Artemis Gold Inc. (ARTG) Earnings Call Transcript
May 7, 2026
Earnings Call Speaker Segments
We appreciate everyone being on the line. I'm the conference operator speaking. You're welcome to the Artemis Gold conference call covering first quarter 2026 results. Please note that everyone attending is in listen-only mode and this call is being recorded. Once the presentation wraps up, we'll open things up for questions. If you'd like to enter the question queue, press star followed by one on your phone's keypad. And if you require help at any point during this call, pressing star then zero will connect you with an operator. At this time I'll hand the conference over to Meghan Brown, Vice President Investor Relations. Meghan, the floor is yours.
Thanks, operator. Morning, everyone, and welcome. Appreciate you being here for our Q1 conference call and webcast. Before we get started, a quick reminder that some of what we say today may be forward-looking, and we'd encourage you to look at our public filings and disclosures, including the cautionary language in yesterday's news release, for a fuller discussion of the risks and uncertainties that could affect these statements. With that, I'll turn things over to our CEO, Dale Andres.
Thanks, Meg, and I appreciate everyone taking the time to be on this call. Joining me today are our President, Jeremy Langford; our CFO, Gerrie Westhuizen; our Chief Business Development Officer, Tony Scott; and our VP Finance, Eric Marchand. Jeremy and Jeremy will help present the quarter's highlights along with me, and after that we'll open things up for your questions. Turning to slide four, there are a number of important updates for the quarter worth highlighting. First, we saw strong performance at Blackwater on the open-pit mine, with record mining rates during the quarter and strong grades continuing. Although we experienced an unplanned mill shutdown in March, we bounced back quickly, and record recoveries helped partially offset the reduced tonnes milled. We also succeeded on several other fronts this quarter, chiefly by advancing our organic growth initiatives, including the Phase 1A expansion, which is running concurrently with a much larger EP2 project. Phase 1A stands at 34% complete and remains on track for tie-in and commissioning by year-end, adding 33% capacity to our plant. As a reminder, this expansion is incredibly capital-efficient, at a cost of just $55 per tonne of annual throughput.
The EP2 project, which is considerably bigger, is likewise moving along nicely and — this matters, I believe — was just designated a priority major project by the Province of BC. Work got underway in January on the early-stage activities, while construction of the major works is set to start in Q3 of this year. Engineering and procurement have advanced considerably, and most of our long-lead items have now been ordered, which takes a great deal of risk out of the schedule. As noted in our news release, the ball mill components are already on their way to Blackwater, a terrific spot to be in at this point in the project. Jeremy will go into more detail on this, but progress to date has simply been excellent, and I really want to commend the team for everything accomplished so far. Turning to finances, we strengthened the balance sheet substantially in Q1 through a $450 million corporate bond issued on very attractive terms, and with the entire $700 million revolving credit facility balance now accessible as risk mitigation. In the first quarter we announced an inaugural dividend policy, reflecting our confidence in the ability to fund all of our organic growth through operating cash flows over the next 2.5 years, and importantly, it sets out our longer-term strategy for returning capital to shareholders, with our first base dividend payment expected in the third quarter.
Slide five presents the operating highlights for the quarter. As I mentioned, we set a new record for tonnes mined, and we delivered high-grade ore to the mill, with grades averaging 1.59 grams per tonne gold during the quarter. The plant processed just over 1.3 million tonnes in Q1, and we produced just shy of 62,000 ounces of gold. That figure is lower than we originally anticipated because of the unexpected failure of the ball mill gearbox. Even so, our team responded quickly to restore full operations. As I said earlier, the lower-than-expected mill throughput was partially offset by both continuing high grades from the mine and record recoveries of 90.6% for the first quarter, which reflects ongoing improvements in ore blending and continued optimization of the mill circuit. From an ore delivery perspective, I do believe we're well set up for the rest of the year. Slide six shows a recent drone photo of the open pit and our current ore stockpile. We continue to see more low- and medium-grade material than estimated in the reserve, and our stockpile for future processing is now approaching 20 million tonnes, which you can see there in the foreground.
