Artemis Gold Inc. (ARTG) Earnings Call Transcript
November 4, 2026
Earnings Call Speaker Segments
We appreciate everyone being on the line. I'm the conference operator, and I'd like to welcome you to the Artemis Gold Third Quarter 2026 Results Conference Call. <<operator_script>> This call is being recorded. At this point, I'll hand things over to Meg Brown, Vice President, Investor Relations. You may proceed.
Thank you, operator. Good morning, everyone, and welcome. Thank you for joining our Q3 earnings conference call and webcast. Before we begin, I would like to remind everyone that certain statements made on today's call may be forward-looking, and we encourage you to refer to our public filings and disclosures, including the cautionary language in yesterday's news release for a more detailed discussion of potential risks and uncertainties related to these statements. I will now hand the call over to Artemis Gold's CEO, Dale Andres. Over to you, Dale.
Thanks, Meg, and I appreciate everyone making time to be on the call. Joining me today is our President, Jeremy Langford, who is dialing in, so there may be a bit of a delay when we get to answering questions. Also with us are our CFO, Erik Marchand; our Chief Business Development Officer, Tony Scott; and our Chief Sustainability, External Relations and Governance Officer, Candice Alderson. I'll walk you through the quarter's highlights, then hand things to Jeremy to go over the growth projects, and then to Erik for the financials, after which we'll open the line for questions. Turning to Slide 4, Q3 was a strong quarter on many fronts. We turned out just under 70,000 ounces of gold during the quarter and are well placed to hit our full year guidance. We continue to rank among the lowest cost gold mines, with all-in sustaining costs of $1,048 per ounce of gold in the third quarter. Phase 1A now stands at 77% complete and remains on track for tie-in and commissioning by the end of the year. As a reminder, that will add 33% capacity to our processing plant. EP2 is coming along well too and remains on schedule for completion in the second half of 2028.
Construction on the major works got underway in August of this year, ahead of schedule, and Jeremy will provide an update on where both 1A and EP2 stand a bit later in the presentation. In the quarter, we announced a deal to acquire Vista Gold, which adds an advanced stage gold development asset of scale in the favorable mining jurisdiction of the Northern Territory in Australia. Slide 5 shows our operating highlights for the quarter. Production, as I mentioned, of close to 70,000 ounces of gold brings us to over 205,000 ounces year-to-date. We achieved higher mill throughput compared to the first half, with close to 1.5 million tonnes of ore through the plant. Debottlenecking and improvement projects are continuing, including rectification of deficient contractor work on tanks in the leach circuit, which is scheduled to be complete at the same time as the Phase 1A commissioning. Grades remained strong in the quarter, averaging 1.55 gram per tonne, and recoveries were close to 90%. I'm proud to say all of this was achieved with a record now 8.9 million hours worked without a lost time incident. Slide 6 shows a recent drone photo of the open pit. And we recently had a visit with analysts and other investors, and I said at that visit, how it looks at how it operates and it looks great.
More mining equipment has come in and is now operational, helping us achieve greater mining and processing rates, with one new shovel plus five new haul trucks brought in over the quarter. On top of that, we are moving toward self-performing our production drilling and blasting, which is underway and progressing well. We've put in significant effort to debottleneck and boost performance across the existing crushing, grinding and leach circuits, anticipating Phase 1A's arrival, and those results are becoming evident now. At the 8 million tonne per annum rate required for Phase 1A, the crushing circuit has been proven, and we're observing better plant availability and reliability as we keep working through assorted mechanical, structural and process upgrades. At this point I'll hand the call to Jeremy, who will walk us through the Phase 1A and EP2 growth project updates. Jeremy, over to you.
Thanks, Dale, and good morning, everyone. At the close of the third quarter, Phase 1 stood at effectively 80% complete, and it remains on track for commissioning as planned. To date, we have achieved a number of significant construction milestones on the path to completion. As the photo shows, the Vertimill building is close to finished, the new pre-aeration and leach tanks are done, and both the shear reactor pump house and the shear reactors have been installed. Electrical cabling and piping installation throughout the 1A expansion scope is well advanced, and the new cyclone cluster, which connects to the new Vertimill, will go in during the Q4 plant shutdown that's coming up. A 33% increase in plant throughput is expected to translate into significantly higher gold production in 2027. Guidance on both production and cost for 2027 will be issued in early January. We can move now to slide 8 and EP2. EP2 represents an increase of 13 million tonnes per year on top of the 8 million tonne per year capacity of the 1A processing plant, and it is expected to raise overall asset throughput to 21 million tonnes per year by the second half of 2028. As a reminder, EP2 lifts gold production to north of 500,000 ounces a year, which gives Blackwater economies of scale that positively benefit unit operating costs.
