Home / Transcripts / Artemis Gold Inc. (ARTG) · August 6, 2026

Artemis Gold Inc. (ARTG) Earnings Call Transcript

August 6, 2026

TSX Venture Exchange CA Materials Metals and Mining earnings 45 min

Earnings Call Speaker Segments

Operator operator
#1

We appreciate everyone being on the line. I'm the conference operator speaking. Thank you for joining us for the Artemis Gold Second Quarter 2026 Results Conference Call. Please note that everyone is in listen-only mode at this time, and this conference is being recorded. Following the presentation, we'll open things up for questions. If you'd like to join the question queue, just press star then one on your telephone keypad. And if you require assistance at any point during the call, you can reach an operator by pressing star then zero. At this time, I'd like to hand the conference over to Meg Brown, Vice President, Investor Relations. Please go ahead.

Meg Brown executive
#2

Thanks, operator. Morning, everyone, and thanks for being on our Q2 earnings conference call and webcast today. Before we get started, I want to remind everybody that some of what we say on this call could be forward-looking, and we'd encourage you to look at our public filings and disclosures, including the cautionary language in yesterday's news release, where you'll find a more detailed discussion of the potential risks and uncertainties tied to those statements. At this point I'll turn the call over to Artemis Gold's CEO, Dale Andres. Dale, over to you.

Dale Andres executive
#3

Thanks, Meg, and I appreciate everyone taking the time to be on this call. Joining me today is our new CFO, Erik Marchand; our Chief ESG Officer, Candace Alderson; our Chief Business Development Officer, Tony Scott; and regrettably, our President, Jeremy Langford, is currently on a plane and can't be with us, though he'll be available for Q&A over the coming days if needed. As you can imagine, things are busy for Jeremy at the moment, and he and his team are making excellent progress. I'll walk you through the quarter's highlights, then hand the call to Erik to go over the financials before we open it up for your questions. On slide 4, Q2 was a record quarter on many fronts, including record production, record revenue, and record operating cash flow. Naturally, this was aided by a low all-in sustaining cost of $955 US per ounce of gold sold. We hit a remarkable milestone with the declaration of an inaugural quarterly dividend yesterday, which now rewards our shareholders with capital returns, and with more to come down the road. This comes after just over a year of being in production and while we're in the middle of executing our transformational growth, and I believe it shows our confidence in the strength and sustainability of our operating cash flows and our confidence in delivering the 1A and EP2 expansion projects as planned.

Dale Andres executive
#4

Phase 1A is now 57% complete and on track for tie-in and commissioning before the end of the year, adding 33% capacity to the processing plant. That means that in only a few months, we will start delivering the benefits of that project. The much larger EP2 project is progressing very well, and we recently commenced the start of major works construction, and that's ahead of schedule. We are in a very strong financial position as well, but we did take prudent steps this quarter to further protect the balance sheet during the EP2 construction period. On slide 5, the inaugural base quarterly dividend of 5 cents per share, announced yesterday, will be paid on September 9 to shareholders of record on August 19. This is consistent with our progressive dividend policy that we announced and introduced earlier in the year, and we expect the quarterly base dividend will increase to 8 cents per share in 2027, taking that up to 32 cents per share on an annual basis. Further, beginning in 2028, we expect to top up the quarterly base dividend by a variable amount, such that the total amount of dividends will approximate 40% of free cash flow.

Dale Andres executive
#5

That puts Artemis Gold in the company of top-tier peers who strike a balance between reinvesting for expansion and giving back to shareholders — and for us, we're doing that midway through our very first complete year of operations, which I believe may be without precedent. In any case, it's a significant milestone. Slide 6 presents our operating highlights for the quarter. We set new records across grades, recoveries, production, and sales, which shows what this asset is capable of delivering beyond expectations. And every bit of that came alongside a record 8 million hours worked with no lost-time incident. That's a remarkable outcome, and it speaks to the robust safety culture built throughout the whole organization — something I think all of us at Blackwater and Artemis can take pride in. Slide 7 shows a recent drone photograph of the open pit, which is advancing nicely. The initial batch of extra mining equipment meant to enable higher mining and processing rates is being put together at the site, and a new shovel plus 5 new haul trucks should be running by September, with 3 of those trucks already operating. Recoveries hit a record 92.2% during the quarter, driven by continuous enhancements in ore blending and ongoing optimization of the mill circuit, and from an ore delivery standpoint we're in a strong position for the remainder of the year.