Like I said, we had more mining tonnage — it rose 7% versus the prior quarter — partly because of productivity gains at the mines, such as adding double-sided loading to our shovels and hot seating on the haulage trucks. At the mill, our focus remains on reliability and optimization of the plant, which includes permanent structural and equipment fixes in certain plant areas, like the CIL circuit, and plans are now in place to tackle and fix these design deficiencies permanently. Moving to slide seven and looking forward, Blackwater is in the midst of an exciting growth phase; we intend to reach gold production above 500,000 ounces annually by the end of 2028 via continued optimization of the existing plant, delivery of Phase 1A — which is coming quite soon, in the fourth quarter of this year — and finishing EP2 construction in the third quarter of 2028, then ramping to full capacity by year-end. Past EP2, we truly believe Blackwater holds tremendous potential. We're progressing studies on a range of initiatives that will feed into our strategic planning process as we evaluate both life extension and additional growth opportunities beyond EP2.
I'll hand things over now to Jeremy, who'll give us an update on where things stand with Phase 1A and EP2. Jeremy, over to you.
Thank you so much, Dale, and good morning to all of you. Progress on Phase 1A is going nicely. Our engineering, procurement, and construction work has moved forward consistent with the plan, and every one of the major procurement packages has now been committed, including the 3.5 MW Vertimill. We've also already commissioned a few of the minor components that I referenced during the last webcast. In Q1, the foundation civil works and the concrete pours for the Vertimill in the mill building were finished, and the oxygen plant foundation work was finished as well. Equipment for Phase 1A should help enable additional optimization of the processing facility that already exists and will be introduced in stages, with Phase 1A completion targeted for Q4 of this year. I'm happy to say that Phase 1A overall, as Dale mentioned a moment ago, stands at roughly 34% complete. Looking ahead, we anticipate reaching several key milestones related to the 1A expansion over the coming stretch through mid-year and even into Q3. To be sure, we aim to wrap up the engineering design and drafting before Q2 ends, and we've just started erecting tanks on site for the new tanks. We will also be starting construction of the Vertimill building during the Q2 period as well. As a reminder, since this is a brownfields expansion, the team has been actively exploring doing certain works on an opportunity basis without affecting the facility that is currently operating.
Like Dale said, Phase 1A gives us remarkable capital efficiency — roughly 33% more throughput capacity on top of the infrastructure we already have, for just $110 million. We remain on schedule to deliver these facilities as we progress toward 8 million tonnes per annum by the latter part of 2026. If we could turn to slide nine now. Early works got underway in 2026, and major works construction is slated to kick off in Q3 of this year and run for about 2 years. Beyond the orders for the 18 MW SAG and ball mills, which we placed in Q3 last year, we've also ordered a number of other long-lead items, among them the gyratory crusher, secondary and pebble crushers, CIP cells, plus the oxygen plants and sulphur burners. With those orders in place and delivery times locked in, in our view this clearly takes risk out of the construction schedule. Our attention has been mostly on moving the construction camp forward — the new construction camp, that is — since it lets us scale up the construction workforce far faster than usual and as needed once we shift into full construction activities later this year. To date we've already built circa over 500 rooms, and those are in advanced stages of commissioning across different tranches.
We expect to bring on roughly another 100 rooms before we reach the middle of the year, and on the accommodation side things are where they should be and looking solid. EP2 definitely changes Blackwater — it takes the operation up to over 500,000 ounces of Au each year and makes Blackwater clearly one of Canada's biggest gold mines. To sum up, I can tell everyone that both growth projects — the 8 million tonne Stage 1A and our new EP2 plant at 13 million tonnes per annum — have moved forward nicely, and the owners along with the engineering hybrid teams have together met their near-term goals so far. I'm happy to say it has been very solid, and we look forward to giving everyone a further update at the next quarterly update. With that, I'll pass it back to Dale. Dale, the floor is yours, mate.
