Artemis Gold Inc. (ARTG) Earnings Call Transcript
November 5, 2025
Earnings Call Speaker Segments
We appreciate everyone being on the line. I'm the conference operator speaking. Thanks for joining us for Artemis Gold's conference call covering third quarter 2025 results. Please note that everyone attending is in listen-only mode, and this call is being recorded. Following the presentation, we'll open things up so you can ask questions. If you'd like to enter the question queue, press star followed by one on your phone's keypad. And if you require help at any point during this call, you can reach an operator by pressing star and then zero. At this time, I'll hand the conference over to Meg Brown, Vice President, Investor Relations. Meg, the floor is yours.
Thank you, operator. Good morning, everyone, and welcome. Thank you for joining our Q3 earnings conference call and webcast. It's an exciting milestone and a transformational time for Artemis Gold as we report our first full quarter of operations since declaring commercial production in May. Before we begin, I would like to remind everyone that certain statements made on today's call may be forward-looking, and we encourage you to refer to our public filings and disclosures, including the cautionary language in yesterday's news release, for a more detailed discussion of potential risks and uncertainties related to these statements. I'll now hand the call over to our CEO, Dale Andres. Over to you, Dale.
Thanks, Meg, and I appreciate everyone taking time to be with us on today's call. Joining me are our Founder and Executive Chair, Steven Dean, our President, Jeremy Langford, our CFO, Gerrie van der Westhuizen, our recently appointed Chief Business Development Officer, Tony Scott, our Chief ESG Officer, Candace Alderson, and our VP Finance, Erik Marchand. Once the presentation wraps up, we'll take your questions. Gerrie and Jeremy will assist in walking through the quarter's highlights, and I'll begin on slide three — actually slide four — with our operating highlights. Q3 marked our first complete quarter of operations following our commercial production declaration in May 2024, and since then we've posted very strong operating and financial results. During the third quarter we produced 60,985 ounces of gold, with an all-in sustaining cost of $840 per ounce. That low-cost position, combined with the persistently strong gold price environment we're experiencing, produced industry-leading all-in sustaining margins. For the third quarter, our all-in sustaining cost margin came in at $2,374 per ounce of gold sold, equal to a margin of 72% of our cash revenue. Both the mine and the mill performed well throughout the quarter.
Mill throughput came in at 101% of design capacity for the quarter, and it averaged 105% during the months of August and September. Gold grades and gold recoveries both moved upward as we keep optimizing how the mill performs. The operations team has delivered mining and milling rates above design capacity in such a short span of time, and we're pleased with that. In July we completed a planned three-day shutdown of the mill, which involved work to fix a number of design and construction deficiencies. Costs for the quarter came in above what we initially planned, mainly because of higher reagent consumption tied to both the ongoing optimization of the circuit and the processing of ore with transitional ore characteristics, along with higher plant maintenance costs stemming partly from the rectification works but also from targeted circuit improvements. We also recently marked a major safety milestone: more than 6 million hours worked without a lost-time incident. That really is a testament to the dedication, care, and culture of our people. Safety has been and will remain our top priority as an organization. Slide five shows an aerial view of the pit, and on the mining front things are going very well.
Our mining rates are running ahead of plan, and we're observing that planned waste is turning into low and medium-grade ore. The pit walls look good, and our attention now is on continuous improvement efforts. A key tool in that continuous improvement journey we're on is short-interval control meetings backed by real-time mine equipment data. That lets us react to operating problems and get the most out of equipment productivities, and, importantly, standardize and enhance our daily operating practices at the mine. I've witnessed this in practice many times, and it's working very well. At the mill, we've made excellent progress and are consistently running above the designed hourly and daily throughput rates. That said, unplanned downtime is showing up more than we expected. We haven't hit any firm bottlenecks so far, and we're working hard to improve reliability, which will let us reach 10% above design for a full quarter, which is our target, and we're targeting that by the end of this year. At the mill, crushing. Circuit modifications have been a major focus area for us since the mill's initial startup. And as is typical with new milling operations, we're continuing to adapt and optimize various aspects, including liner designs.