Dale Andres executive
#6

We're focused on removing bottlenecks and boosting performance at the crushing, grinding, and leach circuits we already have, as we get ready for Phase 1A to come online later this year. Slide 8 shows a drone photo of the low- and medium-grade stockpile, which currently stands at roughly 23 million tonnes. Reconciliation from grade control drilling keeps indicating greater tonnages of low- and medium-grade ore than the mineral resource had forecast, and we're enlarging stockpile capacity to handle that. On the right you'll see a picture of one of our recently assembled 240-tonne haul trucks, and 3 of the 5 extra trucks are already in operation. Moving to slide 9, we've shown this slide several times to illustrate our industry-leading growth profile across the next 2 years, but I want to draw attention once more to the Phase 1A expansion, which is now just a few months from commissioning. Phase 1A is a capital-efficient step change that we're carrying out to upgrade the existing Blackwater processing plant. We're lifting nameplate capacity by 33%, from 6 million tonnes per annum processed to 8 million tonnes per annum, and beginning in 2027, Phase 1A will contribute substantially to our production and cash flow profile.

Dale Andres executive
#7

We anticipate running well above reserve grade material until the significantly larger EP2 project begins operation in 2028. Past EP2, we see enormous potential at Blackwater, and we keep pushing forward on every one of these fronts. Regarding Phase 1A, you will have noticed the news release we issued earlier this week outlining the progress achieved. As of the end of Q2 2026, Phase 1A stood at 57% complete and remains on track for commissioning in Q4 2026. So far, we have finished several key construction milestones on this project, among them substantial advancement on the Vertimill installation as well as the new tanks in our CIL circuit. Having settled the scope, which includes extra spares for operations, Phase 1A is now anticipated to finish at a capital cost of $120 million. That is modestly higher than the prior $110 million, yet it still reflects a very low capital intensity of $60 for each additional annual tonne of processing capacity, with obvious room for further optimization beyond 8 million tonnes per annum. Slide 11 illustrates the Vertimill building construction progressing nicely, and on the right side you can see the foundations for our shear reactors, which will sit directly beside our detox circuit.

Dale Andres executive
#8

You should also keep in mind that the plant upgrades — the shear reactors, the extra oxygen generators, and the reagent system improvements — should support gains in throughput and recovery while also bringing unit costs down. Moving to EP2 on slide 12, that expansion adds 13 million tonnes per annum of capacity beyond 1A, taking us from 8 million tonnes per annum at the close of this year to 21 million tonnes per annum in the second half of 2028. As a reminder, EP2 lifts gold output above 500,000 ounces annually, and those economies of scale deliver lower unit operating costs, which will solidify Blackwater's standing as one of the lowest-cost, highest-margin gold operations anywhere in the world — and that will carry on as it does today. Early works construction kicked off in January and is almost finished. Earlier this week we announced that major works construction has begun. That came ahead of schedule, with the first concrete pour on our ball mill foundation now done. It was the biggest single pour across the entire EP2 project, roughly 900 cubic meters of concrete, and it was finished successfully ahead of schedule.

Dale Andres executive
#9

For the processing plant expansion, site clearing and bulk earthworks are moving along faster than planned. As the drone photo on this slide shows — the one displaying that earthworks — I think it's worth taking a moment to reflect on that image. You can see, I believe, the sheer size and scale of the EP2 project relative to Phase 1A, which sits in the middle of the photo. Every piece of our long-lead equipment has been ordered. The 612-bed construction camp expansion is close to finished and should be fully online in the coming days. We've now obtained supply assurances from BC Hydro guaranteeing continued low-cost renewable hydropower supply at the expanded throughput capacity, so that's a great outcome. Slide 13 shows a couple of extra drone shots, including the bulk earthworks for the new primary crusher, which is coming along well, and the first concrete pour for the EP2 ball mill foundation, as I mentioned earlier. To sum up on EP2, I'd say that while it's still at an early stage, EP2 is progressing extremely well. The EPCM contractor is in place, our project delivery team has been expanded with several key additions — and they're great additions — and our early works strategy is definitely helping to set this project up for success and significantly de-risk the schedule going forward.

Dale Andres executive
#10

At this point I'll hand things over to Erik Marchand, who joined us as CFO not long ago, so he can walk you through the financial results for the quarter. Erik, the floor is yours.

