Home / Transcripts / Core Scientific, Inc. (CORZ) · July 28, 2026

Core Scientific, Inc. (CORZ) Earnings Call Transcript

July 28, 2026

NASDAQ US Information Technology Software earnings 55 min

Earnings Call Speaker Segments

Jon Charbonneau executive
#1

Good morning, everyone, and thanks for joining us for Core Scientific's Second Quarter 2026 Earnings Call. I want to start by noting, before we get going, that anything said here today that isn't a historical fact counts as a forward-looking statement under the Securities Litigation Reform Act of 1995, and it reflects what we currently expect. You'll hear terms like anticipates, expects, intends, believes, along with comparable words and expressions — those are meant to flag forward-looking statements, and they come with risks and uncertainties that might make actual results come out substantially different. To learn more about those risks and uncertainties, please take a look at the risk factors covered in the company's reports on Form 10-Q and 8-K, which were filed today with the Securities and Exchange Commission, as well as the press release and slide presentation included there. All forward-looking statements we're making today reflect our views as of today, and we take on no obligation to revise any of them to account for events or circumstances that arise afterward. You can find today's presentation on our website, investors.corescientific.com. Everything shared in this conference call is accurate only as of today, July 28, 2026. Here with me from Core Scientific are our CEO, Adam Sullivan; our Chief Financial Officer, Jim Nygaard; and our Chief Operating Officer, Matt Brown. Once management's remarks wrap up, we'll hold a question-and-answer session; I'll now hand things over to Adam for his remarks.