We wrapped up a planned four-day shutdown at the end of October, and it included the first full reline of our ball mill — a notable milestone for our operation. With these new liners in place, the mill should also be able to further improve throughput and grind size, and that carries through to recovery. That applies to our current quarter, for November and December, when compared to the months prior to that liner change. We're also advancing an ore characterization program to improve our understanding of the variability of the deposit and its implications for mill performance, and we continue to evaluate and refine reagent dosing to maximize recoveries and optimize our costs. On slide seven, regarding guidance, we are maintaining full-year production guidance of 190,000 to 230,000 ounces of gold produced. However, we expect to come in within the lower half of that range, primarily because of higher-than-anticipated mill downtime as we keep uncovering and rectifying deficiencies, as I mentioned earlier, along with recoveries that are lower than originally planned. On costs, we have revised our guidance to 800 — this is $825-$875 per ounce gold sold, up from our previous guidance of $670-$770.
So that's mostly driven by the weaker sales, along with the fact that we now expect to land in the lower half of the production guidance range, plus greater reagent usage and higher unit costs at the mill and increased maintenance expenses. We expect those elevated reagent and maintenance costs to come down as we head into 2026, and as our optimization work moves forward and the identified deficiencies get fixed. We're making very good progress on that front. With our updated guidance range, we're still in the lowest decile among gold producers worldwide, and our all-in sustaining cost margin remains firmly among the strongest in the industry. At this point I'd like to hand the call over to Gerrie to go through our financials.
Thanks, Dale. One thing that's probably worth flagging: every dollar figure we'll be discussing over the next couple of slides is in Canadian dollars, unless we say otherwise. Meg, could I ask you to flip back one slide, please? Much appreciated. In the third quarter, revenue came in at CAD 308 million, made up of CAD 284 million in cash revenue and CAD 24 million in non-cash revenue, which came from selling 62,863 ounces of gold. Adjusted net income was roughly CAD 142 million, and adjusted EBITDA was CAD 211 million. During the quarter, our average realized gold price on spot sales was just under CAD 4,800 Canadian for us. Cash flow from operations reached CAD 163.7 million, which was tremendously robust. Let me take a moment to note that there are a couple of notable non-cash adjustments in the quarter that we adjust for when arriving at adjusted earnings. The first is a CAD 17 million fair value adjustment on roughly 21,000 ounces of remaining voluntary hedges, which you'll all be familiar with from the previous quarter as well. Another non-cash adjustment: our finance expense for the quarter includes a one-time charge of CAD 13 million this quarter, representing the unamortized transaction cost associated with putting the project loan facility in place back in 2023.
So since we retired that project loan facility this quarter, roughly five years ahead of when it was due, the leftover transaction cost had to be written off as an expense in the current period. Turning to the following slide, in the quarter we repaid CAD 67 million on the project loan facility, and then we refinanced what was left, CAD 449 million, through a corporate revolver. With this revolver we get better commercial terms and significantly more flexibility. It matures four years from inception, and we can extend it by a further four years, and no principal repayments are required before maturity. That flexibility lets us accumulate cash ahead of starting the phase II expansion that Jeremy will discuss later. We finished the quarter with total liquidity of CAD 317 million, made up of CAD 75 million in cash and cash equivalents plus CAD 242 million still undrawn on our revolver. To sum up, our financial position is very strong, with cash growing and the financial flexibility to fund organic growth. I'll hand it back to you, Dale.
Thanks, Gerrie. Now if you look at slide 10, you'll see a handful of the capital projects we've had underway during this year. We've ended up spending more than we first expected on a few of these, but they represent a significant investment and they matter greatly to the operation's success over the long term, particularly as we get ready for phase I-A and phase II growth. To be specific, we've put more investment dollars than planned into building the tailings dam and/or stockpile. That ties closely to favorable grade control reconciliations, which I discussed earlier, and it stems from them — we ended up with more low and medium-grade ore and less waste material on hand. On top of that, because suitable fill material wasn't available from the pit, we had to source material from higher-cost borrow pits, and a number of those borrow pits sat within the tailings footprint area. And although these effects have pushed capital costs above plan so far this year, there is a future payoff in the form of extra pre-stripping. That means future production for the mine, future mill feed from the stockpiled ore — and year to date we have more than 9 million tons of low and medium-grade ore stockpiled. And importantly, there's additional capacity within our tailings footprint for storing future tailings.