Thanks for that, Jeremy. Beyond Phase 1A and EP2, there's clearly meaningful extra optionality and upside at Blackwater. We're pushing forward with a range of optimization studies aimed at greater efficiency, reduced unit costs and, importantly, additional production growth. On the mining front, we're examining shovel electrification, haulage fleet automation and conveyor alternatives for moving waste. The main purpose of these projects is to bring down our unit operating costs. Just as importantly, we're still assessing a Phase 3 plant expansion — what the best timing and scale would be — and we'll move that forward over the course of the year. In late March, we began a diamond drilling program focused on extensions of the Blackwater deposit to the north and east of the current mineral reserve pit design. The deposit is still open at depth and in several directions, and the drilling is meant to assess that potential further. We're drilling to much greater depths than earlier programs did, testing extensions down to 900 meters or more. Later in the year, we plan to refresh the resource block model to capture this new drilling along with recent grade control knowledge from the operation. Lastly, a regional drill program is now underway to test high-priority district targets.
During winter we paused our drilling activity, and with trails in our area beginning to dry out, we're going to get back to drilling now. At this point I'd like to pass things along to Gerrie, who will walk through the quarter's financial highlights. Gerrie?
Thanks, Dale, and good morning everyone. I think it makes sense to start by reminding you that unless we say otherwise, most figures I'll cite are in Canadian dollars. For the first quarter, net revenue came in at $315 million, adjusted net income was $130 million, and adjusted EBITDA reached $176 million. In that quarter, the average realized price we got for gold ounces sold on the spot market exceeded $6,570 Canadian per ounce. Thanks to our low all-in sustaining cost, relative to peers, we produced $128 million in operating cash flows. As that last shareholder will remember, we gave details on our quarterly hedge delivery schedule, and it should come as no surprise that we had an unusually large hedge delivery this quarter — $25,000 under our mandatory hedge program, tied to our original project loan, plus a further 7,000 ounces under our discretionary hedge. Put differently, we delivered more ounces into hedges this quarter than we did into the spot market. Even so, we still achieved a solid all-in sustaining margin of 63% against cash revenue. The slide here sets out the hedge delivery profile for the rest of 2026.
Looking at it relatively, we anticipate selling a significantly larger share of what we produce on the spot market going forward than was the case during Q1. All told, we spent roughly $97 million on capital expenditure in Q1, with the largest portions falling into the EP2 and other categories — and just as a reminder for everyone, other consists mainly of our water and tailings infrastructure. For FY 2026, both Phase 1A capital and EP2 capital are back-end weighted and will climb as we move into the summer and across the remainder of 2026. Moving to slide 12, if we turn our attention to guidance, we are keeping the annual guidance at Blackwater for production that we previously announced, with full-year output projected between 265,000 ounces and 290,000 ounces of gold produced, at an all-in sustaining cost of $925 US to $1,025 US per gold ounce. I would note that all-in sustaining cost for 2026 is anticipated to trend toward the upper end of that guidance, largely because of general inflationary pressures, among them higher oil prices, which the company expects to partly offset via continuous improvement initiatives. Consistent with our growth strategy and the Phase 1 and EP2 plans we announced during the latter part of 2025, we expect to spend a total of approximately $670 million to $745 million in capital expenditures overall in 2026.
Moving to the following slide, as Dale said before, during Q1 we announced and completed a $450 million corporate bond offering. It was oversubscribed by 3.5 times, and it was also the first Canadian mining bond issuance in over a decade, plus the largest B-category Canadian dollar issuance in roughly 14 years. With a coupon of just 5.625%, it stands as the lowest inaugural coupon in 12 years, so this result makes us very proud. We applied the bond proceeds to fully repay the revolving credit facility, which, together with our cash position of $175 million at March 31st, gives us total available liquidity of $875 million. To sum up, our financial position is very strong, with the financial flexibility to fund organic growth and begin returning capital to shareholders. Speaking of returning capital to shareholders, and before I hand the call back to Dale to wrap things up, I just want once more to give a high-level overview of the dividend policy we announced in Q1, in case some of you missed it on the last call. Introducing a progressive dividend policy at this point reflects both our confidence in the strength and sustainability of our operating cash flows and our confidence in our near-term growth strategy, with the disciplined development of the Phase 1 and EP2 expansion projects.