Adam Sullivan executive
#2

Hello, everyone, and thanks for joining us today. This morning, we announced a business partnership with AMD that spans up to 2.5 gigawatts of data center capacity — clear proof that our deliberate strategy of starting development and construction at multiple sites before locking in customer contracts was the right call. Beyond the size of this deal, its contracted value and long-term growth potential, the agreements underpinning this relationship reflect the strength of the company we've built, the discipline and conviction behind how we operate, and the substantial opportunity that still lies ahead. Throughout this entire process, we've concentrated on forming the right relationships — ones that recognize the true worth of our portfolio. What matters most in this industry isn't deals you do just once. Real value lies in partnerships capable of scaling up dramatically as time goes on. Back in 2024, we signed a 16-megawatt lease with Core at our Austin campus, and that relationship has expanded to 590 megawatts of contracted capacity in total. That kind of growth trajectory is significant, and the AMD partnership we're announcing today shows what's possible. Under the initial deal, base contracted revenue comes to over $14 billion, spread across 15-year agreements featuring 2.5% annual escalators. Core Scientific is set to provide 530 megawatts spanning 5 sites — among the largest single deals any of our peers have announced. Following this announcement, we'll have 2 customers, each having committed to more than 500 megawatts apiece across 5 campuses. So under a triple-net lease, roughly 380 megawatts is going straight to AMD, spread across Pecos, Hunt, and Muskogee. Then there's another roughly 150 megawatts in Auburn and Dalton that will serve <<inaudible>> under a modified gross lease, and AMD is providing full credit support for that across the entire 15-year lease term. With this first agreement in place, both Dalton and Auburn end up fully leased. And the key point is that the longer-term opportunity at the other campuses goes far beyond what these agreements cover. As we've said before, Pecos and Muskogee could each eventually support as much as 1 gigawatt of leasable capacity, using a mix of additional trade connected power and behind-the-meter solutions. One thing worth pointing out: unlike some deals that have been announced elsewhere in the market, these credit support agreements contain no equity step-in rights at all, which shields the equity we've put into these projects. To mark this partnership, we've handed AMD a warrant, with the strike price set at where the market stands today, and the investment comes with certain commercial conditions attached. Through this structure with AMD, we stand to gain significant long-term revenue potential, contracted cash flows that are durable, a more varied customer base, and heavy use of the leasable space across our campus portfolio. That first 530 megawatts of contracted capacity is just phase one of what we see as a strategic relationship with the potential to grow far bigger. When certain conditions are met and at particular moments, AMD holds an exclusive reservation right allowing it to lease up to 2 more gigawatts. Our view is that we can deliver this electricity to AMD by combining added interconnected power capacity that moves forward via load studies with behind-the-meter solutions spanning Pecos, Hunt and Muskogee. Given that arrangement, we are set to scale in step with AMD as its infrastructure requirements continue to rise over time. The way we think about providing AMD space to expand throughout our portfolio demonstrates our confidence in its standing within the AI ecosystem, as well as our conviction regarding the long-term promise of this relationship. There's real momentum building for AMD in a rapidly expanding market, since hyperscalers, AI labs, cloud providers, and enterprise customers are adopting its advanced computing platforms more and more — which positions it as a highly attractive, strategic partner for Core Scientific. How big this relationship gets and what form it takes is significant, yet AMD's decision to collaborate with Core Scientific also communicates confidence in our capabilities. Our insistence on waiting for nothing less than the proper commercial deal stems from discipline, while our desire to secure it comes from execution. AMD had the chance to evaluate our power and real estate portfolio, and beyond that, our demonstrated history of building and operating extremely intricate AI infrastructure spanning numerous campuses. Over the past 12 months, we've demonstrated that we can go from signing contracts to construction, energization and generating revenue at significant scale. That experience is also letting us work closely with AMD on codesign initiatives, shaping the future of our campuses to drive greater efficiency and speed across their GPU and CPU products. Our execution capability isn't just theory. A, we're happy to report we're ahead of schedule and are currently billing for 437 megawatts of capacity. That is concrete evidence that we can take signed deals and turn them into working infrastructure that's actually up and running. In our view, that difference is going to carry more weight over time, because the market is shifting away from evaluating companies mostly by the announcements they make, and toward also considering whether they can follow through. You don't get value from a press release — you get it from execution. And bringing hundreds of megawatts of high-density infrastructure online demands much more than simply having power available. It requires a single, integrated platform for development and operations capable of designing, constructing, and running comp line for structure in a dependable and repeatable way at scale. Those are capabilities we have already assembled, and because of them we are positioned to meet the commitments we've already made, even as we continue to sign and grow capacity agreements with major players throughout the AI ecosystem. The deals we told you about today made our contracted portfolio a lot bigger and more varied. Core Scientific's total contracted billable capacity is now around 1.1 gigawatts, which works out to over $24 billion in base contracted revenue. And that matters just as much: we grew while holding to the same principles behind our strategy. We kept our discipline when it came to valuing our power, deciding how to use our campuses, judging customer credit, and weighing the risk-adjusted returns on every opportunity. What that gives us is a sturdier, more varied platform, with better visibility into revenue, plenty of built-in room to grow, and agreements with some of the biggest names in the AI world. Going forward, our aim is simple: wrap up the last 150 megawatts of the core build out. Having completed construction and handed over the leased capacity as planned, we're now set up to grow with our current clients down the road and keep adding sites to bring in new ones. During the last 12 months, our main goal has been shifting power we already have from Bitcoin mining over to high-density colocation. Now that we're moving into the following stage of expansion, we'll add to that approach by growing our power portfolio via targeted purchases of Powered land and by developing fresh locations. The deal we made in Hunt County, Texas earlier this year shows how we're starting to create this upcoming wave of capacity. At this point we've put together a pipeline of new sites totaling over 2 gigawatts of possible added power, with the first capacity likely coming online sometime between late 2028 and 2030. This pipeline significantly widens the range of opportunities before us, and when we move these projects forward we'll use the very same disciplined method that has shaped how our current platforms were built. In our view, the late 2028 to 2030 time lines line up nicely with how we schedule construction. For the next several years, our main emphasis will stay on carrying out the contracted commitments we've made as we push along the wider path toward 2.5 gigawatts with AMD. This pipeline, which stretches further out, gives us extra room to grow past that opportunity. Our situation is one of a kind, and we still possess the balance sheet strength and operational know-how to put money in before customers demand it whenever the economics make it worthwhile. The plan we've laid out is a model we can repeat, and it will steer our growth: obtain power early, stay disciplined with investment, bring capacity online at scale and grow fruitful relationships with customers. The AMD announcement made today serves as a key confirmation of the approach we've been following, yet it also acts as a base for whatever lies ahead. We stay assured about the opportunity in front of us and about our capacity to keep constructing 1 of the most valuable infrastructure platforms supporting AI's expansion. Prior to handing the call to Matt, I want to express thanks to everyone on the Core Scientific team. Their knowledge, dedication and combined work have carried us to this key turning point and put us in position to keep delivering for our customers and shareholders. I'm more excited than I can say about Core Scientific's upcoming chapter and the opportunity awaiting us. With that said, I'll pass the call to our Chief Operating Officer, Matt Brown, so he can go over operations. Matt?