Turning to slide 11, we see substantial growth opportunities through both enhancements at the phase I operation and faster progress on phase II development. We're implementing certain productivity gains in the existing phase one operations that I mentioned earlier. And we see — and keep seeing — the potential to reach 10% above nameplate capacity on a sustainable basis by the end of the year. Phase I-A construction is already underway, with the goal of achieving 8 million tons per annum processed by the end of the next year. Phase II is the bigger expansion project that Jeremy will discuss shortly, and it is in and nearing completion of front-end engineering and design. We still have considerable resource expansion and exploration upside beyond our phase II project, and we've recently launched a regional exploration drill program to test some of that, which I'll touch on briefly after Jeremy. Over to you, Jeremy.
Thanks, Dale. And good morning, everyone. Phase I-A gives us a straightforward but flexible way to expand what phase I currently has, which is 6 million nameplate. Facility, and during the second half of 2026 its throughput will rise. By roughly 33%. At the top of the slide, as you can see, the project budget falls within a capital cost range of CAD 100 milion-CAD 110 million. And it is clearly a metric of capital intensity that leads the industry. Funded out of operating cash flow and with a payback period under six months, we see this expansion as a quality addition. In Q3, we exceeded every key objective on the phase I project. A few of these highlights include. Engineering moved along very well, to the point that we expect it to be completed before the end of 2025. We also made progress on procuring key longer lead items like the vertical grinding mill. Minimal footprint with maximum benefit, and a very simplistic design when interconnecting this mill into the current facility. We purchased the additional two leach train tanks, additional oxygen plant modules, detoxification circuit shear reactors, pre-aeration, and pre-leach agitators, as well as the additional main motor control center for the expansion, or the MCC.
Regarding construction, we made strong headway. It's a pleasure to report that the two extra ring beams at the process facility have already been poured, running a bit ahead of plan. There's a chance we'll seize the moment to pour the foundation for the vertical mill foundation soon. That work, though, isn't slated until early next year. Before I turn to the stage two expansion, stage I-A ended Q3 in excellent condition. Every key date is being satisfied, and the way the operations and project teams on site have worked together deserves praise. Meg, next slide, please. Phase II, juice. An optimized and accelerated expansion. Our aim has been to add substantial extra throughput, with the bonus of achieving it on a more aggressive, shorter timeline than what we communicated before. The new phase II makes this plain. Quarter three went very well in this key growth element, and as Dale mentioned earlier, we are in the final stages of completing the front-end engineering and design phase. A disciplined approach to development remains central to our DNA. And for those who have followed our phase I journey, our de-risking ethos shows clearly in this upcoming expansion project.
On a related note, our approach with phase II has been to allow a complete greenfields construction approach that won't interfere with phase I operations. That's exactly what this new phase II accomplishes. We reduced overall project risk by placing the order for the 18-megawatt ball and sag mills a while back. Just to remind everyone, the ball mill's key mechanical components are in fact completely fabricated. And they will be before the project starts, with the sag mill's design being a duplicate of a mill currently running somewhere else in the world. The scheduling flexibility this gives us is uncommon. And for the build team and myself, certainly very exciting. In addition, we've lowered the risk on the other long lead packages, every one of which is ready to be awarded. Once the full investment decision has been reached. As we progress through Q4 2025 and into quarter one 2026, our main focus is to. Complete the project execution plan and begin an early workspace. That involves finishing construction of the first two accommodation camp expansions, completing the bulk earthworks cut and fill designs, and starting bulk earthworks within the phase II footprint. Growing our owners' team, of course. Beginning our master schedule optimizations and opportunity planning. While advancing phase II engineering and detailed design.
We're doing this under an EPCM format. We'll also keep advancing the optimization work on the mining plan along with the fleet requirements necessary to elevate this new growth opportunity to the next level. Still, it's an exciting period ahead for all of our collective teams. A decision on investment is anticipated before the close of 2025. On-site early works will begin in earnest on January 26. And construction will commence in Q2 2026. With that said, I'd like to return the floor to Dale.