Erik Marchand executive
#11

Thanks, Dale. Our second-quarter financial results set new records. Revenue came in at a record $433.6 million, adjusted net income reached a record of roughly $200 million, and adjusted EBITDA hit a record $285 million. Gold sales during the quarter also set a record at 78,126 ounces. Roughly 49,000 ounces went into the spot market, realizing an average price of $6,119 Canadian per ounce, while the remainder was delivered against our stream and hedge commitments — among that, about 23,000 ounces were delivered under the mandatory and discretionary hedge programs at a weighted average price of $2,995 Canadian. Going forward, we anticipate delivering comparable amounts under our hedge program in the third quarter, including the 7,000 ounces still outstanding under the discretionary hedge program. With Phase 1A ramping up later this year, a considerably larger share of our production will be sold at spot, which raises our exposure to today's strong gold price environment. More information about our hedge commitments appears in note 16 to the financial statements. Despite the effect of our streaming and hedging commitments, we achieved an ASIC margin of 71%. Stronger gold prices certainly played a part, but our low-cost operation is still the key differentiator, with ASIC of only $955 US per ounce in the second quarter.

Erik Marchand executive
#12

Those margins produced record operating cash flow for the quarter, at $208 million. We expect those strong cash flows to keep coming, which gives us the financial flexibility to fund both Phase 1A and EP2, and at the same time to begin returning capital to shareholders by declaring our first quarterly dividend. Growth capital came to $131.6 million in Q2. As planned, spending rises in the second half of 2026 as EP2 major works get underway. I'll go into more detail on that on the next slide, which covers our full-year capital guidance. That spending strategy also played a big part in our choice to put in place the put option strategy Dale referred to earlier. Moving to guidance, we are keeping the annual production and unit cost guidance for Blackwater that we announced previously. I would note, as we announced previously, that ASIC for 2026 should trend toward the higher end of the annual guidance range, mainly because of general inflationary pressures, including higher oil prices, which the company expects to partly offset via continuous improvement initiatives. On our annual capital guidance, nothing changes apart from a $10 million increase to the Phase 1A capital estimate stemming from a scope review on this fast-track project, which now takes in additional operating spares.

Erik Marchand executive
#13

We still need roughly $110 million to finish the $120 million Phase 1A expansion during 2026. Relative to our overall growth capital guidance for 2026 — a range of $685 million to $755 million — that bump isn't material, and we expect to cover it through operating cash flows. On the balance sheet side, we closed the quarter in an exceptionally strong financial position. Available liquidity at quarter-end totaled about $879 million, made up of $179 million in cash plus the entire $700 million accessible through our revolving credit facility. We also meaningfully de-risked EP2 this quarter, putting in place a gold put option strategy that shields operating cash flows across the first year of EP2 major works construction. That program spans 172,500 ounces, carries a strike price of $5,300 Canadian per ounce, and runs from July 2026 through June 2027 — giving us downside protection if gold prices fall while keeping full upside exposure to any rise in gold prices. Taken together, our balance sheet lets us fund growth ourselves while maintaining substantial liquidity, and we're continuing to return capital to shareholders at the same time. With that, I'll hand the call back to Dale.

Dale Andres executive
#14

Thanks, Erik. Beyond Phase 1A and EP2, we're pursuing several avenues at once to demonstrate Blackwater's full potential. The resource expansion diamond drill program is coming along nicely — 2 diamond drill rigs were active during the second quarter, and a third rig is being mobilized right now to broaden the program. Blackwater is a really big mineralized system, and we're testing far past the depths outlined before, with certain holes going beyond 1,000 meters. Updates on this program will come as assay results arrive, and as you'd expect, these holes are long and do take time, and an updated resource model will come later in the year, folding in this new information. On the mining side, we see a range of possible paths for bringing our unit rate down over the long term on costs, and technology in this area is shifting quite fast, and we're assessing numerous alternatives, among them electrification and automation options that might leverage our inexpensive hydro cost. On the processing side, the studies center more on growth past EP2, and the initial step there is demonstrating what can be achieved to get the most out of both the 1A and EP2 builds and infrastructure, and past that, we'll determine what the appropriate size of expansion for a possible Phase 3 would be.