Matt Brown executive
#3

Thank you, Adam. What we're announcing today represents an exciting new stage of expansion for Core Scientific, and it speaks to how well our team has executed. I want to start by highlighting a significant achievement from Q2, and after that I'll walk through the AMD build-out and delivery plan. During our previous earnings call, we shared that we anticipated bringing 4 of the 5 4-week campuses essentially to completion before summer ended. We hit that target ahead of the planned date, hitting 437 billable megawatts and proving we can deliver sophisticated infrastructure in a safe, efficient manner and at scale. Dalton Phase II, which is the fifth and last campus, is still expected to reach full completion in early 2027. Now that most of the core we program has been delivered, we're turning our attention toward the next development stage, anchored by our roughly 530-megawatt AMD commitment spanning 5 campuses. It's important to note that this initiative is not simply a group of separate data center projects. Rather, it's a unified colocation platform built to accommodate AMD Helios rack-scale systems tuned for the most demanding AI workloads. Our tightly integrated AMD design framework matches Core Scientific infrastructure with AMD's technology road map via a repeatable, scalable design that speeds time to compute, improves how capital is deployed and lowers execution risk as contracted capacity grows. Pecos continues to be our flagship AMD site, and it's still on schedule for its first megawatt delivery during the first half of 2027. Vertical construction has begun, major infrastructure equipment is starting to show up on site, and the project keeps moving forward consistent with the delivery schedule. For the other AMD campuses — Hunt, Auburn, Muskogee and Dalton Phase III — we're also making progress through design, procurement, site preparation and construction, with deliveries starting in 2027 and building up through the close of 2028. As we transition from 1 major customer program to the next, our operational priorities stay the same: deliver capacity efficiently, keep schedule discipline and deploy capital responsibly. We also aim to give investors transparent visibility into the genuine all-in cost of delivering high-density AI infrastructure. Cost per megawatt extends far past buying land and erecting the building. It captures the capital needed to bring a site from development planning all the way through construction, utility energization, integrated systems testing, commissioning, customer acceptance and finally rent commencement. We broke that estimate down into 3 categories. The first covers construction labor and on-site execution — skilled electrical and mechanical technicians, pipe fitters, equipment operators, project supervisors and safety personnel needed to integrate and commission the facility. The second covers the critical infrastructure equipment, often called OFE, or owner furnished equipment, such as transformers, switchgears, generators, chillers, pumps, liquid cooling systems, power distribution systems, control systems and the other major components that high-density computing demands. The third covers soft cost and general conditions — design engineering, permitting, utility interconnect, insurance, on-site construction offices, warehouses, temporary power, fuel, widening, program management, testing and contingency. Taken together, these categories capture the complete cost of delivering a commissioned, customer-ready, billable megawatt. Given what we're seeing in the market right now, along with factors specific to each site, our expectation for build cost is roughly $11 million to $12 million for every megawatt. The main point here is straightforward: we've shown we're able to deliver AI infrastructure at scale, and we're now bringing that know-how to a standardized multisite deployment platform for AMD, with real focus on schedule, capital delisting and repeatable execution; with that, I'll hand things over to Chief Financial Officer, Jim Nygaard, to go through Q2 financials.

Jim Nygaard executive
#4

Thank you, Matt. I want to start by walking through what we delivered in the second quarter, and those numbers show that our high-density colocation business keeps building momentum as we scale it. Midway through July, we started charging customers for 437 megawatts — that's close to 200 megawatts above where we stood when the first quarter closed, and it came in better than we had projected. As a result, GAAP colocation revenue climbed substantially on a sequential basis, reaching $137 million, and we anticipate yet another sizable increase when the third quarter is reported. To put that in perspective, GAAP rules have us recognizing revenue tied to the core weave contracts evenly across the 12-year lease terms. In practice, that means future contractual escalators get pulled ahead. When it comes to Bitcoin Mining, nothing about our approach has shifted. We keep fine-tuning that operation and run it mainly so that contractual power costs get offset while we wind things down. At the close of June, the number of miners we had online was almost 30% lower than at the end of the first quarter, and self-mining now happens at just 2 sites; we anticipate that coin mining will keep shrinking through the rest of the year. Turning to expenses, cash SG&A for the second quarter came in at roughly $36 million. That $4 million bump from the prior quarter largely came from one-time professional fees tied to the debt financing we recently completed. We aren't giving specific SG&A guidance, but we still see the low $30 million range as a sensible quarterly baseline, though it could move around somewhat as we make focused investments aimed at supporting growth. Having covered the quarter, I'd like to discuss capital formation and how we plan to fund the next stage of growth. The AMD announcement marks a major commercial win and serves as meaningful validation of the investment and financing approach we've been executing; when the second quarter ended, we had roughly $1.8 billion in liquidity, which gives us a solid base as we get ready to finance the AMD build-out. Based on our present CapEx estimate of $11 million to $12 million per megawatt, the first 530 megawatts will need about $6 billion in capital, and our plan is to fund that through project-level bonds. Past our contracted obligations, we plan to keep selectively moving capacity forward before customer contracts are signed, sticking with the same playbook that put us in position for the AMD opportunity. Broadly speaking, we're ready to put as much as roughly $1 billion toward advancing about 500 megawatts of initial build-outs for future capacity. That money would go toward advancing development, locking in long lead equipment, and creating more certainty regarding ready-for-service dates. The AMD announcement shows how valuable this approach is and strengthens our capacity to turn customer demand into added contracted capacity. We think our balance sheet and financing strategy leave us room to carry out our contracted commitments while still investing in the next phase of Core Scientific's growth; with that, I'll return the call to the operator for Q&A.