Thanks, Jeremy. And yes, this is genuinely, genuinely thrilling, so keep watching as we move forward and share updates down the line. On slide 14, I'd like to offer a bit of an update regarding what lies beyond our major growth projects. Our resource growth strategy at Blackwater has two branches, specifically extensions to the existing deposit and, importantly, our regional exploration. The present Blackwater deposit remains open, and we'll be aiming for reserve growth there going forward. At the moment, though, we aren't drilling the deposit extensions, since our focus is on pushing ahead the phase II engineering, as Jeremy outlined. On the regional side, we've recently kicked off a CAD 5 million drill program expected to deliver 15 to 25 kilometers of reverse circulation drilling. Within our sizable and promising land package. And we began this in mid-October, and we're already 2 kilometers into the program. So keep watching, and we'll report on progress across the coming quarters as we show the potential there. So moving to the final slide, 15, to sum up, all things considered, I believe we've enjoyed an exceptional beginning to commercial operations across the last five months, during which the team has delivered above nameplate capacity performance in a very brief stretch of time.
We achieved this while maintaining one of the lowest all-in sustaining costs anywhere in the industry, and paired with today's strong gold prices, that gives us excellent, exceptional margins. Our balance sheet remains solid, with a cash balance that is growing and is expected to keep rising as the year goes on, and that will back our many near-term organic growth opportunities, including the phase I-A expansion and the phase II expansion. As Jeremy mentioned, our feed is close to completion on the phase two project, and we remain on schedule to bring an investment decision before our Board prior to the end of this year. That wraps up our presentation. And before I hand the call back to the operator for questions, I would like to briefly pass things over to Steven Dean, our Executive Chair, for a few closing remarks ahead of opening the line for questions. Steven.
Thanks, Dale. And I'm really glad all of you could join us on the call and see firsthand the depth and level of expertise at this table among our senior management group. Honestly, I couldn't be prouder or more excited to come into the office and see that for myself. And frankly, you're seeing it in the results we've delivered so far, but also in where we're going and how quickly we're moving toward our various expansion goals. I'd also like to underscore a few of the points the management team has raised. I've gone through some of the analyst reports that have already been published promptly, and thank you all for that. I just want our analyst community to look past some of the headlines and grasp what's really happening in our business. And in particular, our costs — we have adjusted them in our guidance, though not materially. What I think we should be focusing on heavily is our financial performance. And on every metric — cash flow per share, earnings, EBITDA, you name it — we are above consensus, and I believe above nearly every analyst who covers us.
So, what I think you ought to take away from that is how strongly we're concentrating on those financial metrics. Obviously, costs matter. But we already hold the top margin in our industry when it comes to our production base. The spirit and culture of this company is something I take great pride in. It stems from how much ownership our management and board have in this business. We're still entrepreneurial. We're still focused on de-risking. That's how we approach running the business and chasing our growth objectives. And I hope that comes across, and that you'll hear it in the reports you've heard today. As Dale said, we're very much focused on continuing to build value for our shareholders, and we've still got a ways to go. And we're all very excited for the near term as we hit our goals on I-A expansion. And very shortly, as Dale mentioned, on our pursuit of the investment decision on phase two, which will be a very large step in our growth over the next few years. I'll turn it back to you, Meg, for questions.
Thanks, Steven. We’ll now hand things over to the operator so we can begin the Q&A session.
Thank you. We'll now start the question-and-answer portion. To get into the question queue, press star followed by one on your phone's keypad. A tone will sound to confirm your request. Should you be on a speakerphone, lift your handset before you press any keys. If you want to take your question back, press star, then two. We'll hold briefly while callers join the queue. Today's first question comes from Harrison Reynolds at RBC Capital Markets. Please go ahead.
Morning, everyone, and thanks for joining. It's really encouraging to watch the ongoing momentum at Blackwater, and well done on an impressive set of results for the first full quarter. I've got a couple of questions. It's encouraging to see phase I-A taking shape. Could you give us some sense of when the first incremental throughput gains from this spending might show up, and how those would actually appear? Might we see them as early as Q1 2026, or would it take longer than that before the benefits become visible? And do you have any initial thinking on 2026 guidance? Should we be anticipating something above 300,000 ounces?