Our first base quarterly dividend of 5 cents per share kicks in at the close of Q2, and the initial payment should come at some point in Q3. Come 2027, that quarterly base dividend rises to 8 cents per share — put another way, that lifts it to 32 cents per share on an annual basis. After that, starting in 2028, we anticipate adding a variable component on top of the base dividend as well, which would bring it to roughly 40% of our free cash flows. Also, starting in 2027, we might look at repurchasing some shares on an opportunistic basis as part of how we frame capital allocation. That would place Artemis Gold alongside leading peers who strike a balance between reinvesting for growth and returning capital to shareholders. With that, Dale, I'll hand it back to you.
Thanks, Gerrie. As we bring this to a close, the year got off to a strong start, even with that unplanned shutdown in March. Our annual guidance stays as it is, and recovery plans are in place to offset that Q1 production shortfall across the rest of the year. The balance sheet remains strong, and we expect it to support the transformational near-term growth that the Phase 1A and EP2 projects will deliver. Now, next quarter we expect to announce the first dividend payment under our capital allocation framework, as Gerrie noted, and that framework offers a roadmap for returning capital to shareholders in a way that is sustainable and prudent and aligned with both our near-term growth strategy and our long-term goal of maximizing value for shareholders. That concludes our presentation, so I'll hand it back to you, operator, for the Q&A.
The question-and-answer portion of the call starts now. If you'd like to enter the question queue, press star followed by one on your phone's keypad. A tone will sound to confirm your request. Should you be on a speakerphone, lift the handset first before you press any keys. To take your question back out, press star then two. We'll take a brief pause while callers line up. Today's opening question is from Wayne Lam at TD. Go right ahead.
Thanks. Morning, everyone. Maybe my first question is just about how the grade profile looks across the year. Clearly, that high-grade stockpile approach has worked very well from start-up onward. I'm just curious what the mine grades came in at during the quarter. Then, as throughput ramps up, how should we think about process grades over the rest of the year, given that current grades are higher than reserve? When should we begin to expect those mill grades to decline?
Thanks. Appreciate the question, Wayne. I'd say that, as you could see in that photo, our stockpile and the strategy behind it are coming along and performing pretty well. In the first quarter we processed just under 1.6 grams per tonne. On average, and without giving very precise guidance for each quarter, we're looking for roughly the 1.5 grams per tonne level across the year — I think that's likely a touch above where the first quarter averaged out. You should expect grades in the neighbourhood of 1.5 grams per tonne to hold fairly steady over the coming three quarters. As I mentioned earlier, we have a tie-in shutdown planned involving some components of the Phase 1A build near the end of Q3, early Q4, and the downtime from that will offset part of the extra tonnage we anticipate processing once we begin commissioning the 1A facility. Broadly, I think you can view the next three quarters as fairly balanced.
All right, appreciate the context. Perhaps we can shift to the cost outlook for the year. How do you view cyanide usage at this point relative to what was seen before, during the transition material period? And then, is there any update on the size of the sustaining capital budget for the year, considering how much was spent in Q1 compared with the $5 million guidance?
Appreciate the additional questions. Regarding cyanide usage, I'd say we're getting better at how we handle it now that we've moved past that transition material. We're still working through these problems, though we continue to deal with certain agitator and gearbox troubles in our CIL circuit, so we do adjust cyanide consumption levels to get around those mechanical problems that remain in the CIL circuit. We're fixing those. We have a long-term plan in place to solve those problems permanently, and it involves structural and mechanical repairs to those agitators and gearboxes and tanks down the road. Those fixes should roll out progressively. We'll fit them in during mill relines and other downtime. We simply tweak our cyanide levels to get past any downtime on those tanks while we sort those issues out. Overall, I believe we're handling cyanide very, very well at this point, and I think that's helping, as you'd have noticed from our recoveries. We averaged 90.6% in the first quarter, and I'm not claiming we can achieve that every month, but in March we were actually at 92% recovery, yeah, I think things have improved significantly on that front.