Dale Andres executive
#15

Our regional exploration work has restarted as well, after pausing for winter and spring, and this year's first drilling is set for the Top Lake area using a single reverse circulation rig. That program follows up on anomalies we found in Q4 of last year, and the rig will subsequently head to targets located in the Van Tine area. So, to sum up and close out, let me once more draw attention to the record results and the tremendous progress achieved on our Phase 1A and EP2 projects over the quarter. In my view, that reflects both the performance and the quality of the teams running our operations and executing our projects. Our low all-in sustaining costs were a key driver of record cash flows and liquidity, and we have added further protection to the balance sheet through the put options Erik described, which deliver downside price protection across the 12 months of heavy capital spending — the first year of EP2 spend — while giving up no upside. EP2 has begun very well, and I want to remind everyone that Phase 1A is now close at hand, which will substantially lift both production and cash flow in 2027. Importantly, we have now become a dividend-paying company, with plans to steadily grow the return of capital to shareholders in the near term.

Dale Andres executive
#16

That brings our presentation to an end, so operator, we'll hand it over to you at this point for the Q&A.

Operator operator
#17

Thanks. We're going to start the Q&A portion now. If you'd like to get into the queue for questions, just hit star followed by one on your phone's keypad. A tone will sound to confirm your request. Should you be on a speakerphone, lift your handset first before you press any keys. If you want to take your question back out, press star and then two. Our first question is from Wayne Lam at TD Securities. Go ahead, please.

Wayne Lam analyst
#18

Thanks. Morning, everyone. Congratulations on a strong quarter. I just wanted to get a clearer picture of what drove the better grades this quarter, and whether you think there's a chance that holds up over the next few quarters.

Dale Andres executive
#19

Appreciate that, Wayne. In the second quarter, grade was — I'd call it — quite elevated. Across the first half of the year, we came in at an average of slightly above 1.7 grams per tonne. Our stockpiling strategy gives us considerable flexibility within the mine plan, and during the first half, especially in the second quarter, we managed to capitalize on that. I do expect grades to come down a bit — modestly lower — though still within that 1.5 grams per tonne range through the rest of the year, along with stronger throughput in the second half too. Those two factors should cancel each other out, and yes, we're in a strong position to hit our guidance for 2026.

Wayne Lam analyst
#20

Great, thanks. I just had a question about the work that's going into the resource update you have coming. You clearly already have a very substantial resource and a long mine life, so I'm curious whether that extra material at a lower cutoff simply contributes to the low- and medium-grade ounces that would be processed in the later years and extend the mine life, or whether it also provides some added flexibility and upside for processing grades over the medium term—allowing you to front-load a bit more of that higher-grade bucket?

Dale Andres executive
#21

That's a fair question, Wayne. Regarding the additional resources and the low- and medium-grade material, like I said, there's optimization potential we can tap past the 8 million tonnes per annum rate at 1A and past the 21 million tonnes per annum rate at EP2. Those additional resources and the stockpiled material certainly factor into that and let us optimize production further. It does give us added flexibility. I believe I've said this before, but if, as we expand the foundation and the footprint of our low- and medium-grade stockpile, we can segregate the highest-grade portions of it, that genuinely creates near-term opportunities for production optimization, even at the stated capacities — the nameplate capacities of both Phase 1A and EP2 — without additional optimization on throughput rates. There are a number of different levers we intend to pull as we optimize our plans over the coming months, and yes, we'll update the market once those are complete.

Wayne Lam analyst
#22

Great, thank you. Then perhaps just one final point regarding the revised scope tied to the improvements on the Phase 1A expansion — the Vertimill, for instance — does that also have to be duplicated for Phase 2, considering the two designs were meant to be quite alike? Would that be covered inside the EP2 budget?

Dale Andres executive
#23

To add one more point—and I believe I touched on this in my earlier remarks—Phase 1A was a fast-tracked initiative that we implemented ahead of the EP2 announcement. Upfront engineering on it was limited, so we moved directly into placing orders for the necessary equipment and executing 1A very rapidly. Regarding scope changes, much of that involved extra operating spares. All of those are fully captured within EP2. As a reminder, EP2 is comparable but uses a somewhat different processing train from Phase 1. It will feature two-stage crushing with a SABC circuit—a SAG mill, ball mill, and pebble crusher—which differs somewhat from our Phase 1A and Phase 1 design, where we have three-stage crushing and one ball mill with no pebble crusher. Those are the differences. There is no read-across whatsoever from the $10 million increase on 1A to EP2. We remain very comfortable with our budget and schedule for EP2.