Sure, thanks, Harrison. I'll take your last question first. We aren't yet in a position to give guidance for 2026. Beyond that, our goal is to reach 10% above our design throughput by the end of this year. So you can factor that into your analysis. I believe we've addressed this before, but looking at how we execute phase I-A, the main thing that gets us to 8 million tons of design capacity is installing the vertical mill. That comes toward the end of the project. But there are other important pieces that help us keep optimizing the current phase one. For example, the shear reactors Jeremy mentioned, or extra tankage — if we can get those running early, and early here means perhaps near the end of the second quarter, that would let us begin ramping throughput beyond our 10% above-design target, which we are still clearly pursuing before this year is out. So that's a bit of color. We view this as a progressive optimization, bringing in elements of the phase I-A build as soon as they're ready, and.
We're using that to push both recovery and throughput gains while the vertimill is still pending, and that's really the major lever we need to pull. We want throughput raised to 8 million tons, and ideally beyond that once it's installed.
That's clear, and no, thank you. I appreciate the additional detail. Perhaps just one more question. To what degree do you consider these cost increases temporary — simply part of the noise that comes with ramping up? You cited a few of those reagents as well as maintenance. All of that should fade over time. But what about structural shifts? One item on my mind is the greater conversion of waste to ore, which is logical given what is optimal in today's conditions, but also persistently higher costs of waste from other sources. So how do you expect costs to trend? Are there structural elements tied to the way you are approaching mining and processing at Blackwater? And again, recognizing that you are focused on maximizing economics and that you remain at the front of the cost curve, are there structural changes we are seeing now relative to what may have been contemplated in the feasibility study?
Okay, well, thanks for that, Harrison. I suppose I’ll offer a few remarks. There are certain areas where we clearly see our costs — the elevated costs we’ve experienced. During Q3, and we do anticipate that some of those expenses will carry over into Q4, for items such as reagents. And maintenance. We do expect those to be transitory. I believe in our press release, we did mention that we had a recent. Ball mill motor failure that caused two days of unplanned downtime over this past weekend. Obviously, those. And we are still conducting the root cause analysis on that. But it appears to go back to. More of a manufacturing installation issue rather than any kind of operating issue. But we had a spare. The team responded tremendously well to install the new motor. That is behind us. The mill is performing excellently. At the current time. So some of those things are definitely transitory. We are. Continually upgrading our. Reagent control systems and our understanding of the ore body, including the transition zone material. And by definition, that is transitory. And. We will be optimizing our reagent use and our process control. With better understanding of the ore variability to.
We need to eliminate those expenses. We've already made solid headway. I simply can't promise we'll get completely there by Q4, and that's part of why our guidance for costs went up. I'd just note that, in hindsight, perhaps the guidance we set at the beginning of the year came before we had any operating history. Some growing pains are entirely normal, but I'd point to the fact that we're exceeding design capacity. The spine of the plant and its core facilities are running very well. We haven't identified any permanent bottleneck. The bottleneck keeps shifting to different areas of the plant as we uncover various issues and push toward 10% above design capacity. That's a positive thing. We aren't hitting any hard constraints. Turning to the capital side, as we look ahead, we're very near completing construction on our current tailings downlift. We keep finding additional low and medium-grade ore. We expect that to continue given what we're seeing in our recent grade control drilling. We'll need more stockpile pad construction space. So that.
That will keep going. However, since we’ve halted construction of the tailings down lifts, we ought to have plenty of appropriate construction material coming out of the pit. And we’ll be ramping up pit equipment to support I-A, which will also support upcoming tailings downlifts. And when that material comes out of the pit, that’s when it’s far cheaper. When we must rely on borrow sources, it becomes more expensive. But I would just, once more, emphasize, as I said during my presentation remarks, that where we did borrow the material from, even though it cost more, does provide important benefits for the future. So we see those more as an investment than as higher cost.