Regarding sustaining capital, our guidance remains at $5 million. There may be some confusion about the lease payments we have, and Gerrie, I'm not sure whether you'd like to speak to the lease side of things, but our guidance for sustaining is still within that $5 million range.
Yeah, I completely agree with you on that, Dale. Wayne, so you're aware, lease payments definitely need to be counted in your all-in sustaining cost. We had $7 million in lease payments, which is what we expected. To give you an idea of what that will likely look like over the next 12 months, if you check the note disclosures on commitments in our financial statements, you'll see that for the next 12 months — that is, through the end of Q1 2027 — it's approximately $36 million. Of course, it isn't linear. We haven't received all of our equipment at once, but over the next four quarters or so, we'll spend approximately $36 million, so that gives you a sense of what quarterly lease payments will be going forward, rising to that $36 million total for the 12 months.
For clarity, that figure is incorporated within the all-in sustaining guidance we've issued for this year.
Yes, that's completely captured — no question about it.
Thanks — that context is genuinely useful. So perhaps one final item, returning to capex. Spending on Phase 1A appears somewhat slower, while EP2 is expected to pick up as the year goes on. I'm wondering whether you could elaborate a little on how the projects currently in progress get sorted between expansion capital and sustaining buckets — and regarding the other capital projects, with the $200 million budgeted for this year, is that a one-time outlay, or should we expect it to carry on across the coming few years alongside the EP2 expansion?
Appreciate that, Wayne. Jeremy, you might want to add something here, or Gerrie as well, but regarding the timing of those expenditures, much of the work we've been doing involves engineering and procurement, and those represent important advancements on both Phase 1A and EP2. Our committed costs are considerably higher, yet the cash outlay will be heavily back-end weighted across both projects — Phase 1A and EP2 alike — and we're holding to our capital guidance for the year. If you break it into the buckets, and you pointed to the approximately $200 million at the midpoint of guidance for other growth capital, that's mainly water and tailings infrastructure projects. I think you'll remember that when we issued guidance for the year, we did note there would be additional other growth capital in 2027 and 2028, though we wouldn't be providing guidance on that at this time. More work remains on optimizing the mine plan — determining precisely how much potential acid-generating waste goes behind the tailings dam, how much we'll need to raise it, and the water infrastructure tied to that. There will be, I'd say, an ongoing bucket within future guidance, and we'll provide that guidance annually going forward.
That comes on top of the $110 million for Phase 1A in total capital cost, as well as the $1.44 billion for EP2, which covers only plant expansion capital.
Thanks a lot for taking my questions, and congratulations on a strong quarter.
Much appreciated, Wayne.
Up next, we have a question from Harrison Reynolds at RBC. Your line is open.
Thanks. Morning, Artemis team, and well done on a solid beginning to the year. I appreciate the updates provided so far and it's encouraging to see the progress. I'd like to dig a little deeper on costs — I'm wondering whether you could give some detail regarding your diesel exposure, recognizing that it's lower than perhaps other open-pit operations given the downhill haul and a pit that's still relatively shallow, but I'm curious what's baked into your cost outlook when it comes to oil prices, and what sensitivities you have to higher oil prices. And secondly on that same theme, are you seeing cost pressures on other reagents and inputs such as ammonium nitrate for explosives?
Thanks, Harrison. If you happened to catch the press release we put out yesterday, we did call out that for each $10 rise in the oil price, the effect on our all-in sustaining cost — and this ties to how much fuel we burn — falls somewhere between $5 and $10, and it genuinely hinges on how much material we move from quarter to quarter. We get a benefit from the downhill haul and, I'd say, from the pit being relatively shallow, which is still the case for us as well. Our budget and the cost guidance we originally set assumed an oil price of roughly $70 per barrel. Clearly, we're now in the $90 to $100 range, and it has gone above that, so you can work out the approximate impact yourself. That figure covers fuel consumption only. I think the effects tend to lag, I'd say, when it comes to reagents and explosives, and I'd say the same for transportation costs broadly across all the supplies we bring in. I don't believe we've fully felt the effect of those higher oil prices yet. Of course, oil prices have eased recently, but that's something we're monitoring and watching closely. As you'd have noticed, even though we're keeping our cost guidance for the year, we are trending toward the upper end of that cost guidance.