Obviously, this solidifies Blackwater's standing as among the lowest-cost, highest-margin gold operations anywhere in the world. The key milestones for EP2 development take in early works construction, and that is finished, and it includes adding a new 612-bed construction camp, which delivers extra accommodation capacity to back the expanding construction workforce. Plant bulk earthworks are quite far along, and the SAG and ball mill glass foundations have been completed. In addition, the first lift for the ball mill pedestals has been poured, and the SAG mill pedestal's first lift was ready for pouring during the final days of October. Civil works on the leach and CIP ring beams are broadly moving ahead nicely, and every long lead equipment item has been ordered. Crucially, that covers the SAG and the ball mill. Let's go to Slide 9 now, please. And you will notice from the recent drone shot illustrations, which include the EP2 footprint on the left and show the ball and SAG mill foundations in progress and the dark circle shape tank wind beans emerging from the ground. On the right of the screen as well, a close-up shot of the SAG and ball mill foundations. Turning to Slide 10, we have provided a couple more photos, including the leach tank ring beam foundations on the left, and another recent drone shot on the right-hand side of the presentation showing the outline of the plan view of Blackwater EP2's impressive footprint.
There's one more item I want to mention, on top of what everyone else has covered, for all of you: we recently put an image gallery up on our site that displays how construction on EP2 is coming along, and I'd urge each of you to take a look and, I suppose, join us on the journey as the EP2 project moves forward. As of today, I can report that while we're still at an early stage in the project schedule, EP2 is coming along very nicely. The project is still within budget, with an estimated capital cost of CAD 1.44 billion, and our 13 million tonnes per year processing increase remains on track for the planned completion in H2 2028. At this point I'd like to pass things to Erik, who will walk you through our quarterly financials. Erik, the floor is yours, mate.
Thanks, Jeremy. Our third quarter turned in yet another round of solid financial performance. Revenue came in at CAD 357 million, adjusted net income was CAD 158 million, adjusted EBITDA reached CAD 222 million, and adjusted EPS was CAD 0.66 per share on a diluted basis. On top of that, we kept up our strong cost performance, with AISC of USD 1,048 per ounce for the quarter. Alongside solid production levels and favorable realized gold prices, that gave us healthy AISC margins and robust operating cash flows of CAD 183 million during the quarter. We sold a little more than 67,000 ounces of gold in the quarter, with most of it sold into the spot market at an average realized price of CAD 6,021 per ounce. The remainder went out under our mandatory and discretionary hedge programs and gold stream commitments. Notably, we finished the final deliveries under our discretionary hedge program in the quarter. At present, 111,000 ounces remain under our mandatory hedge program, and those contracts mature over the next 8 quarters at a weighted average price of CAD 2,834 per ounce. As a reminder, our MD&A contains a detailed quarterly schedule of the remaining hedge deliveries. Growth capital totaled CAD 180 million in the quarter, which brings year-to-date spending to roughly CAD 400 million.
As we planned, capital spending should rise over the rest of 2026 as the major works at EP2 keep ramping up. I'll give you more detail on the capital spending outlook when we get to our 2026 guidance a few slides from now. Moving to the balance sheet. We ended the quarter with considerable financial strength and flexibility. At quarter end, total available liquidity stood at roughly CAD 891 million, which included CAD 191 million of cash and the full CAD 700 million available under our revolving credit facility. We're still in a strong financial position and have taken prudent steps to protect the balance sheet while EP2 is under construction. Our gold put option strategy, first put in place in Q2, keeps providing protection against lower gold prices. Since last quarter, we've expanded the program by an additional 49,500 ounces, covering most of the Q3 2027 spot sales at a strike price of CAD 5,500 per ounce. As of November 1, we held put options covering 173,000 ounces of gold, with strike prices ranging from CAD 5,300 to CAD 5,500 per ounce and expiry dates running from November 2026 through September 2027. Importantly, this strategy sets a floor on gold prices for the covered ounces while keeping our full exposure to higher gold prices.
Broadly speaking, our balance sheet gives us the financial flexibility to push our growth initiatives forward, while keeping plenty of liquidity and continuing to give capital back to shareholders. After paying our first quarterly dividend of CAD 0.05 per share on September 9, we announced this morning our second quarterly dividend of CAD 0.05 per share, which is payable on December 8 to shareholders of record as of November 17. That shows our confidence in how strong and sustainable our operating cash flows are, and it aligns with the progressive dividend policy we rolled out earlier this year. Going forward, we intend to raise our base quarterly dividend to CAD 0.08 per share in 2027, which works out to an annualized dividend of CAD 0.32 per share. Now to guidance. At Blackwater, we are keeping the annual production and AISC guidance we announced previously. I'd also point out that we anticipate full year AISC landing at the very top of our guidance range, which reflects wider inflationary pressures, including higher diesel prices, and we are working to partly offset that through better operating efficiencies and cost management. On capital expenditures, as noted earlier, we expect Phase 1A and EP2 spending to be heavily weighted toward the back end of the year.