Thanks for laying that out so thoroughly.
Apologies for the lengthy response, Harrison, but I hope that provides you with some useful context.
No, no, that's a lot of detail. Thank you very much. And once more, congratulations to the entire team on the great performance. Thank you.
I appreciate it.
Wayne Lam from TD Securities has the next question in our queue today. Go right ahead.
Yeah, thanks. Morning, everyone. I just had a question about that deferred phase one capital that's being spent. I'm curious what share of it goes to the processing plant as opposed to the other infrastructure projects. And then, just, I wanted to ask whether you can give any updated guidance on how much is left to spend on that deferred phase one capital, given that the CAD 80 million spent this quarter came in above the earlier guidance.
Yes, and as I said earlier — I believe this came up when I was responding to Harrison's question, and thank you for asking it, Wayne — we do expect a portion of this to be transitory on the capital side too. What that means is we're nearing the point of completing the build. We're finishing up the current lift at the tailings down. So as you think about what to expect for the remainder of this year and into the early part of next year, we're going to be in transition. Most of those capital costs relate to what I'd describe as earthworks projects. That covers not only the tailings facility but also construction of the stockpile pad and our water infrastructure work, which includes the freshwater reservoir. On top of that, there are watering wells at the mine. That sort of thing. All of those are one-offs. So they're wrapping up. I think we've been quite lucky to have the construction team from phase I still available to carry out those projects. Keeping that team on hand does come with a somewhat higher carrying cost. But as Jeremy made clear, that team is now shifting into phase I-A construction. And shortly — assuming we approve the phase two project, which we plan to do before this year is out — they will be moving over to phase II.
Construction will ramp up shortly. You'll be seeing some of that as well. So to reiterate, a portion of those expenses will certainly begin to show up. Regarding how the team is carrying out our existing projects, that effort will carry over into I-A and II. And yes, keep an eye out for the phase II update. Our expectation is that it arrives prior to year-end. We're moving along well on it. I hope that addressed what you asked, Wayne.
Our following question this afternoon comes from Jeremy Hoy of Canaccord Genuity. The line is yours.
Hello, Dale and Team, this is our name speaking. Thanks for fielding my questions. It's encouraging to see grade, recovery, and throughput all moving in the right direction. You mentioned that grade should rise again in Q4, which would make it the strongest quarter of the year. Could you give us a bit more detail on that, and perhaps share what grade control drilling is showing as you look toward 2026?
Right. Once more, I don’t believe we’ll provide a specific quarterly guidance figure, Jeremy, but we do anticipate grades in Q4 will come in above those of Q3. There was a sizable step up as we moved from Q2 into Q3 — I think it rose from 1.34 to 1.48. So we’re targeting and expecting something above 1.5 grams per ton in the feed for Q4. And when we carried out the initial grade control drilling on the first 20 million tons — the first 20 million tons being mined from the deposit — we were observing roughly more than 30% additional ore in the low and medium grade categories, and importantly in the medium grade category. And on balance, we saw roughly the same quantity of high grade as we had expected within that classification. We’ve now grade controlled upwards of 30 million tons, so that’s another 10 million tons of material mined from the deposit. And so far that ratio of seeing 30%+ additional ore appears to be continuing. I think it’s too early to claim that this will hold for the remainder of the deposit. But we’re beginning to reach roughly 8% or 9% of the deposit grade control drilled. We are stepping up our drilling — that’s among the factors that have pushed costs up somewhat.
That didn't really deserve a mention, though it plays a small part too. But we've moved the drill to two shifts. We've added—if the exploration rig is midway through, uh, between moves, we're able to shift it over to the pit for extra grade control drilling. Our real aim is to position ourselves for optimization—not only of 2026, through this grade control program, but also for the I-A expansion and, shortly after that, getting ready for phase II. So, yeah, a very, very positive result. Yes, it pushes our costs up somewhat in the near term, but the benefit is simply tremendous. And it will put us in a tremendously strong position for the far larger phase II expansion.
Right. That’s useful, and I understand the point about giving guidance for specific grades. With respect to the efficiency gains you all have identified in the mill, have most of those already been dealt with by now? Or is there still work remaining — I’m trying to get a sense of how that could affect operations through the end of the year and into 2026?