Wayne Lam analyst
#24

Great, it seems everything is running smoothly. Nice work on a solid quarter, and good luck over the coming months.

Dale Andres executive
#25

Appreciate that, Wayne.

Operator operator
#26

Our following question is from Harrison Reynolds at RBC. Go right ahead.

Harrison Reynolds analyst
#27

Hello there, and good morning to everyone at Artemis. Congratulations on a solid quarter. I appreciate how much detail you gave us, and it's great to watch these projects move forward. Regarding 1A, once it's commissioned and tied in, when do you anticipate that 30% throughput lift to take effect? What's the timeline for ramping that capacity up to the new nameplate?

Dale Andres executive
#28

Thanks, Harrison. During Q4, we intend to commission Phase 1A and begin ramping it up. As we've noted before, an 8-day shutdown is presently scheduled so we can tie in that upgrade — the Vertimill along with the new cyclone pack needed to feed it. After that, commissioning gets underway. Ramp-up ought to be relatively quick. The Vertimill, the extra tanks, and the other upgrades are pretty straightforward. Those two factors will balance each other out: the downtime needed for the tie-in, and then the start of ramping throughput. We anticipate realizing the full benefit in 2027 — a full year at the 8 million tonnes per annum rate, or above it should we manage to optimize.

Harrison Reynolds analyst
#29

That's useful, thank you. Perhaps a quick follow-up regarding 1A. You brought up those choices for relieving constraints beyond the consolidated 21 million tonnes per annum. Do you foresee any debottlenecking chances at 1A at the same time ahead of EP2 starting up? Are there any studies you might aim to set in motion in 2027 or 2028 so that 1A delivers additional throughput?

Dale Andres executive
#30

The first priority is getting it operational at design capacity. That should be pretty straightforward and reasonably fast, in our view. We'll be pushing on that in 2027, and we aren't going to sit around waiting for EP2 before pursuing optimization beyond 8 million tonnes per annum. A few remarks on the 1A: our upgrades are mainly on the wet side of the circuit, while the dry side is really just straight debottlenecking — no major capital upgrades were needed there. We're already chasing those optimization opportunities at the front end and making sure the crushing capacity is there to hit first 8 million tonnes per annum and to exceed it. Progress on that work looks really good. At this stage I'm feeling good about our ability to try to drive beyond 8 million tonnes as 2027 progresses. Stay tuned. First we have to get it built, up and running, and commissioned, and then that will be our main focus together with finishing EP2.

Harrison Reynolds analyst
#31

Much appreciated. Thank you for letting me ask a couple of questions.

Dale Andres executive
#32

Appreciate it, Harrison.

Operator operator
#33

Don DeMarco from National Bank Financial has the following question. Go right ahead.

Don DeMarco analyst
#34

Thanks, operator, and good morning to Steven, Dale, and everyone else on the team. Steven, I want to begin with an update that came out earlier this week. BC Hydro gave assurances that it will supply power for EP2 run rates. I'm just wondering what that involves. Will BC Hydro be boosting the power distribution going to the mine? Does it call for upgrades to their power facilities? As part of the EP2 capex, what is the company going to do to make sure it can move up to that higher level of power delivery?

Dale Andres executive
#35

Thanks, Don. I might jump in here, and I'll invite Candace to add anything she feels she can. What I'd say is that BC Hydro is twinning the Northwest Transmission Line, with completion targeted for 2030. We've secured contracted power through the point when that twinning work will be finished, for the EP2 run rate. The assurances we sought from BC Hydro go further than that in case there's any delay in getting that infrastructure built — that work falls to BC Hydro, it isn't ours to do, and they've provided us with those assurances. Those are the assurances we mean. From a power delivery standpoint, we're still finalizing the details on BC Hydro's Glenannan substation. We don't expect anything major needs doing there. The transmission line we built for Phase 1 can fully wheel the power required for EP2 — no upgrade to that line is necessary. It all sits on our side. The work is really at the mine site itself, rather than with delivering power to site. I hope that gives you some color.

Don DeMarco analyst
#36

Thanks for that. I noticed the Q2 report also mentioned the variable dividend — 40% of free cash flow after 2028. Are buybacks something you're looking at too? Once the hedges roll off before 2028, how do you intend to put free cash flow to work, and what's the capital allocation plan?