John Todaro analyst
#5

John, thanks, and congratulations on the lease and all the momentum. I've got two, if that's all right. The first one is about the possible expansion with A&D — from what I can see, 1.5 gigawatts of that sits behind the meter and in the load study, as stated. I'm just curious whether you can provide a bit more detail on the timeline. And if that timeline ends up being somewhat longer, does AMD then hold exclusivity for a meaningful stretch of time, or could you maybe lay that out a little more clearly for us?

Adam Sullivan executive
#6

Yes, happy to, John, and thanks for asking. To begin with, this is clearly a transformational deal for Core Scientific, and our partnership with AMD on it has us as excited as we could possibly be. I don't think it's appropriate for us to speculate, especially about what AMD will do regarding the additional megawatts. As you noted, the agreement covers up to nearly 2 gigawatts of extra capacity. That's an exclusive reservation agreement we hold with AMD. I think the key piece here is that, as you look at it and as you pointed out, behind the meter — behind the meter is becoming far more common across the marketplace among hyperscalers and labs. It's remained a growing segment of this market, and I believe the comfort level among all of the peers keeps rising when it comes to the meter deployments. We have excellent solutions when it comes to our Pecos and Muskogee campuses. We're excited to grow those campuses alongside AMD, and I think the key piece here is that market demand for GPUs just keeps expanding, obviously highlighted by the most recent AMD announcements. But data center capacity remains in very short supply. So we feel we're very well positioned for the continued growth here, and we're going to be able to deliver a site amount of capacity for AMD.

John Todaro analyst
#7

Excellent, that's quite useful. Then a fast question about the Neal cloud lease: will there be some kind of backstop or guarantee for them, and does AMD have a connection to that one too, or is it entirely separate?

Adam Sullivan executive
#8

Yeah, I believe that's right; they're giving complete credit backing across the entire 15-year lease period. And like we mentioned during prepared remarks, that complete credit backing contains no equity step-in rights, unlike what you've observed in certain other transactions, which merely affect, for tax purposes, our equity stakes in those projects.

Brett Knoblauch analyst
#9

Nice work on this transaction. I'm wondering how the numbers break down between, say, the two agreements that sit inside the bigger one. Is it fair to think of the economics of the Neo Cloud piece combined with the backstop as roughly matching what you'd get from the AMD arrangement on its own?

Adam Sullivan executive
#10

Yeah, that's essentially correct. Given how the lease was restructured — a sort of revised growth framework tied to Neo cloud — you can figure those terms fall right where the market is. The same holds, I'd add, for the AMD direct leases; they too sit at market levels.

Brett Knoblauch analyst
#11

Great. Then perhaps regarding capital expenditures. I realize you have been making outlays in advance at several locations. Might you give a rough estimate of what portion of that $11 million to $12 million has already gone toward fixing up some of those sites?

Adam Sullivan executive
#12

Yeah. Yeah. Similar to what was discussed during our prior earnings call, we expected to spend roughly $2 million for each megawatt throughout the portfolio. As a result, we had slightly more than $1 billion in commitments tied to these projects. So when it comes to the equity investment needed for these projects, we are quite far along in our capital commitment.

Analyst analyst
#13

Congratulations, everyone. If I could ask two things. Could you walk us through the reasoning behind whether this agreement is exclusive to AMD, with them essentially dedicating that level of capacity to just one customer — what was the thinking there? And regarding the timeline you presented, how confident are you in your ability to bring that capacity online as scheduled?

Adam Sullivan executive
#14

Sure. Thank you, Darren. I appreciate that. When we consider the commitment we announced with AMD today, this really is a one-of-a-kind partnership within this market; we hold a strong belief that how well we executed across the core contracts was among the primary factors enabling us to secure such a distinctive partnership agreement with AMD. Looking at the product road map and the expansion, the reservation rights AMD holds over additional capacity at locations where they have direct leases — that's Pecos, Muskogee, Hunt. When it comes to the delivery schedules and their reservation rights schedules, those align quite well. So we hold a strong belief that we can keep expanding side by side with AMD at those 3 locations especially. — simply because there's considerable demand in the market. As I said before, market drivers all favor us when it comes to both supply and demand in this industry; and we think AMD will keep growing going forward; and Darren, regarding your other question, about how confident we are in our ability to deliver — we have the equipment secured, we have contractors on site across these 5 campuses. This is an unusual situation relative to others who are announcing deals with Greenland. We have people moving on-site, walls going up at Pecos as we mentioned, we have the building fully complete at this point. So we feel we're in a very strong position, and that confidence in our ability to deliver along with the progress we've made, we believe, is truly the reason AMD selected Core Scientific to partner with.