Yeah. That's tough to pin down. Putting an exact percentage on it is difficult, Jeremy, though I'd say most of the problems we've identified are now behind us. Let me give you a few illustrations besides the mill motor, which I already mentioned. A few of these involve the agitators in our CIL circuit. We simply can't shut the entire CIL circuit down in one go. One tank has to be taken offline at a time so those gear components can be fixed. And by the way, taking a tank down also has an effect on recovery. Still, we're largely finished with that. My sense is maybe one or two tanks remain of the whole train still to be done, but we're most of the way through it. Take the gravity circuit — we're observing wear that's higher than anticipated. Modifications have been made there. We're also building permanent fixes, and those ought to show up early next year. That expense is already beginning to come through, but once the extra high-wear-resistant piping lands early in the new year, installation shouldn't carry a large cost. Those are just a handful of examples of.
A few of the gains that we are making. On the oxygen front, I would say we have needed to — in my view, our oxygen setup was under-designed. In the near term, we have had to bolster it using extra reagents, such as hydrogen peroxide, in our detox circuit. That is fairly costly and was not anticipated. However, we are nearly there — two of the oxygen plants ordered for phase I-A were placed early. Within the coming weeks, those ought to be installed. So. These are a few of the items both on the maintenance side and connected to the reagent side. The two are somewhat linked. Still, it provides a sense of the rectifications we are carrying out and moving forward on.
Thanks, that's genuinely useful. I'll come back to you for further guidance next year, though — on this phase two. We should be getting additional details before the final investment decision on it. Will those arrive as a technical report? And what exactly should we expect to see, and at what point?
Yeah, I'd say our current plan would be — we're getting very close on the front-end engineering and design for phase two. We're still working through items such as the mine plan, ancillary infrastructure like tailings and water, things like DC hydro, making sure we have the power available — various items like that. So that's what we're focused on now, leading up to the investment decision. As for more detailed guidance on that, I think we'll have to wait till we finish the work. Which we do — we do anticipate putting out details on the capital cost and design. And I'd say when it comes to production and costs, we will give a range, a pretty clear range of our expectations with that Phase II project. But we're anticipating a technical report will likely follow in the March-April timeframe as we finish optimization on those aspects outside of the capital build itself. So that's kind of our current thinking. We're still, like I said, we're still progressing the work in advance of the investment decision. And we'll update you and the rest of the market as soon as we have more details to share on that.
All right, it sounds like there will be ample detail for us to model that. My final question concerns the gold forward contracts tied to the PLF. Have they been retired or modified? Going forward, how should we model those?
My apologies, Jeremy. Was your question about the hedges tied to that project loan facility?
Correct. Now that that's done. The project loan facility has been fully repaid, and those hedges were required. What ended up happening with them?
Those are still on the books, and delivery into them begins in Q4 of this year. In our MD&A, I believe around page 11, we've included further disclosures that set out when the roughly 190,000 ounces under the mandatory hedge come due. Beyond that, there are 21,000 ounces of voluntary hedges, and those mature across Q1 and Q2 of next year.
And I’d like to note that the 190,000 ounces under the mandatory hedge are distributed across roughly the next two and a half, nearly three years. So yes, delivery on that begins in Q4, but it is spread across that period.
Yes, that holds through 2028.
That's right.
All right, excellent. I simply overlooked that in the MD&A, it seems. My search was in the financial statements. Thanks for that, everyone. Many thanks.
Appreciate it, Jeremy.
That brings us to the end of the question-and-answer session. At this point, I'll hand things back to Dale Andres, who may have some closing comments to share.
Thanks, operator. And once more, thanks to all of you for being on the call. I hope we've managed to address every question you had. If anything further comes up, we're here for you. And we certainly look forward to updating you on how our optimization and growth efforts are progressing, along with our fourth quarter results in the periods ahead. Thank you, everyone.
That wraps up the conference call for today. At this point, you're welcome to disconnect your lines. Thanks for joining us, and enjoy the rest of your day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Artemis Gold Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Artemis Gold Inc. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.