We have many cost-saving initiatives, through our continuous and business improvement programs, that drive productivities, efficiencies, additional production, and, importantly, just outright opportunities to save on costs. So we'll do everything we can to offset those inflationary pressures driven primarily by the higher oil price.
Thanks. No, that's helpful context. Thank you. Maybe to change topics for a moment, it's good to see the province designate the project, but I was wondering whether you could speak to any outcomes you anticipate from that. One thing that occurs to me is possibly the BC Hydro allocation for EP2, but beyond the 21 million tonnes per annum, would you see any kind of future permitting advantage from this if you began thinking about a Phase 3 expansion?
I'd say there are probably three things that come to mind from this. First, the visibility, profile, and significance within the BC government are now elevated, and so in general that simply gives us added support as we move forward with the EP2 build. There are minor permit amendments that we need. Again, I think this helps that process. As you've rightly pointed out, we're still having discussions with BC Hydro. Those discussions are going very well. Nothing to announce yet on that front, but yeah, we're, I guess, comfortable and confident that we'll resolve any kind of lingering concerns regarding BC Hydro and power availability for EP2 for the longer term.
Thanks a lot. Appreciate you taking my questions, and congrats once more on the quarter.
Thanks for that.
Don DeMarco from National Bank Financial has the next question. You have the floor.
Thanks, operator, and good morning to Dale, Jeremy, and Jeremy too. My first question is for Gerrie. Gerrie, when you look at the hedges that are left, you've laid out how the remaining allocation breaks down by quarter. Do you have discretion over which quarter gets the remaining balance? So that, for instance, you could opportunistically put it into a quarter where the gold price is high, if you decided to. And just to confirm, will every one of the hedges be gone by year-end? Thanks.
Don, good morning, and thanks for asking. The maturity dates on those hedges are fixed by contract. Is there any flexibility? Absolutely, we could look into that. Still, given where gold prices stand at the moment, we believe it makes sense to accept the hit and deliver into these hedges. Production is solid, so our plan is to deliver against the hedges on the schedule, just as you saw in the financial statements and in today's presentation. Apologies, Don — would you mind repeating the second part of your question? It was,
By the end of the year, will every one of the hedges be gone?
No. As our note disclosure shows, we still have certain hedges that need to be delivered into during 2027 and through part of 2028. Delivery of the final hedges occurs in September 2028. I think that disclosure appears in Note 16 of our financial statements, should you wish to consult it for specifics past 2026. As for the voluntary hedges, those will be fully extinguished during this year.
Perhaps I could just build on that point — I do believe there’s a bit more room to maneuver when it comes to the discretionary hedges. As things stand, our intention is to fulfill the remaining 14,000 ounces under the discretionary hedge over the balance of this year. To be clear, we’ll have roughly 100,000 ounces left in the mandatory hedge when this year ends, with about 2/3 of that scheduled for delivery in 2027 and 1/3 during the first half of 2028.
Appreciate that. Phase 1A — nice work, it's 34% done at this point. As we move up toward 8 million tonnes per year by year-end, should we be looking for early gains beyond 6 million tonnes per year starting in Q2 and Q3?
I think I'd tackle that from a few angles. Jeremy, jump in whenever you like — but there are chances to bring forward certain pieces of Phase 1A. The main beneficiary of that will be recovery. That's not to suggest there isn't still room for optimization beyond 6 million tonnes per annum before the Vertimill is commissioned, but the Vertimill is the key equipment that will take us to 8 million tonnes, with throughput rising at that point, which will happen in the fourth quarter. Jeremy, would you like to add anything?