Jon Petersen analyst
#15

Fantastic. Congrats on the AMD agreement. That's genuinely thrilling. Now, regarding — checking out your slide about the load study, the extra power, Pecos, Texas. So I believe on August 7, an update is coming our way from ERCOT, I suppose that 815 megawatts. Could that possibly be freed up for you folks, or do you have a schedule for it sometime in the coming weeks?

Adam Sullivan executive
#16

Judging that is genuinely tough for us. A portion of it is the — pardon me, roughly 300 megawatts out of that belongs to the Pecos load study, and this sits behind the meter. When it comes to how we execute on the following megawatts at Pecos specifically, I'd say that will be steered by the behind-the-meter approach, simply because of the unpredictability around when that subsequent 300 megawatts from on-grid power will arrive.

Jon Petersen analyst
#17

Okay, got it, that helps. Now, turning to development — could you walk us through how this lease came together? Like the various elements you'd already lined up, such as money down on the different supply chain items required for the project, and getting general contractors plus subcontractors arranged. I'm just interested in hearing a bit more regarding what you all have been doing over these last several months, and the components you needed to assemble in order to reach the point of signing that lease this morning?

Jim Nygaard executive
#18

Yes, I'll field that one. As we mentioned during our prior earnings call, we laid out a plan centered on pushing into development before demand arrives. So across the last year, we'd gotten underway building Pecos. We'd begun precon at Hunt along with the second building at Muskogee. That means we were already moving through precon and engineering; we had locked in — in fact we'd placed orders for equipment tied to the first delivery phases at every one of those projects. So what's the takeaway there? It means we'd locked in long-lead equipment covering a substantial quantum of those megawatts. Beyond that, we'd locked in the labor along with the GCs on site, and were moving through GMPs. At this point we've reached a stage where — at Pecos we've finished, for example, the precast, and the building is nearly done here within a matter of weeks. The full shelf for the first 10085 megawatts is done, and we're pad-ready utility reiteration across the remaining sites. We freed up capital for substation construction earlier in the year at multiple sites. So every bit of that work we've been moving through over the course of 2026 has positioned us to work with AMD, and we're genuinely excited about our capacity to execute through 2028.

Nick Giles analyst
#19

Congratulations, everyone. You brought up, I believe, 2 gigawatts of new sites. Could you break that down by the number of sites and how far along due diligence is? And would you anticipate spending capital at those sites before any lease, similar to your existing footprint?

Adam Sullivan executive
#20

Yes, thanks for the question, Nick. Yes, regarding the 2 gigawatts, we aren't providing a specific breakdown of how many sites. But I'd say the Hunt acquisition we completed earlier this year is extremely typical of the opportunities we're chasing now. I'd call that an excellent strike zone when it comes to the total power available at the site; and as for the last part of your question, definitely. When we review new sites and consider acquisition costs, what we factor into those calculations is the ability to get that site to a truly pad-ready condition at the very lease. That involves installing the substation and deploying that capital, so as we assess these sites, we consider how — how this aligns in terms of when the power becomes available versus our construction schedules, and so there are multiple sites in that pipeline at different stages of due diligence that we're confident we can bring a new site to market, hopefully, by year-end here.

Nick Giles analyst
#21

And perhaps one for Jim. Is it reasonable to anticipate project-level debt being raised by you at the site? Or in what way do these AMD direct sites, as opposed to the Neo clouds with the wrapper, shape the broader financing approach?

Jim Nygaard executive
#22

The main financing approach we'll take will involve the project bond structure, which, I'd say, is pretty standard in today's market, quite close to what we executed with Core Weave. In practical terms, the SPVs look much the same in the direct scenario, where the tenant bears direct responsibility for meeting the lease payment. That's essentially what powers that vehicle. Regarding the credit support mechanism, the debt receives full support. That mechanism remains present in a comparable structure; thus they perform and run quite — in a quite comparable manner, yet they do carry differences: having the direct relationship in 1 and having a credit support figure in the other. Even so, they are project bond structures within the SPVs that we have by now employed in the core weave example.

Ben Sommers analyst
#23

When we consider the possibilities behind the meter — I'm just sort of wondering, where do things currently stand when it comes to locking down items that might have long lead times for this? And I suppose — I realize a direct estimate of the timeline isn't something you can provide, but I'm just sort of wondering how that development is moving along as we think about growing with AMD or past that? .