Dale Andres executive
#37

Thanks for that. On the slide we reviewed, we did note the possibility of an NCIB or share buybacks potentially starting as soon as 2027. I believe we've just announced our first quarterly dividend, an inaugural one. Our plan is to raise that dividend beginning in 2027, taking it to 8 cents a share from the 5 cents we have now, and the board will review it as matters move forward — both the 1A ramp-up and the progress on building our project with EP2 — they'll examine that in 2027. Moving into 2028, we're simply noting that on top of the base quarterly dividend, we'll aim for 40% of free cash flow, to demonstrate that disciplined development. We keep assessing what comes after EP2, and we'll evaluate those opportunities for additional growth and investment, organically and perhaps beyond, along with returning 40 40% of that free cash flow to shareholders. Should there be nothing we wish to reinvest into growth at that point, we'll look at extra dividends and/or share buybacks on top of that 40% distribution of free cash flow. That is what our dividend policy and the shareholder return framework we laid out earlier this year set forth, Don.

Don DeMarco analyst
#38

Alright, many thanks, Dale. That covers everything on my end. Appreciate you fitting in my question.

Dale Andres executive
#39

I appreciate that.

Operator operator
#40

Jeremy Hoy from Canaccord Genuity has the next question. Please proceed.

Jeremy Hoy analyst
#41

Hello, Dale and the team. Thanks for fielding my questions. I believe I'll concentrate on the EP2 expansion. Regarding the contingency within the $1.44 billion budget, does it suffice to cover any present inflationary pressures that are affecting operating costs?

Dale Andres executive
#42

Thanks, Jeremy. There are a number of items I'd like to highlight. We had a very clear plan with EP2, and it fit well with carrying out our Phase 1A project to secure immediate cash flow and an immediate boost in production, while also running our early works program. As you may remember, back in September, when we announced the Phase 1A project, we placed orders for a ball mill that had already been built and a SAG mill, and the pricing was fixed at that point. Through our early works program, advanced engineering and procurement, and as we noted in our recent release, we have now ordered all of the long-lead equipment. Once again, locking in those orders and prices reduces our inflation risk. Obviously, we still confront inflationary pressures just like everyone else, and those would mainly involve fuel costs, transportation, and similar items, but at this point our capital estimate contains enough contingency to absorb that, and we have allowed for it through that contingency, and we keep searching for cost improvement opportunities to absorb any parts of the project that may be experiencing inflationary pressures. At this point, we are very comfortable with the $1.44 billion estimate we have released and, importantly, with the schedule.

Dale Andres executive
#43

On these projects, staying on schedule is the most effective way to keep costs in check, and on that front things have been going really well so far — very pleased.

Jeremy Hoy analyst
#44

Thanks, Dale, for that context. To build on the same point — you mentioned that the size of this expansion and the earthworks were fairly far along. Could you remind us how much geotechnical investigation was carried out, and therefore how confident you are in the earth quantities, and what percentage of the earthmoving is complete?

Dale Andres executive
#45

Jeremy and the team put in substantial effort on this, and they worked on optimization alongside our contractors and consultants, and in my view we did an excellent job of optimizing the earthworks. Our plan is to complete all of the bulk earthworks by the close of the third quarter, which means over the next 2 months. I don't have the precise percentage for that, but the bulk earthworks are mostly finished and we are well advanced. I think the photos we showed of the plant site make clear that we have already excavated for the SAG mill, a large concrete pour that we expect to happen this quarter, as well as the ball mill raft pour that we flagged, and the SAG mill represents the second biggest pour on the project. Simply by getting those two out of the way — typically the ball and SAG mills are the biggest pieces of equipment — we have taken that right off the critical path, and so I think that is great. Then we showed another photo displaying the earthworks around the crushing system with the new primary crusher, and that is progressing well.

Dale Andres executive
#46

That precise percentage isn't something I have on hand. Jeremy, we can get back to you on it, but yes, everything ought to be wrapped up by the close of September. No,

Jeremy Hoy analyst
#47

Appreciate that thorough answer. Thank you. One last item from me concerns throughput rates. A debottlenecking initiative has been under way. You noted that the crushing and milling circuits are the areas of focus. On grades for the second half of the year, you said roughly 1.5. Could you explain what matters most for reaching nameplate on throughput, and what level are you operating at right now?