We're keeping our guidance for the full year as it stands, though given how expenditures are currently timed, we do expect growth capital to land at the low end of that range. With that said, I'll hand the call back over to Dale.
Thanks, Erik. Even though this slide has appeared a few times already, it's worth presenting once more to emphasize the growth profile that leads our industry. Commissioning of the Phase 1 expansion is now only weeks off, and the significantly bigger EP2 project is now under two years from reaching production. Past EP2, we see enormous potential in Blackwater, and we keep pushing forward on every one of these fronts. And lastly, the addition of Mt Todd in Australia, which we expect to deliver a large-scale, long-life gold project in a Tier 1 jurisdiction. Crucially, that gives us a route to becoming a producer of one million ounces per year. On Slide 15, as I mentioned, we are also pursuing several fronts at once to show what Blackwater can fully deliver past Phase 1A and EP2. We are striving to lengthen the mine life and anticipate giving an update on our resources and reserves in the first quarter of 2027, along with a newly optimized mine plan, and that plan will rely on higher metal price assumptions and will also incorporate recent resource expansion drilling data together with current grade control reconciliation results. In Q3, the regional exploration drill program followed up on anomalies found in the earlier Top Lake program and on first-pass drilling of targets in the Van Tine and Johnny Lake areas, and we have follow-up drilling scheduled in Q4, especially at Top Lake.
Multiple studies are underway regarding additional growth possibilities at Blackwater past EP2. Those possibilities involve debottlenecking Phase 1A as well as EP2 in order to reach 25 million tons per annum — that work is being studied right now — plus the chance to add more capacity through a future new Phase 3. Our top priority stays the running of the Blackwater mine and the delivery of the Phase 1A and EP2 expansion projects, but buying Mt Todd gives the company more optionality to carry on what I think has been a remarkable growth trajectory and, as I mentioned, offers a pathway toward producing 1 million ounces of gold per year. Mt Todd is a rare asset, and we notice similarities to Blackwater at the time we acquired it back in 2020. With more than 10 million ounces of contained gold in mineral resources, it can be developed at meaningful scale, and we believe we have the ideal team to do it. It sits in a stable, mining-friendly jurisdiction, and it has previously been permitted for the scale of operation we are considering. The acquisition should close in the first quarter. And after closing, we plan to give an update on the proposed development plan for Mt Todd.
To close things out, I'd like to draw attention to the strong results we delivered this quarter, which came from robust grades, steady recoveries, and better performance across the plant overall. Our balance sheet is in very good condition, backed by solid operating cash flow and safeguarded by a sensible put option strategy that offers protection on the downside through this period of heavy capital spending while — and this matters — not sacrificing any upside. As Jeremy mentioned, we're making very good headway on both Phase 1A and EP2. And finally, and significantly, we've now reached the point of being a dividend-paying company, following the announcement made earlier this morning, with intentions to steadily grow the capital returned to shareholders in the near term. That brings our presentation to a close, and I'll hand things back to you, operator, for the Q&A.
<<operator_script>> Our first question is from Harrison Reynolds of RBC.
Congrats on a solid quarter, and thanks for the updates on the projects. Could you walk us through the puts and takes in the cost structure through year-end and as we head into 2027? On the positive side, how meaningful will the throughput uplift from Phase 1A be? And what are you seeing from the ongoing processing optimization work? And is that enough to offset what we're seeing in terms of inflationary pressure?
Yes. Thanks, Harris. I mean, we're seeing the same broad inflationary pressures as everybody else. I do believe that we have — not only with Phase 1A moving toward 2027. Obviously, that's going to support economies of scale. But we also have additional efficiency initiatives and optimization initiatives, as you mentioned, including the tank upgrades. We're off to a strong start in the fourth quarter. And I think that should carry on, obviously, into 2027 once we tie in and commission Phase 1A. I'd just like to point out, and we included this in our press release, that the plant will need to be down for a bit more than a week in early December. Right now we've got that scheduled for December 1, so the first week of December. And after that, Vertimill and the new cyclone and tanks will be commissioned, and those should ramp up pretty quickly. So the real benefit from Phase 1A is not going to show up in the fourth quarter. Again, with the stability we're seeing in the current operation and the ramp-up in the back half of December, we see a solid quarter in Q4 from a cost perspective, but the real benefit of Phase 1A comes in 2027.
Understood. Regarding the Phase 2 expansion, it's encouraging to see the progress, and it was nice to witness it directly earlier this year. Could you give us an update on the critical path from now through year-end 2028? Also, what do the team consider the biggest schedule and cost risks, and how will those be mitigated?