Adam Sullivan executive
#24

Yes. I appreciate the question. What I'm able to share is that our visibility into the development behind the meter at Pecos and Muskogee — we've already had discussions, advanced discussions, with suppliers of natural gas. We've completed preliminary planning regarding lateral development to those locations; and we've had some quite integrated discussions with providers of equipment that would supply the generation 1 site for that. So I'd say where we are today is that we possess really clear visibility into the execution timelines, cost, and every delivery partner needed to pull that together. .

Ben Sommers analyst
#25

Great. Then one more brief question from my side. Regarding adding capacity, could AMD potentially extend that to, say, a different neo cloud, comparable to what Tower is doing here, and afterwards provide a backstop for such a contract? Or must everything go through AMD directly?

Jim Nygaard executive
#26

When it comes to direct leases, everything must go through AMD directly.

Joseph Vafi analyst
#27

I'll add my congratulations too. It's really good to see that AMD news. If we look back roughly a quarter, I recall you were closing out certain exclusive talks involving, I think, a few of those sites and an investment-grade tenant, and now the AMD announcement has arrived. It would be interesting if you could share any color on whether AMD had been that exclusive negotiating counterpart, or whether they showed up once those exclusivity periods lapsed — I think that would be valuable and insightful when it comes to the cadence of negotiations out there across the broader marketplace?

Adam Sullivan executive
#28

Yes, thanks for the question, Joe. I won't comment on the identity of the customer in earlier discussions. What matters most here, I think, is that this is a long-term relationship built up over a lengthy stretch of time with AMD; they were assessing how well we execute, looking at the existing contracts we have in place today. They were assessing our order book when it came to long-lead equipment; and we were assessing the sites over a stretch of time while construction kept moving forward across the 5 campuses they've now signed up for. So these conversations take a while, and I think that's what you'd expect across the market; but what we're signing today is genuinely unique, and we couldn't be more excited about partnering with AMD on a project of this scale.

Joseph Vafi analyst
#29

Absolutely. That's really useful, Adam. Then, Jim, when it comes to producing revenue and cash flow from operations, you seem to be out in front of everyone else at this stage — how does that revenue, and a P&L that's maturing more, shape the strategy now compared with where things stood perhaps 6 or 9 months back?

Jim Nygaard executive
#30

Yeah, I'm glad you asked; this represents a pretty significant shift from what we've done historically in Bitcoin mining, which definitely brings plenty of volatility and a shortage of transparency, into basically a financial picture that's the exact reverse. That's the reason this company, in terms of being able to raise financing, its visibility and ultimately its stability, lets us genuinely commit to investments with great confidence. So that change has us enthusiastic. There's been a great deal of noise in our prior financial statements. What's thrilling about the coming year is that we'll begin from a blank slate, and you'll begin to witness a far more developed financial profile take shape. One that aligns much better with the new business model. . So for us that's a thrilling change, and 1 we believe will benefit us greatly, and I'm grateful for what you said about us leading the pack. That's a key thing to note regarding how we stand apart in the market, something I feel we frequently don't receive much recognition for. So I thank you for pointing that out.

Stephen Glagola analyst
#31

Nice work on the transaction. Adam, I'd like to hear your wider perspective regarding what the debt side of the funding market looks like right now? Also, during the past several months, has project financing availability shifted in any way? .

Adam Sullivan executive
#32

Sure. Appreciate it, Stephen. Clearly, the announcement has us thrilled, and its timing lined up remarkably well given the wider market backdrop and the recent reports that have come out — so regarding the funding market, like you said, what we observe right now is unquestionably a rates backup. My read is that this reflects a broad digestion phase tied to AI; across every bond currently in the market, we're just seeing a major degree of digestion from investors who are expressing their views through their trades and through where rates have been heading. So with such a strong investment-grade counterparty on this, it doesn't worry us — appetite for bonds of that kind will persist in the market; that's genuinely what made us confident about executing this contract. If you happened to be signing a contract with somebody beyond, roughly, this credit tier, you'd have question marks around capital raising. Yet considering where we stand now alongside AMD as our partner, confidence regarding financing this deal is extremely high.

Jon Hickman analyst
#33

Can you go over the schedule once more — when power first gets delivered for the AMD deal — does that happen in early 2028?

Adam Sullivan executive
#34

For that initial AMD contract, the earliest megawatts to be energized are going to be at the site we have in Pecos; we've stated this before, and that energization is set for the first half of 2027. More generally, our guidance has been that roughly 50% of the contract gets delivered during 2027, with the remaining 50% delivered during 2028.