No, thanks, Dale. Morning, Don. I believe we’ve said a few times that some parts of the 1A project can be tied in while operations continue, as we speak. Of course, introducing the new aeration and leach tanks and connecting them electrically is somewhat harder. Things such as oxygen addition, reagent addition, tying in the peripherals around the Vertimill, and clearly erecting the building and getting it covered can all be completed in a — I won’t say ad hoc — but a brownfield sequence. We capitalize on chances to get work done when they arise. Right now, we’re mainly focused on finishing the welding of the tank bases and beginning to erect the tanks. A major focus has been preparing the EP2 footplate, while on the other hand also getting the 1A project ready for handover on a concise timeline.
Don, we don't want this to drag on, so we're putting quite a lot of effort into planning these tie-ins and making sure they don't interfere with the Stage 1 facility.
Appreciate it. Moving on, my last question concerns how we manage the stockpile. Could you remind us of its size? And how large do you expect it to become? Clearly there are considerable advantages when it comes to blending ore, which connects to recovery rates and similar factors. What is your view on whether this is largely lower-grade material that will be processed further out in time, or what approach will you take to reducing it across the coming couple of years, even? Is there perhaps visibility for stronger cash flow should you decide to take a larger share sooner?
No, I appreciate that question, Don. Our current stockpile — and I think I mentioned this in the presentation we just gave — is approaching 20 million tonnes. I think when you combine it with our run-of-mine and coarse ore stockpile, we're just shy of 20 million tonnes, though the stockpile itself is over 19 million tonnes. By the end of this year, that's forecast to grow towards 35 million tonnes, assuming similar low- and medium-grade ore gets added similar to what we're seeing to date. That's a very big stockpile considering we're processing around the 6 million tonne per annum mark. That's for 5 years at the current processing rate. Obviously, we're going to be increasing that processing rate. We don't currently, in the current life-of-mine plan, dip into the stockpile in any material way. The opportunity lies in the mine plan optimization work that we're going to be doing, incorporating our grade control drilling and additional drilling at depth this year. Right now, because we've found so much more material than originally anticipated, and it is low, but importantly also medium-grade material, we're putting anything that's below 1 gram per tonne onto that stockpile, there is above-reserve grade in that stockpile. To date, we have not been able to segregate the higher-grade portions from the lower-grade portions just because there's been too much material.
The foundation pads are not something we can construct. There's water management and other factors we have to work around when we build out pad space for those stockpiles, and we haven't managed to create that space quickly enough to establish segregated stockpiles. That's an area we're actively pursuing and evaluating, including the possibility of going higher, which would open up room for segregation, and every one of those options is under review at the moment. That's where the opportunity lies, Don. If we're able to separate some higher-grade material from the lower-grade portions as we optimize the mine plan, we can draw selectively from that stockpile, and that will contribute to future cash flows as well as improvements to the mine plan profile and milling profile going forward after the EP2 build. That's something we're actively focused on this year.
All right, that sounds like it gives you some flexibility when you need the time. Then just one last quick question. You brought up Phase 3 and touched on it a bit regarding permitting, but what would you be considering when it comes to how large the throughput would be in a Phase 3 scenario? Does that depend on exploration success?
My apologies — I didn’t catch that. Sorry, Don, could you say the question again?
Yeah, so about a hypothetical Phase 3 expansion — that would take things above EP2. What kind of level were you thinking of reaching? It might be too soon to answer, since some work remains to be done on this, but could you give us a sense of the potential size? As things stand, EP2 reaches 21 million tonnes per year — for a Phase 3, are you considering 25, 30? And does moving forward on that depend on exploration success?
Yes, I appreciate that. I think our exploration potential is absolutely phenomenal — and not only across the district, but within the deposit itself at depth. We've completed our first deep hole; assays aren't back yet, but as I said, we're drilling 900 meters below surface. I think, as we optimize for higher gold prices, our current reserve was done at $1,400 gold. As we fold in our grade control and the tonnages we're seeing above what was expected — and in the first year, some of those tonnages come in 30% to 40% higher than we expected on the low- and medium-grade side — incorporating all of that into a new mine plan, a new resource, a new reserve, that's going to be the backbone of our analysis on Phase 3 options. I do think there's potential, ahead of any kind of capital build for Phase 3, to get towards 25 million tonnes just through optimization of EP2 — we'll call it a similar capital-efficient optimization to what we're doing with Phase 1A. We'll be looking at that for EP2, we'll call it EP2A, whatever nomenclature we put to it, but I think that kind of potential exists to get to 25.