Dale Andres executive
#48

Looking at what came through in our Q2 numbers, output was roughly 5.5 million tonnes on an annualized basis during the quarter, which puts us a bit below the 6 million tonnes we designed for. We more than compensated for that, of course, through considerably better grade and a meaningful lift in recoveries — we came in above 92% on recoveries — and those higher grades genuinely delivered a very, very solid quarter for both production and sales. We did highlight earlier this year some of the unplanned downtime we experienced. Part of that traces to design issues and shortcomings in, for instance, the CIL circuit — specifically our tanks, and in particular the agitators and the gearboxes that drive them. Every one of those agitators and gearboxes needs swapping out for larger units. We also need to carry out structural steel upgrades on our tanks. The new tanks being installed for Phase 1A, clearly, are already built at that larger size with the right steel and structure in place, but we have to work methodically through our existing 11 tanks constructed with Phase 1. That covers everything from our pre-aeration and leach tanks to our six CIL tanks and our two detox tanks, replacing those and doing structural upgrades so bigger agitators and gearboxes can be accommodated.

Dale Andres executive
#49

That work is underway. We're making our way through it. It's taking a bit longer since the equipment has to be ordered and we have to wait for delivery, but you can't shut the entire circuit down. We're still running, and running well, but that's one concrete example of what we're doing. We do expect that work to be largely finished before the end of the year, and then we do get the additional tanks with 1A. We don't anticipate any kind of — I think it's just steady improvement from where we are today right through to the startup of 1A over the next 4, 5 months.

Jeremy Hoy analyst
#50

Got it. All right, I appreciate your answers in that detail and for fielding my questions. I'll return to the queue.

Dale Andres executive
#51

I appreciate that, Jeremy.

Operator operator
#52

Andrew Mikitchook of BMO Capital Markets has the next question. You're up.

Andrew Mikitchook analyst
#53

Hi, team. Congrats on a very solid Q2 and a great trajectory. I’ve just got one situational question. All of us are dealing with different levels of wildfire risk across Canada and the US, and I’m sure everyone listening remembers that you dealt with this during the past two summers. From what I recall, the area around the site has already burned fairly extensively, so there’s probably no additional danger near the site. What are you observing regarding the risk to your access road and the risk to your power line, based on the fire activity you’re seeing in that region?

Dale Andres executive
#54

Thanks, Andrew. I think that's a perceptive remark and question, in the sense that at the site, and particularly with our EP2 project, a fair amount of the area has been cleared, and, as you noted, we were affected by fires for a couple of seasons — not last year, but the 2 years before that. I'll look for some wood nearby here because I'll try knocking on it. So far, we've done very well. You'll see plenty of reports in Canada and the US about large fires. We haven't encountered fires of that kind right around us. There have been a couple of small ones, 20 kilometers away, that were dealt with and extinguished very quickly. I don't want to claim we're out of the woods yet. Things can change. It was a dry winter, with low snowpack and a fast melt, so conditions can dry out quickly. Through June and July, we've done very well, and we've actually had cooler weather and rain. If anything, some of that rain has affected our mining and our roads and our traction and similar things, rather than our worrying about fires at the moment.

Dale Andres executive
#55

That could shift. We are thoroughly ready. We stay in touch with the BC Wildfire Service on a regular basis. They are quite familiar with us. We have collaborated closely, and I believe we are well positioned to handle whatever might come our way during the next couple of months. So far, things are good, and I think we have come through really, really, really well relative to, sadly, certain other parts of the province and the region that have not been as fortunate. So far, good.

Andrew Mikitchook analyst
#56

All right, I appreciate the update. Once more, congratulations on such an impressive trajectory. Continue doing the right things. I’ll sign off now.

Dale Andres executive
#57

Thanks for that, Andrew — I appreciate it.

Operator operator
#58

That brings the Q&A portion to an end. I'd now like to hand the floor back to Dale Andres, who may have some closing comments for us. Please go ahead.

Dale Andres executive
#59

Appreciate it, operator, and once more my thanks to each of you for being on the call. Hopefully we've managed to address every question you had. Should anything else come up, including from Jeremy, we're here to help with follow-ups. We're eager to share updates on how our optimization and growth efforts are going. Thanks to you all.

Operator operator
#60

That concludes the conference call for today. You're welcome to disconnect your lines now. Thanks for joining us, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Artemis Gold Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Artemis Gold Inc. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.