Tim Horan analyst
#35

Is there a sweet spot for how many megawatts you'd want to construct annually? And does some sort of ceiling exist on that? And then regarding the power behind the grid, what actually sits on the critical path? Is that the pipeline? Is that the turbines, or something else? .

Adam Sullivan executive
#36

Yes. I'll handle the opening portion, and Matt Brown can address the second. When it comes to the ideal megawatt figure each year, looking at what we see for 2028, our belief is we could aim for roughly 600 megawatts in 2028, given today's labor limitations and the long-lead equipment limitations present in the market. Naturally, that hinges on schedules for signing extra capacity under the AMD agreement. Still, I think it's an excellent target for us, 6 — give or take 600 megawatts each year, it's a strong cadence for the business. That said, though, should the chance emerge to deliver beyond that within one year, it doesn't mean we wouldn't want to keep scaling our capabilities and internal team to truly satisfy that need; but as we stand today, in 2028, we're targeting roughly 600 megawatts of delivery. Matt, want to field the question.

Matt Brown executive
#37

Yeah. The limitations differ from one location to another, though I'd say for the most part they come down to how long delivery takes. What holds things up is either the time required to construct the lateral pipeline or getting the equipment delivered, and it simply comes down to the different sides of things. At certain locations of ours, the delivery schedules will lean more heavily on equipment manufacturing and production capacity. Meanwhile, at other sites, it will lean more toward pipeline development and delivery. So — those are really the 2 primary factors that tend to determine the schedules there.

Paul Golding analyst
#38

Nice work on that transaction. My question concerns capital expenditures. The slide mentions an estimate of $11 million to $12 million for each megawatt, and the $6 billion figure over 530 megawatts suggests the same thing. What I'd like to know is why this CapEx runs higher than the core — the one we discussed right at the start. Does that come down to greenfield against brownfield? Is the basis of design different, and what ought we to anticipate later on regarding cost for each megawatt should you complete additional deals with other counterparties? Then my second question: I wanted to ask about speeding up those 437 megawatts delivered for Core Weave — does that unlock the acceleration? Could you pull that same lever further with the AMD engagements? Does any breathing room exist there?

Matt Brown executive
#39

Yes. I'll handle the first portion of that question, the part about cost, and how it connects to where we stand now with the present $11 million to $12 million projections on a portfolio basis. Regarding the Core Weave sites, that engagement began in early '24. So in '24 we began locking in labor and equipment. What we've observed, more or less year-over-year, is a fairly broad-based rise — equipment costs going up, partly because of tariffs during the past year, partly because of supply chain constraints and availability, and then — yet the main factor pushing, I would say, construction cost at present is labor. Across many U.S. markets, labor is extremely scarce. Many of the GC — many electrical subcontractors, especially the big ones, along with plenty of the mechanical trades, are simply swamped with work at the moment. So the result is that this labor shortage naturally pushes wages higher in certain highly competitive regions throughout the U.S. So I'd say that's 1 of the largest distinctions — simply the way cost has risen over time. And regarding certain Core Weave sites, there are simply some basic design variations at a number of those locations that differ from what we're doing now and, without getting into every detail, there are some basic variations between what we did with Core Weave and the present product set.

Brian Dodso analyst
#40

Congrats on getting that deal done. Now that it's signed and announced, could you share a bit more detail about how the demand environment is shaping up? I'm certain you've been talking with plenty of interested parties, so maybe you could tell us what to expect regarding sector deal signings over the next 6 months? What's your take on this? And in what way is demand changing?

Adam Sullivan executive
#41

Yes, Brian, thanks for asking. When we examine the demand landscape for developers who are currently in direct talks with counterparties able to execute contracts, the picture stands in sharp contrast to the media headlines. What we observe on the ground remains a substantial volume of demand originating from the hyperscale channel and the AI labs. Regarding what lies ahead over the coming months and through the remainder of this year, I believe we'll see ongoing new deal announcements tied to large-scale infrastructure commitments. The key point here is that many of these large-scale GPU contracts are only being signed right now. Those GPUs don't have a home yet. Considering what we've witnessed across the course of the past 12 months and late deliveries throughout this industry, plenty of GPU is sitting on the ground. Those GPUs still need to be plugged in. As that backlog keeps building, I think what we'll ultimately see is more constraints across data center supply. And clearly, given, I would say, some of the headwinds related to new developments of data center capacity across this industry, having available rack space within the next few years is going to be in high demand for all data center developers; and this is a great win for the DCs, and I feel very strongly that we're going to continue to see new contracts being signed over the remainder of this year as this demand picture and supply are shaping up for continued new leases to be signed.

George Sutton analyst
#42

Nice work. I'd like to know, regarding the reservation chance involving AMD, in what ways do we keep talking with other partners? What do you do to keep that blend active? .