When we consider what a Phase 3 might look like—one that goes past evaluating potential beyond 25 million tonnes—I think it's too early to say precisely what that would involve, but something along the lines of an additional third plant is how we're framing it. We genuinely believe this isn't just a mine life lasting decades; we do believe it carries generational potential. As we firm up the resources and reserves through exploration and drilling at depth, I really do think it opens up a lot of opportunity to consider what the next major expansion could be beyond EP2, and that's what we're starting to turn our attention to this year.
Thanks so much — that’s really useful, and I have everything I need. Best of luck for the remainder of the quarter.
Thanks for that, Don.
Andrew Mikitchook from BMO Capital Markets has the next question. Go ahead, please.
Hi, Dale. I appreciate how thorough and patient you've been with everyone's questions before mine. I have two quick ones. Was your supply team able to lock down one more spare gearbox, in addition to the unit that got used up replacing the one that failed?
To give you a fast response on that: yes, there are 2 gearboxes. That ball mill has 2 gearboxes. We hold 2 spares, and importantly, they come with the couplings already attached. Failure of these gearboxes shouldn’t happen. A full root cause analysis is still underway, and at the same time we’re carrying out a complete review of our operating and maintenance procedures. These units shouldn’t fail. Storage and transportation of the gearbox before installation may be a contributing factor. There may be other issues too. We’ll address that. Importantly, we do have 2 spares, 1 for the main gearbox and 1 for the follower gearbox, and with couplings already attached. If we did — and we shouldn’t — but if another failure ever did occur, getting back up and running would be much quicker.
All right. Don posed quite a few questions regarding the stockpile, but perhaps I can keep it to one easy one, and I believe you hinted at this. It is indeed very large, and according to my notes, you mentioned 35 million tonnes by year-end. At what point do you basically run out of room, or have to consider something entirely different from what is presently planned, if these additional tonnes keep getting identified in the grade control?
Thanks for that, Andrew. Well over 100 million tonnes is what our initial study and permit provide for. The stockpile, I believe, was ultimately meant to reach 111 million tonnes under the original plan. Things have shifted a bit, of course, thanks to our Phase 1A and EP2 profiles as we optimized the mine plan. And as we keep optimizing those expansions, whether it ever reaches 111 million tonnes, I'm not certain, though the space is there. The real issue is constructing those stockpile foundations quickly enough. Put simply, ore leaves the pit at a faster rate than we can build the foundations to hold it. We're working to get ahead of that. With winter behind us, we can move faster on it and, hopefully, remove that constraint and begin to segregate.
The issue here isn't a lack of space—it's simply about giving the construction crew the time and room they need to do their work.
Right, precisely. It's the speed at which it's arriving. Reaching nearly 20 million tonnes already at this point wasn't something we had anticipated, so we've genuinely needed to accelerate clearing and constructing storage capacity sooner than our original plans assumed.
Excellent. Thanks once more to both you and the team for those thorough and patient responses. I'll step aside now and let other people pose questions if time still allows.
Appreciate that, Andrew.
That brings our Q&A portion to an end. I'll now hand the conference back to CEO Dale Andres, who has some closing remarks.
Thanks, operator, and I appreciate everyone taking part in today's call once more. I believe we've addressed every question you raised. Should anything else come up, we're here to handle those follow-ups, and we're eager to keep you posted on how things are progressing — and, crucially, on our Phase 1A and EP2 projects down the road. Thank you, everyone.
That concludes the conference call for today. You’re welcome to disconnect your lines now. Thanks for joining us, and enjoy the rest of your day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Artemis Gold Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Artemis Gold Inc. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.