I'll simply state that I'm quite pleased with how things have gone so far and with announcing major works from August onward. That said, Jeremy, I'll hand it over to you on that point.
Thank you. Harris, we've really taken a lot of risk out of the critical path, largely because we procured quite early in the program. In that first phase, the ball mill and the SAG mill have already been delivered, and every piece of long-life equipment has been ordered. There are some synergies for us between 1A and the EP 2 components. So overall, I feel fairly good about where procurement stands today. We keep managing and watching — and I believe I've said this before — the global strain on electrical infrastructure: switchgears, switch rooms, transformers, where other industries in the technology sector appear to be capturing the lion's share. But we ordered our equipment early enough to stay on track across the board and mitigate as needed. Cost pressures, like the ones Dale mentioned earlier — the oil price rising and diesel costs — do affect the project, since we're on the main power line less than everyone else really and depend on diesel fuel for most activities. Still, we keep that under control through shorter-interval management. And with the winter months approaching, it's really about keeping our near-term goals and milestones within reach and kicking them off as we finish 2026 and head into 2027.
The next person to ask something is Jeremy Hoy of Canaccord Genuity.
The first question is a follow-up to what Harrison asked regarding 2027 costs. You said Phase 1 should ramp up very quickly to the 8 million tonne per annum level. Should we expect that level to be sustained from the beginning of 2027, or is some ramp-up through Q1 more likely? No. Jeremy can address the Vertimill specifically, but we anticipate a fairly straightforward tie-in. The largest task for commissioning Phase 1A involves swapping out the cyclone pack. Once that is complete, ramping up the Vertimill should happen fairly quickly. So I do expect us to reach the 8 million tonne per annum rate starting in Q1. There may be some commissioning in early January, possibly, but I don't — it won't be material for the year in 2027. Jeremy, I don't know whether you'd like to add any color to that.
I agree with Dale on this, Jeremy. As you've probably heard me mention before, the Vertimill is essentially just a pump plus a tank, and tying those into the existing milling circuit and the Phase 1 plant isn't especially complicated. We all recognize, of course, that we'll need to figure out how to run a plant that's larger and a bit newer, if that makes sense. So those are challenges we always deal with. That said, our training and the migration of items like the control system and the new operating philosophy have been going on for a good while now. So we're reducing that risk as much as we can. And we're heading into the snowy part of the year and it's gotten a little colder. So how the asset behaves shifts somewhat from time to time and with the seasons. And this year we're adding a new trick to it. So I think we're doing everything we can, and we'll keep you posted if we learn anything different.
All right, great. We're going to move around a bit here. Previously, you've talked about possible variable dividends or buybacks too. Could you explain what would set either of those off and how you'd weigh returns to shareholders against EP2 and Mt Todd funding?
Yes, and thanks for that, Jeremy. We're very pleased to be announcing this second base quarterly. As I believe we've indicated, our intention — and of course this remains subject to approval from the Board — is to lift the base quarterly dividend to CAD 0.08 per share each quarter in 2027. On an annualized basis, that works out to CAD 0.32. We're really only just beginning the larger EP2 spend, so I'd rather not speak to share buybacks. Naturally, it hinges on the gold price, which has been somewhat volatile of late in 2027. But as we move into 2028 and the EP2 project begins to ramp up, beyond that higher base dividend of CAD 0.32 per year, I think there will be substantial capacity — again, naturally, depending on the gold price — to look at a variable dividend above the base, on top of the base, to look at possible share buybacks, and to push forward not only Mt Todd but also additional expansion projects at Blackwater. We're going to be a producer of more than 500,000 ounces. Our hedges will have been cleared by the third quarter of 2028, and we'll be in a strong financial position, obviously, depending on the gold price.
So Jeremy, I think everything we just went through can be taken into account.
Alright, and it's nice to see gold trading above CAD 4,000 again today. My final question concerns silver sales. During Q3, every sale flowed into the stream along with those spot transactions. Is the silver sitting in inventory, or are stream deliveries weighted toward the front? I'd just like some clarity on what to expect quarter over quarter regarding spot versus stream sales.
I'll pass it along to Erik so he can answer that.
Yes, Jeremy, much of that relates to how silver is recovering right now, along with gold production overall. So we did change the silver stream to a fixed ratio, and at this point it really is just a timing difference that we expect to reverse later on and sort of settle into a ratio closer to 50%.
That wraps up the Q&A portion. I'll now hand the conference back to Dale Andres for any closing comments. Please go ahead.
Thanks, operator, and once more, thanks to all of you for being on the call. We hope we got to every one of your questions. We're around for any follow-up, and we look forward to bringing you updates on how our optimization and growth efforts are going in the quarters ahead. Thank you.
That concludes the conference call for today. Your lines can now be disconnected. We appreciate your participation, and we hope you have a pleasant day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Artemis Gold Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Artemis Gold Inc. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.