Jim Nygaard executive
#43

George, thanks for asking that. Through the arrangement we've got in place with AMD, this is a partnership. Therefore, while the extra capacity falls under the observation agreement, we won't be talking to customers. As a result, we'll coordinate very closely with AMD regarding what they'll need down the road, and we intend to keep expanding right along with them. Within this sector, this is a genuine and one-of-a-kind partnership. Plus, I believe it will require time before folks truly grasp how transformative this is, along with the distinctive spot Core Scientific occupies in the wider landscape. So as far as we're concerned, we simply anticipate carrying on growing right alongside AMD, and we anticipate what unfolds at Pecos, Muskogee and Hunt. .

George Sutton analyst
#44

George, on that Neo Cloud client — Neo Clouds differ a lot, so can you share anything about how big this one is and what its scope looks like? And I'd imagine the contracts backing it are already signed?

Jim Nygaard executive
#45

Jim, unfortunately that's not something we're able to discuss right now. What I'd point to as the main thing about the deal we closed with the Neo Cloud is the complete 15-year credit support agreement we have with AMD, with them backing the credit; that makes us feel quite good about the transaction; and the 2 leases that got signed across — across Auburn.

Michael Donovan analyst
#46

I want to say congrats on the progress. To build on what was asked about behind the meter, is it only turbines you're considering, or are fuel cells also part of the evaluation?

Adam Sullivan executive
#47

That's right. We aren't closing any doors, and which technology ends up being paired in will probably differ from one site to another. From recips to linear generators and fuel cells — all of those are on our list. In part, the local geography is what shapes that choice, along with the environmental conditions where the site sits; and then the other factor is simply what's available in the supply chain and so on. So I'd say — but we've — we've definitely had conversations with quite a few vendors for every one of those equipment categories.

Michael Donovan analyst
#48

Got it. Now regarding that gross modified lease tied to the Neo Cloud, what's the right way for us to think about it when it comes to large margins?

Adam Sullivan executive
#49

The way to look at those NOI margins is that they're fairly in keeping with the market standards that have been made public for the other deals that have been announced. So our view is that we're squarely in line with that.

Andrew Beale analyst
#50

Could you discuss the reservation entitlement for additional capacity? In other words, does AMD hold the option to lock in Phase 1 pricing along with that 2.5% escalator, or at whatever point that option kicks in? Or does some other process exist for arriving at a market price on subsequent signings?

Adam Sullivan executive
#51

The single point we're able to address regarding that reserved capacity is that any future capacity executed under that agreement would take the form of direct leases with AMD.

Andrew Beale analyst
#52

All right. But when are those agreed upon — at that moment, or is the price fixed beforehand?

Adam Sullivan executive
#53

The terms would be largely the same as those in the leases currently in effect.

Analyst analyst
#54

Morning, everyone. There's plenty of positive news in what we've shared today. I just want to make sure I fully understand — at what point will that final 150 megawatts for Core Weave be built and handed over?

Adam Sullivan executive
#55

Appreciate you asking. Right — that remaining 150 megawatts relates to our Dalton Phase II campus, which is set to start coming online toward the close of this year, with full completion expected in early 2027.

Analyst analyst
#56

Okay. As a follow-up, you mentioned how mature your model has become. At this point, you've got contract visibility, a customer base that's more diverse, and Neo cloud. Since your P&L does show adjusted EBITDA margins, what would that metric look like given the business mix and how it evolves by the end of 2028?

Adam Sullivan executive
#57

Yes. Thanks for asking. So far, we haven't given specific EBITDA targets for the business. As we move closer to a cleaner set of financial statements, we'll definitely refine that thinking. We've been working through the mining dynamics of our business, and as we get to year-end and begin 2027 with a clean year, we expect that to be an even smaller portion. We haven't provided specific SG&A guidance. That said, in my commentary today, we discussed that quarterly baseline of roughly $30 million a year, and naturally, we've disclosed the revenue numbers behind the Core Weave contracts. So when it comes to EBITDA margins in this business, we monitor them very closely from a cash perspective. Lease accounting under GAAP has a dynamic where escalators in the top line, a bit early, inflate the GAAP margins. On that metric, but we track it on a cash basis. And we're quite confident that this is a much higher EBITDA margin that's very attractive and frankly has considerable leverage on the operating expense line; so the business we announced here today will only strengthen that financial profile, and there's only upside to that margin profile going forward.

Operator operator
#58

That brings us to the end of our Q&A portion for today. Everyone, we appreciate you taking part. With that, today's conference call is officially over. Please go ahead and hang up your phones, and we wish you a great rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Core Scientific, Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Core Scientific, Inc. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.