18 months — and honestly, often shorter than that. In our case, when we can share photos and videos showing construction underway at these sites, plus the equipment list that's already been ordered, that really transforms how the conversations unfold, since what they're looking at isn't merely a picture of some land. This is a site where construction is happening, making real progress toward a data center being built.

George Sutton analyst
#45

Understood. Thanks, Adam.

Jon Hickman analyst
#46

Hello, and I appreciate you fielding my question. This may come across as somewhat obscure, yet since you are now significantly along in the CoreWeave construction effort, might you share your observations? For instance, which aspects proved more challenging than anticipated? Which turned out simpler? And where do you believe a competitive edge now exists, given that you have brought that quantity of megawatts — that many — online?

Matt Brown executive
#47

Yes. That is genuinely an excellent question. Thinking back on it, the piece that proved far tougher than we ever expected credit for was really carrying out brownfield conversions — which explains why every project you observe us pursuing going forward is in fact a greenfield location featuring a highly standardized design approach, enabling us to gain some advantage across our supply chain and remain extremely consistent regarding construction and the dates we deliver. Brownfield locations are exceptionally hard to forecast. Such sites demand extensive customization. Retrofitting a building that already exists takes considerable work. Though at times that route may be quicker, it brings substantially greater intricacy; that, I would argue, ranks as perhaps our largest — among our largest — takeaways from all of this.

Jon Hickman analyst
#48

All right. When it comes to competition, now that you have that knowledge, how do you see your position relative to others attempting to—I mean, plenty of other rivals are also trying to construct data centers?

Matt Brown executive
#49

Yes, the wonderful thing about.

Jon Hickman analyst
#50

What makes you the right pick, in a sense?

Matt Brown executive
#51

Right. The wonderful thing here, I'd say, is that although 5 sites haven't been practiced on, we've still been carrying out these high-density builds at every CoreWeave location; that let us refine those designs repeatedly. In other words, over the course of the portfolio we've put through more than 150 design changes. That hands us somewhat of a head start regarding what fails and what succeeds. All of that knowledge has, in a way, been brought together and shaped into a build strategy for going forward. I'd say we simply benefit from picking up all those lessons ourselves as things happened. Those errors won't be repeated by us down the line.

Jon Hickman analyst
#52

Excellent. Thank you. Nice work on those new agreements.

Henry Hurl analyst
#53

Thanks, operator; Henry Hurl here, filling in for Nick Giles. I'd like to inquire about how your stance on exclusivity has shifted. Under what circumstances would you pursue it? You also brought up that you're talking with a number of counterparties. If you were to strike one, should we anticipate an exclusivity announcement? Thanks.

Adam Sullivan executive
#54

Yes. Thank you, Henry. I wouldn't say we'd necessarily expect to make an announcement, you know, during the period between quarters. What we've really shifted toward is adopting a milestone-based structure, which lets us confirm that things are progressing at the speed we'd anticipate for a deal heading toward closing. That gives us the ability to put a site back on the market should we sense the pace and cadence aren't where we'd want them. We've made this move strategically. It's being put into action right now, and we believe it offers our strongest chance at success given the demand we're witnessing in today's market.

Henry Hurl analyst
#55

Got it. Appreciate the color. Moving to the phasing out of your Bitcoin mining business over the next several quarters — is there a firm deadline you have in mind for exiting that line entirely, or is it going to serve more as a modest hedge down the road? Thank you.

Adam Sullivan executive
#56

No. What I'd tell you is that as we move through what's left of 2024, that Bitcoin mining segment will keep shrinking. Once we reach the close of 2024, just 1 or maybe 2 locations will still be running Bitcoin mining.

Henry Hurl analyst
#57

Thank you. Continue. Best of luck.

Adam Sullivan executive
#58

Thanks, Henry.

Stephen Glagola analyst
#59

Hey, thanks for asking. Adam, I just wanted to check in once more regarding the difficulties we're facing in locking down leasing commitments at Pecos and Muskogee. From where I sit, it looks like your negotiating position is quite strong. The sites have power available in the near term. You can point to what you've delivered and the CoreWeave buildouts completed so far. I suppose my real question is this: are hyperscalers getting pickier about which development partners they work with? And if that's happening, how does it affect demand or the timing of deals?

Adam Sullivan executive
#60

Yeah, I'd say the interesting thing here is that the exclusivity lapsed, yet that customer remains engaged and still has interest in those locations. I think you're witnessing that on a broad scale throughout the market. You're observing repeat transactions among certain developers, particularly those on the private side. I'd concur with that. Beyond that, they're seeking proven experience in developing this kind of infrastructure; it differs from conventional data center infrastructure. With the track record we possess and our capacity to demonstrate 5 sites we've completed, 590 megawatts of critical IT load underway, that sets us apart, and it genuinely places us in a distinct category here. As you pointed out, we bring substantial building expertise; we have sites currently under construction, and it truly positions us in a rather unique tier within this industry.

Stephen Glagola analyst
#61

Thank you.

Operator operator
#62

That brings our Q&A portion to an end. Everyone, we appreciate your joining us. Today's teleconference is now finished. Please feel free to hang up your lines. Enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Core Scientific, Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Core Scientific, Inc. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.